W50S8A23Q0006
157 ARW Portable Toilets
AMENDMENT 1
Paragraph 5.0 of the PWS is hereby changed:
FROM:
5.0 Requirements- The contractor shall: The contractor shall provide 160 standard portable toilets, and
40 handicapped accessible portable toilets. Contractor will also provide 50 four-person hand-washing/sanitation stations (or a KO approved alternative to meet crowd capacity) to accompany the portable restrooms. Technical Exhibit 1 gives generic examples of an expected product. The exact location of each porta john shall be provided at the time of contract award but will remain subject to change. The Government shall inform the contractor of any change within one week prior to the start of the period of performance.
TO:
5.0 Requirements- The contractor shall: The contractor shall provide 175 standard portable toilets, and
25 handicapped accessible portable toilets. Contractor will also provide 50 four-person hand-washing/sanitation stations (or a KO approved alternative to meet crowd capacity) to accompany the portable restrooms. Technical Exhibit 1 gives generic examples of an expected product. The exact location of each porta john shall be provided at the time of contract award but will remain subject to change. The Government shall inform the contractor of any change within one week prior to the start of the period of performance.
Paragraph 5.1 of the PWS is hereby changed:
FROM:
5.1 The contractor shall provide and maintain 160 standard portable toilets, Contractor will keep the portable toilets stocked with sufficient quantities of toilet paper and hand sanitizer throughout the event. Contractor will empty and clean/service all portable toilets after 1800hrs on 9 September 2023 to prepare for the event’s second day.
TO
5.1 The contractor shall provide and maintain 175 standard portable toilets, Contractor will keep the portable toilets stocked with sufficient quantities of toilet paper and hand sanitizer throughout the event. Contractor will empty and clean/service all portable toilets after 1800hrs on 9 September 2023 to prepare for the event’s second day.
Paragraph 5.2 of the PWS is hereby changed:
FROM:
5.2 The contractor shall supply 40 ADA compliant portable toilets Contractor will keep the portable toilets stocked with sufficient quantities of toilet paper and hand sanitizer throughout the event.
Contractor will empty and clean/service all portable toilets after 1800hrs on 9 September 2023 to prepare for the event’s second day.
TO:
5.2 The contractor shall supply 25 ADA compliant portable toilets Contractor will keep the portable toilets stocked with sufficient quantities of toilet paper and hand sanitizer throughout the event.
Contractor will empty and clean/service all portable toilets after 1800hrs on 9 September 2023 to prepare for the event’s second day.
Paragraph 5.2.1 of the PWS is hereby changed:
FROM
5.2.1 The contractor will install the restrooms to the locations on exhibit 3 beginning at 0800hrs on 7
September 2023, with all units in place no later than 1200hrs (noon) on 8 September 2023. A staging area within Pease ANGB but outside the show area can be facilitated up to 10 days prior to the Period of
Performance, if requested by the contractor.
TO:
5.2.1 The contractor will install the restrooms at locations that will be assigned and provided to the contractor after award beginning at 0800hrs on 7 September 2023, with all units in place no later than
1200hrs (noon) on 8 September 2023. A staging area within Pease ANGB but outside the show area can be facilitated up to 10 days prior to the Period of Performance, if requested by the contractor.
Paragraph 5.3.1 is hereby changed:
FROM
5.3.1 The contractor will install the hand-washing stations to the locations on exhibit 3 beginning at
0800hrs on 7 September 2023, with all units in place no later than 1200hrs (noon) on 8 September 2023.
A staging area within Pease ANGB but outside the show area can be facilitated up to 10 days prior to the
Period of Performance, if requested by the contractor.
TO
5.3.1 The contractor will install the hand-washing stations at locations that will be assigned an provided to the contractor after award beginning at 0800hrs on 7 September 2023, with all units in place no later than 1200hrs (noon) on 8 September 2023. A staging area within Pease ANGB but outside the show area can be facilitated up to 10 days prior to the Period of Performance, if requested by the contractor.
***NOTE: a reference to paragraph “5.1.2 Reserved” between paragraph 5.3.1 and paragraph 6.0 is struck from the PWS****
File details come from the government source that posted it. Updated .