Solicitation W50S7L20Q0002 - JKSE 192403, Upgrade/Maintain Recreational Area

Question and Answers as of 13 August 2020

1. Question: What is the water line pressure?

Answer: We have been seeing static pressures up here of between 51-53 psi.

2. Question: Asphalt work around the electrical room?

Answer: It is just around the electrical room and not the switching gear.

3. Question: Your bid docs show 3 week engineering lead time and 7 weeks fabrication. Our current engineering lead time is 4 weeks and fabrication is 9-10 weeks after drawings are approved. We’ve had an extremely busy spring/summer and this is our busiest time of year so we cannot commit to the lead times on the bid docs. Can you extend the lead times on the project?

Answer: We will work with all interested parties after award to accommodate lead times.

4. Question: Did you want the 26-gauge exposed fastener metal roofing, or 24-gauge standing seam metal roofing?

Answer: 26-gauge exposed fastener is spec’d

5. Question: The estimate is $100-250,000. This project will probably be more than that. Does the government have the money?

Answer: The government currently has funds for the independent government estimate, which falls within the project magnitude of $100,000-$250,000.

6. Question: There is a trench detail for water pipes on 1/C005, do you have a trench detail for the electrical(from building 30 to panel LP)(from LP to Pavilion)(from LP to food truck receptacles)?

Answer: Specification section 26 05 00 is reference on detail.

7. Question: Will you require a ¾” x 10’ cu clad ground at panel LP?

Answer: Yes.

8. Question: 26 05 26 2.2 C. 2. calls for exothermic connections. May we use compression?

9. Question: 26 05 26 3.3 B. Should this be deleted, as these sections do not really apply. You have it covered under 26 05 26 3.3 C.