W50S8E20B00020001.pdf

PDF 369 KB Posted

Attached to
Concrete Pads Federal contract opportunity
Solicitation number
W50S8E20B0002
Issued by
Department of the Army New York Army National Guard

View the file

Other files for this federal contract opportunity

Other files attached to Concrete Pads, newest first.
File Type Posted
Attendanace Sheet.pdf PDF
Abstract of Offers Page 2.pdf PDF
Abstract of Offers Page 1.pdf PDF
Attachment 5.pdf PDF
W50S8E20B0002.pdf PDF
Attachment 1.pdf PDF
Attachment 3.pdf PDF
Attachment 2.pdf PDF
Attachment 4.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F9E7CE39134A002

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

A. This Amendment is issued to privide Request for Information 1 to 5.

B. Bid due date is not extended.

C. All FAR provisions and clauses remain unchanged and in full force.

D. This amendment must be acknow ledged, see Block 11 above.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 20-Apr-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W50S8E20B0002

X 9B. DATED (SEE ITEM 11)

02-Apr-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

20-Apr-2020

CODE

USPFO NY 106 MISSION SUPPORT CONTRACTING

FRANCIS S GABRESKI ARPT BLDG 250

WESTHAMPTON BEACH NY 11978-1201

W50S8E 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W50S8E20B0002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

REQUEST FOR INFORMATION 1 TO 5

Q1-The tie downs do you have an approved supplier for these?

A1- The mooring point hardware will be government furnished-contractor installed

Q2-The layout can be done by us, in the excavated area, or do we need a licensed surveyor? There are no grades on the plan, do we follow the existing area?

A2- The contractor would be responsible for layout and mark outs. Follow the existing grade -the government had already contracted this work in which they established the grade well and made the footprint.

Q3-Do we supply the guard shack, and install?

A3- The government will supply the guard shack, contractor is responsible for installing to manufacturers specs attached to SOW.

Q4-We have to install a sub panel in the building, then just supply and install conduit to the foundation, is that correct?

A4-The contractor is to install sub panel in the building supply and install 2 runs of conduit one to be left with drag line and one to have contractor installed electric from sub panel to the guard shack to meet the guard shack specs attached to SOW.

Q5- Can these 3 sites be worked on simultaneously, or complete one, then go on to next?

A5- All sites can we worked on simultaneously as long as prior coordination with the Civil Engineering Squadron.

(End of Summary of Changes)