W15QKN-23-Q-5080 QUESTION AND ANSWERS

Q1: Who was the contractor and the award amount of the contract (for previous contract)?

A1: W15QKN-18-P-1073 to Advant-Edge Solutions of Middle Atlantic for $112,250.00.

Q2: Could you please provide the specific location or locations where the services are expected to be performed?

A2: Services will be performed at the Fleming-Godwing USARC, 344 North New Street, Dover, DE 19904 (DE001) and Cape Henlopen USARC/BMA #86-1, 1137 Savannah Road, Lewes, DE 19958 (DE002).

Q3: In the Performance Work Statement under section "1 General" it states, "this is a non-personal services contract." Further down, under Section 1.5.6.2 titled "Contractor Representative" it states, "the contractor shall provide an onsite contractor representative who shall be physically present during normal duty hours." Could you please confirm that you do want a person present at both properties during all duty hours?

A3: A contractor need not be on site while the dumpster vendor on site. A contractor IS NOT required to be present during all duty hours; however, performance MUST be completed during duty hours.

Q4: Will the roll off containers need to remain onsite throughout the year, or will they only need to be onsite for a short period of time, once requested?

A4: The large [roll-off] dumpster(s) are only on site for two weeks at a time when needed.