B08 Solicitation Amendment W25G1V20Q0245-0001.pdf
PDF 537 KB Posted
- Attached to
- TREE CLEARING
- Solicitation number
- W25G1V20Q0245
View the file
Other files
| File | Type | Posted |
|---|---|---|
| QUESTIONS and ANSWERS for TREE CLEARING 20Q0245.docx | DOCX document | |
| B08 Solicitation W25G1V20Q0245.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W25G1V0135016U
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The reason for this Amendment is to post questions and answ ers and additional information. The Questions/Answ ers and Additional information are all included in one attachment labeled in the Clause Section of this Solicitation. It is labeled as Questions and Answ ers. This amendment must be signed and returned w ith bid offers for offers to be able to be considered. All other terms & conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 22-Sep-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W25G1V20Q0245
X 9B. DATED (SEE ITEM 11)
03-Sep-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
22-Sep-2020
CODE
ACC-APG, TOBYHANNA DIVISION
11 HAP ARNOLD BLVD
TOBYHANNA PA 18466-5100
W25G1V 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
kimberly.m.jurkiewicz.civ@mail.milEMAIL:570 615 7066TEL:
KIMBERLY M JURKIEWICZ / PURCHASING AGENT
W25G1V20Q0245
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION C - DESCRIPTION AND SPECIFICIATIONS
The following have been added by full text:
QUESTIONS AND ANSWERS
QUESTIONS and ADDITIONAL INFORMATION for TREE CLEARING SOLICITATION W25G1V20Q0245
THIS IS FOR SOLICITATION AMENDMENT 01
Additional information for this requirement provided by Tobyhanna Army Depot:
Bulldozing trees and removing all stumps shall be allowed in order to eliminate the need of new soils as stated in section 2.3.2. **This method of work must adhere to all other sections and subsections of this contract. Work shall leave no "mounds" or "voids" within the limit of disturbance, whether existing or created by the contractors operations. With that being said, final site must be graded by the contractor upon completion of the work.
QUESTIONS/GOVERNMENT RESPONSES:
QUESTION 1: Will we be required to seed and mulch the site after clearing?
GOVERNMENT RESPONSE 1: Grass seeding will be required after work is completed.
QUESTION 2: Will hand felling be allowed?
GOVERNMENT RESPONSE 2: Hand felling will now be allowed. *Sidewalks, curbs, streets, fencing, manhole covers, meter pits, barriers, assets, etc. shall always be protected from the impact of falling wood.
(End of Summary of Changes)