Amendment 02 - Attach Questions_Answers.pdf
PDF 3 MB Posted
- Attached to
- Multiple Siding and Gutter Repairs Federal contract opportunity
- Solicitation number
- W50S8J22Q0013
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 01 - Extend Due Date.pdf | ||
| W50S8J22Q0013.pdf | ||
| SOW Multiple Repairs to Siding and Gutters.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
F9S3S32111AW01
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to answ er questions that w ere posed in response to the solicitation and site visit. See attached Q&A.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 23-May-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W50S8J22Q0013
X 9B. DATED (SEE ITEM 11)
05-May-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
23-May-2022
CODE
USPFO NY 109 MISSION SUPPORT CONTRACTING
1 AIR NATIONAL GUARD RD
SCOTIA NY 12302-9572
W50S8J 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W50S8J22Q0013
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
Q&A from site visit – Multiple Siding and Gutter Repairs
Q: We are having difficulty matching the siding panels, do you have a manufacturer for the existing panels A: Unfortunately, we do not have records for the paneling types. They are different for each of the three buildings.
Q: Can you clarify the statement in the SOW 1.2.2.1 that states supply one framing metal panel to match the existing? Does that mean the tube steel that supports the siding or is this something else?
A: The framing panel is shown in Photo #4, but it is the piece at the bottom that supports the vertical siding.
Q: Can you provide any more information on any manufacturers of any of the siding that would be of help in matching patterns and colors?
A: Unfortunately, previous records for each building do not supply a tremendous amount of information. For Building 18, we were able to find a warranty (photo below) for a material we believe may have been utilized on the building during a recent (2019) building renovation. This material may not be correct, however. No additional charges to the contract pricing will be allowed if this is the incorrect material. All materials must be submitted to the COR for review and approval prior to purchase. The submittal will require an actual sample for comparison to existing conditions. It is believed that each building has a different panel style and type.
Q: Is it possible to extend the due date 5 business days to allow more time to investigate manufacturers and colors to match existing?
A: Yes, the due date has been extended to 31 May 22 / 12:00 PM EST.
(End of Summary of Changes)