MEMORANDUM TO THE FILE
(This is only applicable to acquisitions under the Simplified Acquisition Threshold. Acquisition using FAR Subpart 13.5 shall follow the special documentation requirements at FAR 13.501.)
Subj: USE OF OTHER THAN FULL AND OPEN COMPETITION FOR AN
ACQUISITION UNDER THE SIMPLIFIED ACQUISITION THRESHOLD
I. BACKGROUND:
1. FAR 13.106-1(b)(1)(i) states for purchases not exceeding the simplified acquisition threshold, Contracting Officers may solicit from one source if the Contracting Officer determines that the circumstances of the contract action deem only one source reasonably available (e.g., urgency, exclusive licensing agreements, brand-name or industrial mobilization).
2. As required by FAR 13.106-3(b)(3)(i), this memorandum explains the absence of competition for this acquisition, as only one source will be solicited for this requirement (or for a portion of the requirement) and the requirement is not expected to exceed the simplified acquisition threshold.
II. DESCRIPTION OF ITEM OR SERVICE:
III. THE DETERMINATION FOR USE OF OTHER THAN FULL AND OPEN
COMPETITION IS BASED ON THE FOLLOWING (select all that apply):
A. ONLY ONE RESPONSIBLE SOURCE (select all that apply):
1. RESTRICTIVE RIGHTS. The source has established proprietary rights, limited rights in data, patent rights, copyrights or secret processes in the item or service required.
2. EXCLUSIVE LICENSING AGREEMENTS. The item or service is only available from the Original Equipment Manufacturer (OEM), or there is only one authorized distributor or technical representative for the OEM.
3. OTHER REASONS.
B. BRAND NAME. Item required must be a brand name product, or feature of a product, particular to one manufacturer.
C. UNUSUAL AND COMPELLING URGENCY. The supplies or services are of such unusual and compelling urgency that the Government would be seriously injured unless the agency is permitted to limit the number of sources from which it solicits bids or proposals.
Urgent requirements are supplies or services that will result in a work stoppage, or are mission critical and the routine processing time would result in injury to the Government. The determination that the procurement for the above item/service is an urgent and compelling requirement is based on the following:
1. Date on which the requirement was first identified:
2. Required delivery date/period of performance:
3. Explanation of why delivery/commencement of services by the date mentioned above is required:
4. If appropriate, include any additional pertinent information.
MEMORANDUM TO THE FILE
| Text1: The required long lead time material is in support of the USS SAN ANTONIO LPD-17, repairs to the Number 2 Ship's Service Diesel Generator required by SSP TPPC-LPD17-MARMCN22-CN01, WI 311-22-001. |
| Text2: Parts required for repairs to the number 2 ship's service diesel generator are sole source to Tranter Parts and Service/ manufactured by Alfa Lav as indicated in Tech Manual EATP 17-0024 REV C. |
| Check Box3: Yes |
| Check Box4: Yes |
| Check Box5: Yes |
| Check Box6: Off |
| Check Box7: Off |
| Text8: Tranter Parts and Services is the OEM for this material and is the only manufacturer that has the means to forge the material required to produce the item. Material provided by any other manufacturer has not been through the proper testing and therefore is not technically acceptable for use. |
| Text9: Other reason not identified above. Provide details on mission impact if requirement is not solicited from only one source. |
| Text10: Discuss why you are precluding consideration of a product manufactured by another company. Describe how the particular brand name, product, or feature is essential to the Government’s requirements and why a “brand name or equal” purchase description cannot be used (see FAR 11.104). Describe how market research indicates other companies’ similar products or products lacking the particular feature do not meet, or cannot be modified to meet, the agency’s needs. |
| Text11: |
| Text12: |
| Text13: Explain the impact to the mission if the date above is not met, any special circumstances or conditions that exist which validate the requirement as “urgent,” estimated production lead time for the item, etc. |
| Text14: |