PERFORMANCE WORK STATEMENT (PWS)
FOR
MCSAT Lead Abatement Services
1.0 General:
1.1 Scope: The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary, except as specified in Paragraph 3.0 as Government Furnished, to perform lead abatement services, as defined in this PWS.
1.1.1 Objectives: Remove lead contamination so that the MCSATs is free of lead contamination. The work includes the cleaning of the interior contact areas, the return duct system to the back of the filter bank, and the cyclone collection point. With this cleanup the site will be considered lead safe and with use non-lead bullets in the future, no further cleaning of lead shall be needed.
1.2 Background: The MCSATs is an indoor shooting range. Approximately 7 years ago, lead bullets were used in this indoor range. Since then “green” bullets have been used.
The MCSATs was never abated when the change from lead to “green” bullets occurred.
1.3 Period of Performance (PoP): The Period of Performance shall be 30 days.
1.4 General Information:
1.4.1 Place and Performance of Services: The contractor shall provide services between the hours of 0630-1700 on Monday – Friday, except on recognized US holidays or when the Government facility/installation is closed due to local or national emergencies, administrative closings, or similar Government-directed facility/installation closings. Performance shall be at 1776 National Guard Way, Reno, Nevada, Building MCSAT. The contractor shall at all times maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS when the Government facility/installation is not closed for the above reasons. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential. Teleworking is not authorized.
1.4.1.1 Telework: The Government will not permit the contractor to telework in support of this requirement. In furtherance of Continuity of Operations Planning (COOP), a telework program may be enacted to ensure that the Government's mission-critical operations stay operational during times of national emergency or incidents of national significance. Telework shall be at no additional cost to the Government.
1.4.1.2 Unscheduled gate closures by the Security Police may occur at any time causing all personnel entering or exiting a closed installation to experience a delay.
This cannot be predicted or prevented. Contractors are not compensated for unexpected closures or delays. Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.
1.4.1.3 The contractor’s employees shall become familiar with and obey the regulations of the installation; including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All contractor employees shall carry proper identification with them at all times, and shall be subject to such checks as may be deemed necessary. The contractor shall ensure compliance with all regulations and orders of the installation, which may affect performance. The Government reserves the right to direct the removal of an employee from Government property or revoke access to Government systems for misconduct, security reasons, or any overt evidence of communicable disease. Removal of contractor employees for reasons stated above does not relieve the Contractor from responsibility for total performance of this contract.
1.4.2 Recognized Holidays: The following are recognized United States (US) holidays.
The contractor shall not perform services on these days:
1.4.3.1 New Year’s Day: January 1st
1.4.3.2 Martin Luther King, Jr.’s Birthday
1.4.3.3 President’s Day
1.4.3.4 Memorial Day
1.4.3.5 Independence Day: July 4th
1.4.3.6 Labor Day
1.4.3.7 Columbus Day
1.4.3.8 Veteran’s Day: November 11th
1.4.3.9 Thanksgiving Day
1.4.3.10 Christmas Day: December 25th
1.4.3 Reserved.
1.4.4 Quality Assurance (QA): The Government will evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government will do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and acceptable quality level(s) or defect rate(s).
1.4.5 Access and General Protection/Security Policy and Procedures. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, Headquarters Air Force (HAF) and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
1. The contractor shall obtain base identification and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished, contractor identification badges while visiting or performing work on the installation.
2. The contractor shall submit a written request on company letterhead to the contracting officer listing the following: contract number, location of work site, start and stop dates, and names of employees and subcontractor employees needing access to the base. The letter will also specify the individual(s) authorized to sign for a request for base identification credentials or vehicle passes. The contracting officer will endorse the request and forward it to the issuing base pass and registration office or Security Forces for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver s license, current vehicle registration, valid vehicle insurance certificate, and [insert any additional requirements to comply with local security procedures] to obtain a vehicle pass.
3. During performance of the contract, the contractor shall be responsible for obtaining required identification for newly assigned personnel and for prompt return of credentials and vehicle passes for any employee who no longer requires access to the work site.
4. When work under this contract requires unescorted entry to controlled or restricted areas the contractor shall comply with AFI 31-101, Integrated Defense.
5. Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.
6. Failure to comply with these requirements may result in withholding of final payment.
1.4.5.1 Reserved
1.4.5.2 Reserved
1.4.5.3 Awareness Training (AT) Level 1: All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, and controlled access areas shall complete AT Level 1 training within 30 calendar days after contract start date and within 30 calendar days of new employees commencing performance. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee to the COR within 15 calendar days after completion of training by each employee or subcontractor personnel. AT Level 1 awareness training is available at the following website:
https://jko.jten.mil/courses/atl1/launch.html.
1.4.5.4 Reserved
1.4.5.5 Communications Security/Information Technology (COMSEC/IT) Security: All communications with DoD organizations are subject to COMSEC review. All telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. DoD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DoD organizations. Therefore, the contractor is advised that any time contractor personnel place or receive a call they are subject to COMSEC procedures. The contractor shall ensure wide and frequent dissemination of the above information to all employees dealing with DoD information. The contractor shall abide by all Government regulations concerning the authorized use of the Government's computer network, including the restriction against using the network to recruit Government personnel or advertise job openings.
1.4.5.6 Through 1.4.5.14 Reserved
1.4.6 Physical Security. The contractor shall safeguard all Government property provided for contractor use. At the close of each work period, Government facilities, equipment and materials shall be secured.
1.4.7 Special Qualifications: The contractor shall ensure all employees possess all required licenses for lead abatement used in the performance of this contract. This does not include education or other qualifications for the position in which the contractor employee is performing, dress codes, or other information. (NOTE: The Government does not provide training to contractors. Contractors must ensure that any personnel performing under a contract are fully trained, licensed, certified, and otherwise qualified to provide services.)
1.4.8 Post Award Conference/Periodic Progress Meetings: The contractor agrees to attend any post award conference convened by the KO in accordance with FAR 42.5.
The KO, COR and other Government personnel, as appropriate, may meet periodically with the contractor to review the contactor’s performance. At these meetings, the KO will apprise the contractor of how the Government views the contractor’s performance and the contractor shall apprise the Government of problems, if any, being experienced.
The contractor shall resolve outstanding issues raised by the Government. Contractor attendance at these meetings shall be at no additional cost to the Government.
1.4.9 Contract Manager (CM): The contactor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO.
The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the COR to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.
1.4.10 Identification of Contractor Employees: All contractor personnel attending meetings, answering Government telephones and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government employees. The contractor shall ensure that all documents or reports produced by contractor personnel are suitably marked as contractor products or that contractor participation is appropriately disclosed. The contractor’s status as a “contractor” shall be predominantly displayed in all correspondence types (to include signature blocks on e-mail) and dealings with Government or non-Government entities. Contractor personnel shall wear identification badges distinguishing themselves as such. The badges shall have the company name, employee name and the word “contractor” displayed.
1.4.11. Combating Trafficking in Persons: The United States Government has adopted a zero tolerance policy regarding trafficking in persons. Contractors and contractor employees shall not engage in severe forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. The contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at
FAR 22.17.
1.4.12 Reserved
1.4.13 Reserved
1.4.14 Organizational Conflicts of Interest (OCI): The contractor and subcontractor personnel performing services under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent OCIs, as defined in FAR Subpart 9.5. The contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO. In the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may impose other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.
1.4.15 Reserved
2.0 Definitions and Acronyms:
2.1 Definitions:
2.1.1 Contractor: A supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.
2.1.2 Defective Service: A service output that does not meet the standard of performance associated with the PWS.
2.1.3 Deliverable: Anything that can be physically delivered and includes non-manufactured things such as meeting minutes or reports.
2.1.4 Key Personnel: Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.
2.1.5 Physical Security: Actions that prevent the loss or damage of Government property.
2.1.6 Quality Assurance: The Government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
2.1.7 Quality Assurance Surveillance Plan (QASP): An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.
2.1.8 Quality Control: All necessary measures taken by the Contractor to ensure that the quality of an end product or service shall meet contract requirements.
2.1.9 Subcontractor: One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.
2.2 Acronyms:
AEI Army Enterprise Infostructure AR Army Regulation AT/OPSEC Antiterrorism/Operational Security BI Background Investigation CM Contract Manager COR Contracting Officer Representative DA Department of the Army DD254 Department of Defense Contract Security Classification Specification DFARS Defense Federal Acquisition Regulation Supplement DoD Department of Defense EPA Environmental Protection Agency FAR Federal Acquisition Regulation GFP/M/E/S Government Furnished Property/Material/Equipment/Services HQDA Headquarters, Department of the Army HSPD Homeland Security Presidential Directive IA Information Assurance IS Information System(s) KO Contracting Officer NGB National Guard Bureau OCI Organizational Conflict of Interest OSHA Occupational Safety and Health Administration PII Personally Identifiable Information PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement RCRA Resource Conservation Restoration Act QA Quality Assurance QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program SCR Service Contract Reporting SSN Social Security Number TE Technical Exhibit USD(I) Under Secretary of Defense for Intelligence
3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S):
The Government will provide the property, material, equipment, and/or services listed below solely for the purpose of performance under this contract:
3.1 Property: The Government will furnish the necessary workspace for the contractor to perform services outlined in this PWS to include desk space, telephones, computers and other items necessary to maintain an office environment. None
1266720617N Cross-Out
3.2 Materials: None
3.3 Equipment: None
3.4 Services: None
3.5 Utilities: All utilities in the facility will be available for the contactor’s use in the performance of this contract. The contractor shall instruct employees in utilities conservation practices. The contractor shall operate under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount.
4.0 Contractor Furnished Property, Materials, and Equipment (CFP/M/E):
4.1 General: Except for those items specifically stated to be Government-Furnished in Paragraph 3.0, the contractor shall furnish everything required to perform these services as indicated in Paragraph 1.1.
4.2 Reserved
4.3 Reserved
5.0 Requirements: The contractor shall:
5.1 Only licensed lead abatement Contractor will perform the abatement. All workers must be EPA certified. The Contractor will provide to the COR a copy of the lead license for each employee that will be involved in the removal of the lead.
5.2 The Contractor will clean all lead contaminated material to ensure clearance level of <10 micrograms per square foot.
5.3 The Contractor will provide all clearance, testing, and analytical results to the COR.
5.4 The Contractor is required to furnish all labor, equipment, materials, personal air monitoring equipment, laboratory fees, disposal permits / fees, and lead liability insurance necessary to perform the work.
5.5 The Contractor will properly dispose of all waste in accordance with local, state, and federal laws and regulations.
5.6 The Contractor will provide all disposal trip tickets to the COR within 10 days of disposal.
5.7 A third party subcontractor will be required to perform the following tasks:
5.7.1 Provide a copy of their lead license to the COR.
5.7.2 Provide final clearance inspection and testing. A copy of the final clearance inspection and testing will be provided to the COR.
5.7.3 Lead Range Contact Zone Dust Removal: This work includes the end of each of the shooting lanes from where the bare concrete floor begins to the contact end of the lane and includes the floor, sides, and top surfaces with the work conducted in a Regulated Area with barriers, signage and a personal Decontamination Station in place, per the OSHA Lead in Construction regulation requirements in 29 CFR 1926.62. The lead cleanup and removal in these areas should start on the top and back of the impact zone, then continue to clean out toward the front. At the conclusion of the cleaning there should be no visible dust on any surface in the Regulated Area. The cleaning can be with special wipes, HEPA vacuuming and/or other techniques to remove all dust. This work also includes removing the beige contact sheet at the end of the range that the bullets impact. See attached photos.
5.7.4 Lead Range Contact Zone Encapsulation: This work includes encapsulating the concrete floor and the end contact steel plates with a high-quality lead specific encapsulant such as Fiberlock LBC (Lead Barrier Compound) or equal such that an even coat exists on all concrete floor and metal impact surfaces. The result will be encapsulation that locks any remaining lead dust in place as a permanent shield that can be disturbed by bullet contact, however, will not allow general dispersion of dust locked in cracks or indentions in the surfaces. This work also includes encapsulating the rubberized mats along the sides of the lanes in the same area with Fiberlock Lead Shield or equal. The result of this is surface encapsulation that will not allow easy dispersion of minor lead dust present in the mats.
5.7.5 Roof Duct System Cleaning: This work includes cleaning the return air duct system to the filter bank such that the result is no lead in the air when it is tested with the system on and testing at the filter bank location. The cleaning shall be conducted by a specialized duct cleaning that is aggressive and that includes capturing cleaning return air in a HEPA filtration system. The cleaning also includes removal, disposal, and replacement of the filters at the filter bank.
5.7.6 Cyclone Compartment Cleaning: This work includes cleaning the Cyclone Compartment at the ground level including the catch basin with the bullet debris and the compartment surrounding the cyclone such that no lead dust remains. This work shall be conducted in a mini-containment surrounding each cyclone compartment and with use of dust cleaning approaches similar to the shooting lanes. When no dust is visible the work also includes encapsulating the surfaces with Fiberlock Lead Shield or equal.
5.8 Reserve
6.0 Applicable Publications: Publications applicable to this PWS are listed below:
Publication (Chapter/Page)
Date of Publication
Mandatory or Advisory
Website
Federal Acquisition Regulation https://www.acquisition.gov/?q=browsefar Defense Federal Acquisition
Regulation Supplement http://www.acq.osd.mil/dpap/dars/dfarspgi/current/in dex.html or https://www.acquisition.gov/dfars DoDM 1000.13-M-V1
DoD Identification (ID) Cards (Enclosure 2, paragraph 3.b)
01/23/2014 (Change 1:
07/28/2020) http://www.esd.whs.mil/Directives/issuances/dodm
Federal Information Processing Standards (FIPS) Publication 201-2 Personal Identity Verification (PIV) of Federal Employees and Contractors
(paragraph 9)
August 2013 http://nvlpubs.nist.gov/nistpubs/FIPS/NIST.FIPS.201 -2.pdf
DoDM 5200.2 Procedures for the DoD Personnel Security Program
(PSP)
04/03/2017 https://www.esd.whs.mil/Directives/issuances/dodm/
DoDI 5400.11 Department of Defense Privacy and
Civil Liberties Programs
01/29/2019 https://www.esd.whs.mil/Directives/issuances/dodi/
DoD 5400.11-R Department of Defense Privacy
Program
05/14/2007 https://www.esd.whs.mil/Directives/issuances/dodm/
DoD 5220.22-M National Industrial Security Program
Operating Manual (NISPOM)
02/28/2006 (Change 2:
05/18/2016) https://www.esd.whs.mil/Directives/issuances/dodm/
AFI 10-245
Antiterrorism
03/28/2013 (Certified current
03/30/2017) https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&catID=1&series
=-1&modID=449&tabID=131
AFI 31-101
Security Forces Standards and
Procedures
08/18/2020 https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&catID=1&series
=-1&modID=449&tabID=131
AFMAN 31-113
Security Forces Standards and Procedures
03/05/2013 Change 1:
12/02/2015 https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&catID=1&series
=-1&modID=449&tabID=131
AFI 10-701
Operations Security 7/24/2019 (Change 1:
06/09/2020) https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&catID=1&series
=-1&modID=449&tabID=131
6.1 Applicable Forms: Forms applicable to the PWS are listed below:
Form Date Website
NA
TECHNICAL EXHIBIT 1
Performance Requirements Summary (PRS)
This PRS includes performance objectives the Government will use to determine contractor performance and will compare contractor performance to the Acceptable Quality Level (AQL).
Performance
Objective Performance Standard Acceptable Quality
Levels (AQL) Surveillance Method / By
Whom
Cleaning of lead contaminated
MCSAT
Lanes and HVAC will be cleaned of lead to <10 micrograms per square foot.
See examples below:
<5 mg/L Visual surveillance method conducted by the COR.
Final clearance testing
The contractor shall provide after abatement.
<5 mg/L Review of the clearance testing by the COR.
TECHNICAL EXHIBIT 2
Deliverables Schedule
PWS Reference / Deliverable Title
Frequency Number of Copies
Medium/Format Submit To
1.4.10 Identification
Media
Return within 14 days of employee’s departure from contract performance.
Original(s) Hard Copy KO
1.4.7.1 Base
Access
One time each: within 7 days of start.
1 Electronic COR
5.1 Provide lead
license for each employee
Within 10 days of Notice to Proceed
1 Electronic COR
5.3 Analytical
Results of
Abatement process
As performed 1 Electronic COR
5.7 Waste Disposal
Trip Tickets
As performed 1 Electronic or hard copy
COR
5.8.1 Third party
abatement
Contractor license.
Within 10 days of Notice to Proceed
1 Electronic COR
5.8.4 Final
Clearance Testing by third party
At the end of the project 1 Electronic COR
TECHNICAL EXHIBIT 3
Estimated Workload Data
This information is provided for historical background only. It is not a guarantee of workload quantities.
ITEM NAME ANNUAL ESTIMATED
QUANTITY
1 Lanes 12 Lanes 2 Cyclone filter area 12 closets 3 Ventilation area 12 vents 4 Analytical Results pre-remediation NA
1 Photo of a Lane at MCSAT – All Lanes are exactly the same.
2 Cyclone Filter closet area. There are two cyclone filters per closet.
3 Ventilation – Located on roof.
Analyst: Baird, Marti
Test Method: SW846/M3050B/7000B
Lead Wipe Analysis µg Pb Calculated Sample
Sample Description In Sample Area Units RL Results Units
21026357 - 1 ANG-GR1 / Concrete Floor, Near End Lane
830 1.000 Sq. Ft. 10 830.2 µg/ft2
21026357 - 2 ANG-GR2 / Side Wall Matt, Middle Lane 30 1.000 Sq. Ft. 10 29.6 µg/ft2 21026357 - 3 ANG-GR3 / Air Duct Case, Near Entry < 10 1.000 Sq. Ft. 10 <10 µg/ft2 21026357 - 4 ANG-GR4 / Floor Matt, Near Shooting
Station < 10 1.000 Sq. Ft. 10 <10 µg/ft2
Method Reporting Limit < 10 µg/wipe
Signature:
Date: 6/2/2021 Date: 6/2/2021
Sample ANG-GR1 received with 3 wipes in baggie.
Reviewed:
21-134Project Number:
P.O. Number:
Project Name: ANG Indoor Range
5/27/2021Collected Date:
5/28/2021 10:20:00 AMReceived Date:
6/7/2021 9:16:38 AM
21026357 SanAir ID Number
FINAL REPORT
Wise ConsultingName:
Address: 5400 Mill Street
Suite A
Reno, NV 89502
775-827-2717Phone:
4. Analytical Results – Pre-Remediation