STATEMENT OF WORK
Replace Existing Dust Collector System
Range HQ
1.0 SUMMARY
The US Army Support Activity (ASA) – Fort Dix requires a turn-key solution to replace an existing dust collector system located at Range HQ. The work entails removal and disposition of the existing dust collector system. Contractor shall provide and install new dust collector system. New system shall be as manufactured by AMTECH, Model ATC-247-1D Cyclone Dust Collector equipped with an ATAF-6W Felt Polyester Air Filter assembly or an approved equal.
Unit shall be provided with a mechanical isolation valve to meet NFPA requirements. Existing ductwork inside the building shall remain. Contractor shall tie new system into existing exterior ductwork. Existing electrical feed can be reutilized if adequate for new system. Otherwise, contractor shall provide new service for equipment. System shall be complete and useable after install.
2.0 DETAILED WORK REQUIREMENTS
2.1 EQUIPMENT REMOVAL
The contractor shall inspect, prepare, and remove existing 36 HPH Donaldson dust collector system. System shall be removed and taken to a designated location as specified by the Government within the Range HQ complex. Contractor shall NOT remove the existing system off-site unless specifically requested, in writing, from the Government.
2.2 SITE SURVEY/PREPARATIONS
The contractor shall perform a site survey of the facility in support of developing and executing a project plan for the removal of existing system and the installation of the new system. Survey shall include any physical, environmental, or other conditions, concerns, or requirements that may be essential to successful completion of the project. The contractor shall provide all site preparation duties including but not limited to electrical modifications in accordance with local Installation, agency, state, and federal regulations, policies, guidelines, etc.
2.3 NEW EQUIPMENT
The contractor shall provide new equipment at site for inspection to ensure there are no defects/physical damage. Government reserves the right not to accept an equipment deemed unacceptable. New dust collector system shall
2.4 INSTALLATION/TESTING
The contractor shall provide all installation and testing in accordance with the manufacturers equipment specifications. Contractor is responsible to provide all labor and equipment to install the new equipment. Government will NOT provide any support for this effort. Contractor shall ensure new equipment is fully operational in the presence of the Government and provide all necessary training for designated Government personnel.
3.0 PROJECT WORK DETAILS:
The information stated here are the details of the project performed by the contractor for the Government with specifications on date, time, and place.
3.1 SCHEDULE
Period of Performance (POP) shall be 120 calendar days from contract award. This allows for equipment lead-time.
3.2 LOCATION
The location of this project will be on-site at Range HQ located at 9003 Hanover Road, Fort Dix, NJ 08640.