VA259-17-R-1086-00003001.pdf

PDF 36 KB Posted

Attached to
Site Prep for CT Scanner
Solicitation number
VA25917R1086
Issued by

About this file

VA259-17-R-1086 00003 RFI2 Answers.pdf

View the file

Other files

File Type Posted
VA259-17-R-1086-00009001.pdf PDF
VA259-17-R-1086-00009000.docx DOCX document
VA259-17-R-1086-00008000.docx DOCX document
VA259-17-R-1086-00008001.pdf PDF
VA259-17-R-1086-00007000.docx DOCX document
VA259-17-R-1086-00006000.docx DOCX document
VA259-17-R-1086-00005000.docx DOCX document
VA259-17-R-1086-00005001.pdf PDF
VA259-17-R-1086-00004002.pdf PDF
VA259-17-R-1086-00004001.pdf PDF
VA259-17-R-1086-00004000.docx DOCX document
VA259-17-R-1086-00003002.pdf PDF
VA259-17-R-1086-00003000.docx DOCX document
VA259-17-R-1086-00003003.pdf PDF
VA259-17-R-1086-A0002001.pdf PDF
VA259-17-R-1086-A0002000.docx DOCX document
VA259-17-R-1086-A0002002.pdf PDF
VA259-17-R-1086-A00001000.docx DOCX document
VA259-17-R-1086-000.docx DOCX document
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Ref Spec. 1 of 2, 010000-3, section 1.5 construction security requirements, C, Guards. Questions is, are we required to provide guards for off hours? No That section is deleted Page 01 00 00 -3 C 1-3.

2. What is the floor thickness where the scanner will be located? The floor thickness is 5” thick, 3000 PSI concrete topping. This is advisory only and it is the contractor’s responsibility to verify all measurements.