B08 Solicitation Amendment W25G1V21Q0004-0001.pdf
PDF 396 KB Posted
- Attached to
- WOOD COMPACTOR SUPPY & INSTALL Federal contract opportunity
- Solicitation number
- W25G1V21Q0004
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B08 Solicitation Amendment W25G1V21Q0004-0002.pdf | ||
| B08 Solicitation W25G1V21Q0004.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ACC-APG, TOBYHANNA DIVISION
KIMBERLY JURKIEWICZ
KIMBERLY.M.JURKIEWICZ.CIV@MAIL.MIL
PHONE 570 615 7066
TOBYHANNA PA 18466-5100
W25G1V0230009K
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The reason for this Amendment is to remove and clarify some items w ithin the Statement of Work (Revised Statement of Work is attached).
Please Refer to the Statement of Work attached and labeled REVISED STATEMENT OF WORK.
The revisions made to the Statement of Work encompass the follow ing changes: The w ood compactormachine w ill need to be a minimum of 40HP. The government w ill be preparing the concrete pad foundation and installing electrical equipment. The w ood compactor manufacturer and/or supplier w ill set the w ood compactor equipment.
Also, the MFR name w as asked, please refer to the specifications required as per the Statement of Work and description of requirement.
The largest factor on specifications is the ability to breakdow n and compact the w ood items as listed in the specifications for performance testing, how ever, all listed specif ications need to be met in order to consider offers.
This amendment must be signed and returned w ith offers for offers to be considered. All other terms & conditions remain the same.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 5
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 15-Oct-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W25G1V21Q0004
X 9B. DATED (SEE ITEM 11)
06-Oct-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
15-Oct-2020
CODE
ACC-APG, TOBYHANNA DIVISION
11 HAP ARNOLD BLVD
TOBYHANNA PA 18466-5100
W25G1V 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE W25G1V
FACILITY CODECODE
EMAIL:TEL:
W25G1V21Q0004
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
SOLICITATION/CONTRACT FORM
The required response date/time has changed from 20-Oct-2020 05:00 PM to 23-Oct-2020 05:00 PM.
SUPPLIES OR SERVICES AND PRICES
CLIN 0001
The CLIN extended description has changed from:
WOOD COMPACTOR, HEAVY DUTY INDUSTRIAL; 60HP WITH TURN KEY INSTALLATION; THIS
AWARD WILL BE FOR THE TURN KEY DESIGN, SUPPLY, DELIVERY, ASSEMBLY, INSTALLATION,
AND ALL TRAINING ASSOCIATED WITH THE WOOD COMPACTOR.*PLEASE REFER TO ATTACHED
STATEMENT OF WORK FOR SPECIFIC SCOPE OF WORK DETAILS AND FOR WOOD COMPACTOR
MINIMUM SPECIFICATIONS.THE AWARD WILL BE BASED ON THE LOWEST PRICE THAT MEETS OR
EXCEEDS ALL MINIMUM SPECIFICATIONS LISTED AS PER THE ATTACHED STATEMENT OF
WORK.**NOTE TO OFFERORS: All Contractor Proposal Requirements to the Solicitation must be submitted with proposal in order for proposals to be considered. (See the section titled Contractor Proposal Requirements to the Solicitation in the attached Statement of Work).ITEM IS BRAND NAME OR EQUAL. IF QUOTING EQUAL, VENDOR MUST PROVIDE FULL SPECIFICATION PACKAGE FOR BID TO BE CONSIDERED. POINT OF
CONTACT: MATT ARGUST, PHONE: 570-615-6594;EMAIL:
MATTHEW.J.ARGUST.CIV@MAIL.MILDELIVERY INSTRUCTIONS LOACTED IN THE CLAUSE
SECTION OF THIS SOLICITATION.
To:
WOOD COMPACTOR, HEAVY DUTY INDUSTRIAL; MINIMUM 40HP WITH TURN KEY INSTALLATION;
THIS AWARD WILL BE FOR THE TURN KEY DESIGN, SUPPLY, DELIVERY, ASSEMBLY,
INSTALLATION, AND ALL TRAINING ASSOCIATED WITH THE WOOD COMPACTOR.*PLEASE REFER
TO ATTACHED STATEMENT OF WORK FOR SPECIFIC SCOPE OF WORK DETAILS AND FOR WOOD
COMPACTOR MINIMUM SPECIFICATIONS.THE AWARD WILL BE BASED ON THE LOWEST PRICE
THAT MEETS OR EXCEEDS ALL MINIMUM SPECIFICATIONS LISTED AS PER THE ATTACHED
STATEMENT OF WORK.**NOTE TO OFFERORS: All Contractor Proposal Requirements to the Solicitation must be submitted with proposal in order for proposals to be considered. (See the section titled Contractor Proposal Requirements to the Solicitation in the attached Statement of Work).ITEM IS BRAND NAME OR EQUAL. IF
QUOTING EQUAL, VENDOR MUST PROVIDE FULL SPECIFICATION PACKAGE FOR BID TO BE
CONSIDERED. POINT OF CONTACT: MATT ARGUST, PHONE: 570-615-6594;EMAIL:
MATTHEW.J.ARGUST.CIV@MAIL.MILDELIVERY INSTRUCTIONS LOACTED IN THE CLAUSE
SECTION OF THIS SOLICITATION.
The following have been added by full text:
REVISED STATEMENT OF WORK
Statement of Work Wood Compactor
General Scope
This Statement of Work (SOW) is for the turn-key design, supply, delivery, assembly, installation and training of Wood Compactor to include the supply, delivery, installation, documentation and personnel training for a Wood Compactor. The machine will be located at Bldg. 66 at Tobyhanna Army Depot (TYAD) and shall meet or exceed all applicable industrial, Federal, State, and Local standards and codes. The Contractor shall provide on-site machine training for TYAD operator personnel and maintenance personnel.
ACCESS TO INSTALLATION SITE (Bldg. 66): The site location for the compactor will be outside of Bldg. 66 in the Recycling Yard at Tobyhanna Army Depot.
SITE VISIT: Interested Contractors shall request a site visit prior to submitting a proposal, (see the section in this SOW titled Contractor Proposal Requirements to the Solicitation for this and the other proposal submission requirements.
Site visit must be requested by email to: MATTHEW.J.ARGUST.CIV@MAIL.MIL OR
KIMBERLY.M.JURKIEWICZ.CIV@MAIL.MIL
Any site visit requests must be submitted via email request to the above email(s) by no later than, Tuesday, Oct 20, 2020.
Wood Compactor Machine Specifications, Characteristics and Features
1. The compactor should meet a minimum of 40HP and be able to fit on 10’x 10’ concrete pad.
2. The machine must be fully capable of sitting outside in the open without any cover.
3. The machine must be able to accept pallets of up to 60” x 96”in dimension, crates at least 48” x 48” x 60” in dimension and wood spools of up to 60” in diameter.
4. The machine must not directly use fossil fuels.
5. The machine should allow it to be fed primarily by forklift truck.
General Requirements
Delivery, Assembly, and Installation
1. It shall be the responsibility of the Contractor to contact the TYAD Fire Department to obtain a Burn
Permit prior to conducting welding, torch cutting, or soldering.
2. The Contractor shall be responsible to supply all labor, materials, supervision, tools and equipment to deliver, off-load, locate and place into position, and anchor all component pieces, materials and supplies necessary for the turn-key assembly and installation of the wood compactor. The Contractor shall be responsible to uncrate and unpack all supplied equipment. The Contractor shall be responsible to remove from TYAD all packing, packaging and crating materials.
3. All equipment, tools, materials, supplies and component pieces shall be delivered concurrently; no partial deliveries are acceptable.
4. The Contractor can perform all post-delivery work during normal 1st-shift hours: Monday—Friday, 7:00 AM—4:00 PM, but shall not interfere with normal production. Deliveries shall be coordinated by the Contractor with the COR 10 working days, minimum, in advance of delivery.
5. The Contractor shall adhere to all TYAD Environmental, Safety, and Fire standards, codes and regulations.
Furnishing of personal protective equipment (PPE) to Contractor personnel shall be the responsibility of the Contractor.
6. It shall be the Contractor’s responsibility to supply and deliver a dumpster for waste collection. Location for a dumpster shall be coordinated with the COR prior to its arrival. The Contractor shall remove the dumpster within 3 calendar days of work completion.
7. For all Contractor-owned electrical equipment that requires battery recharging it shall be the responsibility of the Contractor to supply his own battery-charging equipment. Connection of Contractor-supplied battery-charging equipment to TYAD power shall be the responsibility of the Contractor.
8. The Contractor shall have 180 days ARO to install the wood compactor and complete all operator and maintenance personnel training. The Contractor shall commence installation of wood compactor within 3 working days of arrival of the equipment.
9. The Contractor shall submit to the COR a project time line 10 working days ARO.
10. The Contractor shall be responsible for start-up and verification of system.
Warranty
1. The Contractor shall warrant wood compactor, all ancillary pieces of equipment, and installation parts and workmanship for a period of 4 calendar years following final acceptance by the COR. During this warranty period all parts costs, labor costs, transportation and shipping costs, travel costs, tool costs and per diem for all Contractor personnel shall be the responsibility of the Contractor. The Contractor field repair technician shall arrive on-site within 24 hours after being contacted by TYAD personnel to make warranty repairs during the warranty period. The Contractor field repair technician shall arrive on-site within 24 hours after being contacted by TYAD personnel to make repairs for the life of the machine at TYAD. The Contractor shall supply Contact Telephone Numbers and Points of Contact (POCs) for use by TYAD personnel to contact the Contractor for warranty, operation and maintenance questions and support.
2. All pieces of equipment that have a manufacturer’s warranty that exceeds the 4 year warranty period such warranties shall be provided by the Contractor to the Government at the expiration of the 4 year warranty period at which time it will become the responsibility of the Government to submit warranty claims.
Documentation
1. The Contractor shall provide to the COR 3 hardcopies each of the Operation and Maintenance (O&M)
Manuals and 3 hardcopies each of the Parts Manual. The Parts Manual shall include a list of parts— including consumables—that are recommended by the manufacturers to be kept on-hand at all times.
These parts shall be identified by nomenclature, part number, quantity, and pricing. The O&M manuals shall contain complete detailed instructions and schedules for system PM. All documentation shall be provided to the COR prior to final acceptance being given. O&M manuals shall contain a detailed description of the lock-out/tag-out procedures needed to bring the wood compactor to a zero mechanical state for maintenance and servicing. Procedures for returning the wood compactor to full operational capability shall also be provided.
Training
1. The Contractor shall provide machine operator training for 4 TYAD Environmental Branch personnel.
Training shall be conducted by the Contractor’s qualified training representative. Training shall be done on-site and personnel shall be trained in the full operation and operator-recommended maintenance.
2. The Contractor shall provide maintenance training for 2 TYAD Logistics Support Division (LSD) personnel. Training shall be conducted by the Contractor’s qualified training representative. LSD personnel shall be trained in the full maintenance and PM of the wood compactor. LSD personnel training shall occur prior to installation of the wood compactor.
3. All materials and documentation used in the training of operator personnel and LSD personnel shall become the property of the Government.
General Acceptance
1. Upon completion by the Contractor of the installation of the wood compactor shall be the responsibility of the Contractor to verify and show the wood compactor, all ancillary components are operating within manufacturers’ specified parameters and specifications.
2. The Contractor or his qualified representative shall demonstrate the functioning of the wood compactor and ancillary components by successfully shredding/compacting a pallets of 60” x 96”in dimension, a crate at least 48” x 48” x 60” in dimension and a wood spool of 60” in diameter. The demonstration will be witnessed by Environmental Branch operators; the Environmental Branch supervisor; the COR; and a technical representative of the COR’s choosing. Demonstration shall be coordinated with the COR so as to permit all necessary personnel to be present. All defects encountered prior to or during the demonstration shall be immediately corrected by the Contractor. Only upon correction of the defect will the demonstration be allowed to continue.
3. Only following the successful demonstration of the wood compactor; conclusion of maintenance personnel and operator personnel training and furnishing of all manuals to the COR will general acceptance be granted to the Contractor.
Final Acceptance
1. Final acceptance will occur upon acceptance in Wide Area Workflow (WAWF) of the Contractor’s submitted invoice by the COR. The warranty periods associated with the wood compactor and ancillary components will begin on the date of final acceptance. Final acceptance will be granted only after general acceptance has been given to the Contractor.
Contractor Proposal Requirements to the Solicitation A Contractor’s submittal to the solicitation shall contain explanatory descriptions to all aspects listed below and these descriptions will be used by the Government for technical review and evaluation of the submitted proposal. A single statement of Contractor compliance will not be accepted in lieu of an explanatory description and shall disqualify the Contractor for contract award consideration. A Contractor’s submittal not in compliance with all aspects of the Contractor Proposal Requirements to the Solicitation will not be considered and will result in the Contractor being disqualified from consideration for contract award.
1. A Contractor considering submission of a proposal to the solicitation shall schedule a site visit. All dimensions and dimension verifications are the responsibility of the Contractor.
2. The Contractor proposal shall indicate the training that will be provided for operator personnel and maintenance personnel as well as the training durations. The Contractor shall provide a detailed description of maintenance personnel and machine operator personnel training programs.
3. The Contractor proposal shall include 3 references of prior projects of similar scope and complexity along with points of contact (POCs) for each project and their telephone numbers.
4. A rough time line shall accompany the Contractor proposal.
The following have been deleted:
STATEMENT OF WORK
(End of Summary of Changes)