STATEMENT OF WORK
FOR
W31P4Q-19-R-0031 Switchblade Aerial Munition System
Hardware Procurement
Prepared by
CLOSE COMBAT WEAPONS SYSTEMS
17 July 2019 Version 1.0
Switchblade Statement of Work
STATEMENT OF WORK
Switchblade Aerial Munition System
TABLE OF CONTENTS
1.0 SCOPE……………………………………...……………………………………………4
2.0 APPLICABLE DOCUMENTS …………………………..………………………….…4
3.0 DESCRIPTION OF HARDWARE…………………………………..…………………4
3.1 SPARE Kit……………………………………………………………………………….4
4.0 EQUIPPING……………………………………………………………………………...5
4.1 NOTIFICATION TO DCMA……………………………………………………………,5
4.2 PACKAGING…………………………………………………………………………….5
4.2.1 PACKAGING DATA……………………………………………………………………5
4.2.2 PERFORMANCE ORIENTED PACKAGING………………………………….…….5
5.0 PRODUCTION SERVICES…………………………………………………………….5
5.1 SOFTWARE UPDATES………………………………………………………………..5
5.2 RESERVED
5.3 SYSTEMS ENGINEERING SUPPORT………………………………………………6
6.0 PRODUCT ASSURANCE………………………………………………………….…..6
6.1 MANUFACTURING DOCUMENTATION…………………………………………….6
6.2 PROGRAM SPECIFICATION DOCUMENTS……………………………………….6
6.3 ACCEPTANCE TEST PROCEDURES………………………………………………6
6.4 TEST STATIONS AND PROCEDURES……………………………………………..6
6.4.1 TEST STATION VALIDATION………………………………………………………..7
7.0 PROGRAM MANAGEMENT………………………………………………………….7
TABLE OF CONTENTS (Cont.)
7.1 CONTRACTOR MANPOWER REPORTING……………………………………….7
7.2 TRAVEL………………………………………………………………………………….8
8.0 CONFIGURATION MANAGEMENT………………………………………………….8
8.1 CONFIGURATION OF SWITCHBLADE QUALIFIED PRODUCT BASELINE….8
8.2 CONFIGURATION CONTROL………………………………………………………..9
8.3 DATA ASSERTIONS…………………………………………………………………...9
9.0 LOT ACCEPTANCE TESTING………………………………………………………..9
10.0 SAFETY………………………………………………………………………..……….10
11.0 SECURITY REQUIREMENTS……………………………………………………….10
12.0 AT/OPSEC ADDDITIONAL REQUIREMENTS
13.0 CYBER SECURITY REQUIREMENTS……………………………………………..13
13.1 AUTHORIZATION TO OPERATE…………………………………………………..13
14.0 HAZARDOUS MATERIAL MANAGEMENT .…………………………………….13
1.0 SCOPE
This Statement of Work (SOW) defines the effort to furnish the personnel, facilities, equipment and materials necessary to build and deliver Switchblade equipment, and the technical and administrative requirements to manage this Program.
2.0 APPLICABLE DOCUMENTS
Applicable top-level documents are contained in the Document Summary List (DSL), reflected in Section J to this contract, by number, title, and date. The document versions specified in the DSL take precedence over the generic references (without revision letters) cited in this SOW.
3.0 DESCRIPTION OF HARDWARE
The contractor, as an independent contractor and not as an agent of the Government, shall furnish all the personnel, facilities, equipment, and materials necessary to perform the following: build and deliver as defined in the Contract Line Item Number (CLIN) structure for the following Configuration Items (CIs):
Switchblade Configuration Items AV Part Number Contractual Name Item Description
62883-DDL All Up Round (AUR) ASSY, ALL UP ROUND, DDL
78030 Inert Training Vehicle Lite (ITV
Lite) ASSY, FLIGHT TRAINING, ITV DDL (Lite) 68125- DDLM1 Fire Control Unit (FCU) M1 ASSY, SYSTEM, FCU WITH TOUGHBOOK, M1 DDL 68125- DDLM2 Fire Control Unit (FCU) M2 ASSY, SYSTEM, FCU WITH TOUGHBOOK, M2 DDL
68129-DDL Training Simulator (T-Sim) SIMULATOR, TRAINING, SYSTEM, SBLD, DDL, CCWS 68021 Tactical Battery Charger ASSY, TOP, CHARGER, TACTICAL BATTERY 84286 Multi-Pack Launcher (MPL) ASSY, TOP-LEVEL KIT, MULTIPACK LAUNCHER, MPL 73407 Modular Battery Payload (MBP) ASSY, PAYLOAD, MODULAR BATTERY
56500-005 Modular Battery Payload
Charger ASSY,UNIVERSAL BATTERY CHARGER, SBLD
74483 Piglet Launcher-Pneumatic
TOP, ASSEMBLY, TACTICAL LAUNCHER
SIMULATOR, PNEUMATIC
68969 Catch Net ASSY, TOP, CATCH NET
3.1 SPARE KIT
The contractor shall provide spare kits as described in Attachment 004, Special H Provisions.
4.0 EQUIPPING
The contractor shall assist in the development of a delivery schedule to equip the Government. The contractor shall support the Outside Continental United States (OCONUS) equipping effort by preparing, packaging, and shipping all items procured as part of this SOW to a Government facility. Shipping locations will include but not limited to Redstone Arsenal, AL, Norfolk Naval Air Station, VA, and Dover Air Force Base, DE.
4.1 Notification to DCMA
The contractor shall provide notification to Defense Contract Management Agency (DCMA) representatives seven (7) business days prior to expected completion of CI production or the intended date of DCMA inspection.
4.2 Packaging
4.2.1 Packaging Data The contractor shall prepare packaging data in accordance with (IAW) DI-PACK-80120 (A002) and DI-PACK-80121 (A003) for Government hardware delivered under this contract and to include storage and transportation.
4.2.2 Performance Oriented Packaging The contractor shall perform testing and acquire data necessary to support compliance with the Performance Oriented Packaging (POP) requirements of hazardous materials as defined in Title 49, Code of Federal Regulations. The contractor shall prepare a POP test report IAW DI-PACK- 81059 (A008). Preservation, packaging, and packing for shipment shall be in accordance with good commercial practices and adequate to ensure acceptance by a common carrier and safe transportation at the most economical rate.
5.0 PRODUCTION SERVICES
5.1 Software Updates
The contractor shall provide updates to fielded equipment with the latest Government approved software including operating system patches, tactical and mapping software IAW DI-IPSC-81756 (A022) (Software Documentation)
5.2 RESERVED
5.3 Systems Engineering Support
The contractor shall provide systems support to assess and ensure Switchblade reliability and safety as directed by the LAT procedures. The contractor shall provide Field Incident Reports to include results of the contractor’s assessments IAW DI-MISC- 80508 (A010).The contractor shall perform configuration management reviews and provide systems integration support through completion of hardware delivery. The contractor shall prepare and maintain a Flight Log IAW DI-MISC-80508 (A011) of Switchblade related training, live fire shots associated with rounds under Close Combat Weapon System (CCWS) cognizance and supporting CCWS related CONUS/OCONUS operations. The contractor shall ensure interoperability between all fielded versions of CIs.
6.0 PRODUCT ASSURANCE
6.1 Manufacturing Documentation
The contractor shall provide access to the generated, maintained, and implemented manufacturing planning documentation for the production baseline for Government review upon request. The contractor shall prepare the manufacturing plan to include the top level drawings of each component, operation process charts depicting the production flow, and production process planning such as work instructions, Manufacturing Engineering Standard Operating Procedures and operator instructions IAW DI-MGMT-81889 (A018).
6.2 Program Specification Documents
The contractor shall prepare program unique specification documents IAW DI- SDMP-81493 (A015) and MIL-STD-961 to support production reviews, failure/fault analysis, quality/configuration management, fault trees, and Work Breakdown Structure (WBS) layout.
6.3 Acceptance Test Procedures
The contractor shall prepare an updated ATP IAW DI-NDTI-80603 (A020).The Government reserves the right to require revalidation of any ATP changed/modified by the contractor. If revalidation is required, the contractor shall ensure the revalidation is successfully accomplished prior to further final acceptance testing use of the ATP.
6.4 Test Stations and Procedures
The Government will validate test stations and procedures used for acceptance or production of subassemblies and major components. The contractor shall control the test station software and hardware (HW/SW) configurations. The contractor shall notify the Government a minimum of 30 days prior to making any HW/SW changes to validated test stations. The Government reserves the right to require revalidation of any test station changed/modified by the contractor, including Government visits and oversight. If revalidation is required, the contractor shall ensure the revalidation is successfully accomplished prior to further final acceptance testing use of the test stations.
6.4.1 Test Station Validation
The Government will validate test stations and procedures used for acceptance or production of subassemblies and major components by subcontractors. The prime contractor shall control the test station software and hardware configurations. The prime contractor shall notify the Government prior to making any HW/SW changes to validated subcontractor test stations. The Government reserves the right to require revalidation of any test station changed/modified by the subcontractor, including Government visits and oversight. If revalidation is required, the prime contractor shall ensure the revalidation is successfully accomplished prior to further final acceptance testing use of the test stations.
7.0 PROGRAM MANAGEMENT
The contractor shall perform program management and reporting tasks required to successfully execute this SOW, program status reporting (technical and cost), and coordination with the Government customer through completion of hardware delivery.
The contractor shall prepare cost reports IAW DI-FNCL-80912 (A007), a quality assurance program plan IAW DI-QCIC-81794 (A009) and ISO 9001, and a program management plan IAW DI-MGMT-80004 (A001). The contractor shall prepare and maintain an Integrated Master Schedule (IMS) IAW DI-MGMT-81861 (A012) that shall contain a production schedule.
7.1 Contractor Manpower Reporting
The Office of the Assistant Secretary of the Army (Manpower & Reserve Affairs) operates and maintains a secure Army data collection site to capture all direct labor hours and direct labor dollars incurred by prime contractors and subcontractors required for performance of this contract. The prime contractor shall provide the information addressed in the contractor user guide at the following web address:
https://www.ecmra.mil. The prime contractor shall ensure that subcontractors provide the information addressed in the subcontractor user guide at the web address provided above.
The required information includes Contract Number; Delivery or Task Order Number (if applicable); Direct Labor Hours; Direct Labor Dollars; Country, State, Zip Code, City, or Installation of Service; Total Obligated Dollars; Total Invoiced Amount; Contractor Company Name; Contractor Point of Contact First and Last Name, Phone Number, and Email Address.
The contractor shall include, and require inclusion of, this term in subcontracts at any tier under this contract (except to vendors providing good and no services other than incidental services). NOTE: The prime contractor shall ensure that subcontractors shall not enter any contract level information, only location data to include direct labor hours, direct labor dollars, and location where provided.
While the Contracting Officer’s Representative (COR) will normally establish the contract record at the above address, the prime contract may establish the record.
The contractor shall prepare a status report IAW DI-MGMT-80368 (A013) which includes a list of small business subcontractors, the details of how the contractor shall utilize those subcontractors in performing the contract, and how the contractor shall adhere to or exceed their proposed utilization of its small business subcontractors. The Procuring Contract Officer (PCO) will use this report in determining an overall Contractor Performance Assessment Reporting System (CPARS) rating for subcontracting management by the contractor. The contractor shall coordinate with the PCO if small business firms identified in the list of subcontractors are substituted for or not utilized during the quarter. The contractor shall attempt to find like/similar small business firms matching the socio-economic categories identified in the original list of small business subcontractors when replacing/substituting small business subcontractors from the list. The PCO must agree with small business subcontractor substitutions requested by the contractor prior to those replacement subcontractors performing work on this contract.
Small Business Subcontracting Commitment Plan. The contractor shall make a good faith effort to find opportunities for small business subcontractors in the performance of this contract. The contractor shall contact the local Procurement Technical Assistance Center (PTAC), the local Office of Small Business Programs, and utilize the Small Business Dynamic Search Website to assist in finding small business subcontractors that are capable of performing the work to be subcontracted.
Competition in Subcontracting. The contractor shall prepare a Status Report IAW DI- MGMT-80368 (A013), to report the level of competition in subcontracting achieved or percent of subcontracts that are competed.
7.2 Travel
The contractor shall travel in support of all elements of the SOW. The contractor shall obtain written approval from the Project Management Office (PMO) prior to all related travel.
8.0 CONFIGURATION MANAGEMENT
8.1 Configuration of Switchblade Qualified Product Baseline
The contractor shall ensure that the qualified baseline for this effort consists of the current contractor product baseline and the latest Government approved baseline, which shall meet or exceed all requirements in Attachment 5 – System Capability Document. The Government approved baseline shall include all Government approved Class I ECPs, Value Engineering Change Proposals (VECP), or Requests for Variance (RFV). The contractor shall not implement, without prior Government approval and contractual change, configuration changes which impact the performance or interface requirements of the Configuration Items listed in Paragraph 3.0 of this SOW. AV shall provide a summary of all proposed Class II engineering changes or variances for review of classification. The Government reserves the right to delegate this task to DCMA as necessary. The contractor shall prepare Product Drawings/Models and Associated lists for any newly developed or modified drawings or technical data resulting from a Government directed, funded, and approved change request or proposal IAW DI-SESS- 81000 (A014), MIL-STD-31000, and TDP Option Worksheet to complete this scope of work. The contractor shall also prepare Source Control Drawings for any newly developed or modified drawings or technical data resulting from a Government directed, funded, and approved change request or proposal IAW DI-SESS-81010 (A021) and TDP Option Worksheet
8.2 Configuration Control
The contractor shall prepare a configuration management plan IAW DI-SESS-80858 (A017). The contractor shall maintain the Switchblade Technical Documentation for this contract effort. CIs (hardware, firmware, and software) to be delivered are identified in Paragraph 3.0 of this SOW. Contractor initiated changes to Government controlled documentation shall be prepared IAW DI-SESS-80639 (A004) (Engineering Change Proposal (ECP)) and shall be accompanied by appropriate data prepared IAW DI- SESS-80642 (A006) (Notice of Revision (NOR)) and DI-SESS-80463 (A019) (Engineering Release Record (ERR)). The contractor shall prepare a formal RFV IAW DI-SESS-80640 (A005) for departure from Government requirements. In this, the contractor shall identify newly identified or newly addressed safety hazards and shall include an assessment of their associated safety risk.
8.3 Data Assertions
The contractor shall identify pre-award assertions for the major components (CIs) identified in the SOW IAW DFARS 252.227-7017. Post-award assertions, shall be made IAW DFARS 252.227-7013 and DFARS 252.227-7014. The contractor shall mark all technical data, computer software documentation and computer software deliverables IAW DFARS 252.227-7013 and DFARS 252.227-7014 the provisions of this contract. The contractor shall ensure that data rights markings and legends are consistent with the agreement between the Government and contractor as documented in pre-award contractors data rights assertions.
9.0 LOT ACCEPTANCE TESTING
The contractor shall participate in and support a Lot Acceptance Test (LAT) for each lot of AURs delivered. Each homogeneous lot shall consist of a minimum of fifty (50) AURs with a maximum of two-hundred (200) AURs. The contractor shall store these components in a separate location at the respective contractor’s facility until entire lot is complete. Regardless of lot size, five (5) AURs will be randomly selected by either the Defense Contract Management Agency (DCMA) or CCWS personnel. The payloads shall also be randomly selected by DCMA or CCWS personnel. The contractor shall transport the assembled AURs to Dugway Proving Grounds (DPG) or another Government test location for Live Fire Testing after those selected AURs have been accepted by the Government. Upon arrival at DPG the rounds shall meet the criteria listed in Attachment 0004 Special Provisions H. The Government reserves the right to modify any portion of the LAT described in Attachment 0004 Special Provisions H for all test articles. Should any portion of the LAT be modified to a degree that would affect contract price, schedule, or combination thereof, a contract modification will be negotiated.
10.0 SAFETY
The contractor shall perform all Switchblade related production efforts in conformance with federal, state and local safety requirements and regulations.
The contractor shall treat all safety problems and issues as high priority and come to a resolution within 72 hours. The contractor shall prepare an Accident/Incident Report to report incidents to the CCWS PMO IAW DI-SAFT-81563 (A016).
11.0 SECURITY REQUIREMENTS
The contractor shall obtain a SECRET facility clearance from the Defense Security Service (DSS) and be able to maintain it. The contractor shall provide cleared personnel at the SECRET level to perform classified tasks. The contractor shall have, at a minimum, a SECRET level facility clearance in order to retain this contract.
Contractor personnel working with classified or sensitive information shall maintain, at a minimum, a clearance at the level of the information they will be working.
Note: PEO Missiles and Space requires a final granted SECRET clearance to work on PEO Missiles and Space network systems.
12.0 AT/OPSEC ADDITIONAL REQUIREMENTS
1. Anti-Terrorism (AT) Level 1 Training. (This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area.)All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 30 calendar days after completion of training by all employees and subcontractor personnel.
AT level I awareness training is available at the following website: http://jko.jten.mil.
2. AT Awareness Training for Contractor Personnel Traveling Overseas. This standard language is required for US based contractor employees and associated subcontractor employees to make available and to receive government provided area of responsibility (AOR) specific AT awareness training as directed by AR 525-13. Specific AOR training content is directed by the combatant commander with the unit ATO being the local point of contact.
3. iWATCH Training. (This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area.) The contractor and all associated subcontractors shall brief all employees on the local iWATCH program (training standard provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 45 calendar days after contract award.
4. Contractors Authorized to Accompany the Force. (DFARS Clause 252.225- 7040, Contractor Personnel Authorized to Accompany U.S. Armed Forces Deployed Outside the United States.) This clause shall be used in solicitations and http://jko.jten.mil/ contracts that authorize contractor personnel to accompany US Armed Forces deployed outside the US in contingency operations; humanitarian or peacekeeping operations; or other military operations or exercises, when designated by the combatant commander. The clause discusses the following AT/OPSEC related topics: required compliance with laws and regulations, pre-deployment requirements, required training (per combatant command guidance), and personnel data required.
5. Contracts Requiring Performance or Delivery in a Foreign Country.
(DFARS Clause 252.225- 7043, Antiterrorism/Force Protection for Defense Contractors Outside the U.S.)This clause shall be used in solicitations and contracts that require performance or delivery in a foreign country. This clause applies to both contingencies and non-contingency support. The key AT requirement is for non-local national contractor personnel to comply with theater clearance requirements and allows the combatant commander to exercise oversight to ensure the contractor’s compliance with combatant commander and subordinate task force commander policies and directives.
6. Access and General Protection/Security Policy and Procedures. (This standard language is for contractors with an area of performance within an Army controlled installation, facility or area.) Contractors and all associated subcontractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office.
Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
6.1 Contractors Requiring a Common Access Card (CAC). Before CAC issuance, the contractor employee requires, at a minimum, a favorably adjudicated National Agency Check with Inquiries (NACI) or an equivalent or higher investigation IAW Army Directive 2014-05. The contractor employee will be issued a CAC only if duties involve one of the following: (1) Both physical access to a DoD facility and access, via logon, to DoD networks on-site or remotely; (2) Remote access, via logon, to a DoD network using DoD-approved remote access procedures; or (3) Physical access to multiple DoD facilities or multiple non-DoD federally controlled facilities on behalf of the DoD on a recurring basis for a period of 6 months or more. At the discretion of the sponsoring activity, an initial CAC may be issued based on a favorable review of the FBI fingerprint check and a successfully scheduled NACI at the Office of Personnel Management.
6.2 Contractors not Eligible for a CAC, but Requires Access to a DoD Facility or Installation. Contractor and all associated subcontractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, IAW status of forces agreements and other theater regulations.
7. Contracts Handling or Having Access to Classified Information.
Contractor shall comply with FAR 52.204-2, Security Requirements. This clause involves access to information classified “Confidential,” “Secret,” or “Top Secret” and requires contractors to comply with - (1) The Security Agreement (DD Form 441), including the National Industrial Security Program Operating Manual (DoD 5220.22-M); (2) any revisions to DOD 5220.22-M, notice of which has been furnished to the contractor.
8. Army Training Certification Tracking System (ATCTS) Registration for Contractors with a Government Information Systems Access Requirement.
All contractor employees with access to a government info system must be registered in the ATCTS (Army Training Certification Tracking System) at commencement of services, and must successfully complete the DOD Information Assurance Awareness prior to access to the IS and then annually thereafter.
9. For contracts that require a formal OPSEC program. Reserved
10. Contracts that Require OPSEC Training. Per AR 530-1 Operations Security, the contractor employees must complete Level I OPSEC Awareness Training. New employees must be trained within 30 calendar days of their reporting for duty and annually thereafter.
11. . Information Assurance (IA)/Information Technology (IT) Training. All contractor employees and associated sub-contractor employees must complete the DoD IA awareness training before issuance of network access and annually thereafter. All contractor employees working IA/IT functions must comply with DoD and Army training requirements in DoDD 8140.01, DoD 8570.01M and AR 25-2 within six months of appointment to IA/IT functions.
12. Information Assurance (IA)/Information Technology (IT) Certification. Per DoD 8570.01-M , DFARS 252.239.7001 and AR 25-2, the contractor employees supporting IA/IT functions shall be appropriately certified upon contract award. The baseline certification as stipulated in DoD 8570.01-M must be completed upon contract award.
13. Threat Awareness Reporting Program (TARP). For all contractors with security clearances. Per AR 381-12 Threat Awareness and Reporting Program (TARP), contractor employees must receive annual TARP training by a CI agent or other trainer as specified in chapter 2, paragraph 2-4b of AR 381-12.
13.0 CYBER SECURITY REQUIREMENTS
The contractor shall adhere to Cyber Security regulations and policies including the National Security Act; Clinger-Cohen Act; Federal Information Security Management Act (FISMA); AR 25-1 Army Information Technology; AR 25-2 Information Assurance; Any applicable DoDI 8500 series Directives and/or Instructions and their associated references (Cyber security); National Institute of Standard and Technology (NIST) SP 800 series Special Publications (SP) and their associated references; CNSSI No. 1253 Security Categorization and Control Selection for National Security Systems; Chairman of the Joint Chiefs of Staff Instruction (CJCSI) and Chairman of the Joint Chiefs of Staff Manual (CJCSM) 6000 Series; National Security Agency (NSA) Guides; Defense Information System Agency (DISA) Security Technical Implementation Guides (STIGs).
13.1 Authorization to Operate
The contractor shall maintain the system IAW DI-MISC- 80508 (A023) to support a system Authorization to Operate (ATO) IAW DoDI 8510.01 National Institute of Standard and Technology (NIST) SP 800 series Special Publications (SP) for Risk Management Framework (RMF) for a system that is categorized as confidentiality low, integrity low, and availability low.
14.0 HAZARDOUS MATERIAL MANAGEMENT
All contractor and subcontractor activities shall be in compliance with applicable federal, state, and local environmental laws and regulations. The contractor shall ensure that design, maintenance, operation, manufacturing, programmatic decisions and trade-off studies strive to eliminate or reduce hazardous materials and waste. The contractor shall implement a Hazardous Material Management Program (HMMP) IAW National Aerospace Standard 411. The contractor shall not use any Class I Ozone Depleting Chemical/Ozone Depleting Substance (ODC/ODS) (identified at http://www.epa.gov/ozone/ods.html) or any unacceptable ODC/ODS solvents (identified at http://www.epa.gov/ozone/snap/lists/index.html) in the manufacture or support of items required by this SOW unless a waiver is obtained from the Army Acquisition Executive. Any ODC/ODS refrigerant alternatives used shall appear in the Environmental Protection Agency's Significant New Alternatives Policy (SNAP) list (identified at http://www.epa.gov/ozone/snap/lists/index.html and have received a toxicity clearance from the US Army Public Health Command. The contractor shall provide immediate notification of any proposed hazardous material mitigation/elimination efforts that may adversely impact schedules, cost and/or performance.
http://www.epa.gov/ozone/ods.html http://www.epa.gov/ozone/snap/lists/index.html http://www.epa.gov/ozone/snap/lists/index.html
File details come from the government source that posted it.