RFI 2 - Electrical Panel.pdf
PDF 177 KB Posted
- Attached to
- REPLACE ELECTRICAL PANEL Federal contract opportunity
- Solicitation number
- W50S8221R0009
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFI - Electrical Panel 25 Aug 2021.pdf | ||
| BLDG2120 Power Plans And Panel Schedules 04-01-95 PLTE-2.pdf | ||
| Sign In Sheet.pdf | ||
| Pre-proposal slides W50S8221R0009.ppt | PPT presentation | |
| PJMS 172027_SOW_Electrical_Panelat Base Support Final.docx | DOCX document | |
| WF 113 - Installation Access Application.pdf | ||
| W50S8221R0009.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The scope of work highlights the following:
*The contractor is to furnish and install a new 200Amp sub-panel in the same location of sub-panel EPA.
* Contractor is to furnish and install new 200Amp sub-panel in the same location of sub-panel EPB. (80amp existing)
If we are to furnish a new 200Amp Main Breaker for EPA panel and then run a 200 amp feeder to the new EPB sub panel, we would not have enough capacity to power the existing loads in the EPA panel.
Question: Shouldn't' we be upgrading the EPA panel above 200amps to handle the existing loads there and the new 200 amp sub-panel downstream?
Answer: Install 200 AMP panel per SOW.