Pre-Bid_RFI_Track_Project_Log_09-05-2018.pdf

PDF 50 KB Posted

Attached to
Running Track Resurfacing Federal contract opportunity
Solicitation number
Not on record
Issued by
Department of the Army Oklahoma Army National Guard

About this file

RFI update as of 05 Sep 2018

View the file

Other files for this federal contract opportunity

Other files attached to Running Track Resurfacing, newest first.
File Type Posted
Curb_and_track_section.pdf PDF
Pre-Bid_RFI_Track_Project_Log_09-11-2018.pdf PDF
Pre-Bid_RFI_Track_Project_Log_08-22-2018.pdf PDF
Site_Visit_Sign_In_Track_Revitalization.pdf PDF
138FW_Safety__Accident_Prevention_Guide_2018.pdf PDF
Asphalt_Specifications_for_track.docx DOCX document
18-Q-6000.pdf PDF
ESOH_Clause_SOW.DOCX DOCX document
Notification_of_Contractor_Operations_Involving_Radioactive_Materials.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Date: RFI No.

RFP Reference (Sect/Para/Page) QUESTION GOVERNMENT RESPONSE

8/21/2018 1 As a point of clarification, is there synthetic material on the track currently?

No there is not a synthetic material on the track currently.

8/21/2018 2 Is the resurfacing of the existing asphalt or is new asphalt being applied?

The existing asphalt is to be removed and replaced not just a resurfacing.

8/29/2018 3 Is testing required on the subgrade? If so and the existing subgrade fails is there provisions for replacing failed subgrade?

Compaction testing will be required every 150ft. But compaction must be uniform through the entire track.

8/29/2018 4 Can you please confirm which bridge is being widened? There is a crossing on the East side of the pond as well as the West side.

the west bridge is to be widened.

8/29/2018 5 Can you please confirm the depth of the existing track and subgrade?

No

8/29/2018 6 Can you please confirm there is existing base rock?

The damage to the existing track appears to be mostly due to failed subgrade.

There is no existing AG base. A 6" layer oc Crusher Run will need to be put down as a base layer and compacted in accordance with base specifiactions

Pre-Bid RFI Log for Track Revitalization