Q: Will you be providing drawings for us to get footages of the required fiber runs?
A: Attached to this response. Primary buildings are circled in red and core buildings have orange squares.
Q: Are the pathways (underground conduits) for the fiber install already in place?
A: Pathways to be used are existing and fiber will be installed in parallel to systems already in place.
Q: What are the lengths of the runs noted in the SOW?
#172 and 5 core sites identified below utilizing 24 strands of Single Mode fiber.
(1) Building #172 and Building #210
(2) Building #172 and Building #211
(3) Building #172 and Building #219
(4) Building #172 and Building #223
(5) Building #172 and Building #331
#350 and 5 core sites identified below utilizing 24 strands of Single Mode fiber.
(1) Building #350 and Building #210
(2) Building #350 and Building #211
(3) Building #350 and Building #219
(4) Building #350 and Building #223
(5) Building #350 and Building #331 A: Pull distances have not been determined. See attached drawings/map for footage determination.
Q: Can the government provide a base map with the associated buildings identified?
A: Attached to this response.
Q: What connector type is required (SC, LC, ST)?
A: Termination standard requested will be SC-APC.
Q: Do we need to charge you Sales Tax on this project?
A: No. The government cannot pay sales tax. Additionally, no sales tax is collected in the state of Oregon.
Q: Can you provide how much fiber cable is needed for this project?
A: Length of pull will be determined by maps/drawings provided.
Q: The SOW states to procure/install 24 strands of fiber for bldg. #172 and 24 strands for #350. How many pairs of fiber per core site?
A: Request is for 24 strands of fiber pulled from the primary buildings (#172 and #350) to each of the core buildings
Q: Can you provide the make and model of all the switches in each building to spec out the SFPs? Do they all match?
A: Switches have not been procured at this time and will be installed by the government at a later time.
Q: Are there enough SFP slots in each switch to land fiber?
A: Contractor will provide termination in patch panel only. Connections to SFP/Switches will be done by the government at a later time.
Q: By my count, the project will need a minimum of 20 SFPs to run 1 pair of fiber to each building. Is the contractor to provide the SFPs?
A: Contractor will provide termination in patch panel only. Connections to SFP/Switches will be done by the government at a later date.
Q: Is the contractor also to procure the patch panel for each building?
A: Yes.