QUESTIONS ANSWERS 12072023.pdf

PDF 76 KB Posted

Attached to
HVAC UNITS WITH REMOVAL & INSTALLATION Federal contract opportunity
Solicitation number
W50S9H-24-Q-0001
Issued by
Department of the Army National Guard

About this file

This document contains questions and answers regarding solicitation number W50S9H-24-Q-0001 from the Department of the Army National Guard for HVAC UNITS WITH REMOVAL & INSTALLATION. The questions and answers provide clarification on the existing HVAC system, specifying that a lead/lag controller is already installed to alternate operation of the two Bard HVAC units. While a Bard heat pump was questioned as an alternative, the solicitation requires the model number identified. The delivery date for the requirement will be adjusted based on the date of contract award, currently 12 weeks for Bard HVAC units.

View the file

Other files for this federal contract opportunity

Other files attached to HVAC UNITS WITH REMOVAL & INSTALLATION, newest first.
File Type Posted
QUESTIONS ANSWERS 12182023.pdf PDF
QUESTIONS ANSWERS 12072023 E2.pdf PDF
ECU PIC - 4.pdf PDF
ECU PIC - 3.pdf PDF
ECU PIC - 1.pdf PDF
ECU PIC - 2.pdf PDF
BRAND NAME JUSTIFICATION - HVAC UNITS.pdf PDF
SF 1449 - W50S9H-24-Q-0001 - DASR HVAC REPLACEMENT.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W50S9H-24-Q-0001

HVAC UNITS WITH REMOVAL & INSTALLATION

QUESTIONS & ANSWERS

Q1. Is there a Lead / Lag controller currently in use to operate the existing Bard HVAC units? If no, would a Lead / Lag Controller for the Bard HVAC units be desirable?. The lead / Lag controller will alternate the operation of the two Bard HVAC units at a preset schedule interval, (e.g. every 7 days) to maintain both Bard HVAC units fully operational with 100% redundancy.

A1. There is already a lead/lag controller installed on the system. The Bard units are connected to preconfigured control panels inside the equipment shelter that provide lead/lag functions and override capabilities.

Q2. Would a Bard Heat Pump be considered in place of the Bard AC unit for this procurement. The Bard Heat Pump is the same size and dimensions as the Bard AC unit, with the exception that the heat pump would be the primary heating and cooling engine and the 9 KW electric heat kit would provide auxiliary heating?

A2. The model number identified is the one required by the DASR program office. Please reference solicitation Brand Name Justification document.

Q3. Current delivery time for Bard HVAC units is 12 weeks. Can the period of performance be extended accordingly?

A3. The Delivery Date for the requirement will be adjusted based on the date the contract is awarded.

Current as of 7 Dec 2023