Asphalt_Specifications_for_track.docx
DOCX document 17 KB Posted
- Attached to
- Running Track Resurfacing Federal contract opportunity
- Solicitation number
- Not on record
About this file
Asphalt Specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Curb_and_track_section.pdf | ||
| Pre-Bid_RFI_Track_Project_Log_09-11-2018.pdf | ||
| Pre-Bid_RFI_Track_Project_Log_09-05-2018.pdf | ||
| Pre-Bid_RFI_Track_Project_Log_08-22-2018.pdf | ||
| Site_Visit_Sign_In_Track_Revitalization.pdf | ||
| 138FW_Safety__Accident_Prevention_Guide_2018.pdf | ||
| 18-Q-6000.pdf | ||
| ESOH_Clause_SOW.DOCX | DOCX document | |
| Notification_of_Contractor_Operations_Involving_Radioactive_Materials.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DESIGN OF REPAIR AND CONSTRUCT PARKING
XHZG162000
SECTION 32 12 17
Page
PART 1 GENERAL
1.1 REFERENCES
SECTION 32 12 17
HOT MIX BITUMINOUS PAVEMENT
04/08
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASPHALT INSTITUTE (AI)
| AI MS-2 | (2015) Asphalt Mix Design Methods ASTM INTERNATIONAL (ASTM) | |
| ASTM D4867/D4867M | (2009; R 2014) Effect of Moisture on Asphalt Concrete Paving Mixtures |
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-05 Design Data Job-mix formula Perform in accordance with ODT Specifications (2009) Section 707 and Section 708. Trial mixes may be waived if a proved ODOT approved Job-mix formula (JMF) with the same superpave type is submitted and approved. JMF must be less than 2 years approved and designed for the Tulsa County area. Provide a new job-mix formula for each source change. Submittal shall include all tests indicated in MIX DESIGN section of this specification.
MIX DESIGN
SD-06 Test Reports Bituminous mix tests Pavement courses Submit in accordance with paragraph entitled "Mock-Up Test Section."
1.3 QUALITY ASSURANCE
1.3.1 Safety Requirements
Provide adequate and safe stairways with handrails to the mixer platform, and safe and protected ladders or other means for accessibility to plant operations. Guard equipment and exposed steam or other high temperature lines or cover with a suitable type of insulation.
1.3.2 Required Data
Job-mix formula shall show the following:
a. Source and proportions, percent by weight, of each ingredient of the mixture;
b. Correct gradation, the percentages passing each size sieve listed in the specifications for the mixture to be used, for the aggregate and mineral filler from each separate source and from each different size to be used in the mixture and for the composite mixture;
c. Amount of material passing the No. 200 sieve determined by dry sieving;
d. Number of blows of hammer compaction per side of molded specimen;
e. Temperature viscosity relationship of the asphalt cement;
f. Stability, flow, percent voids in mineral aggregate, percent air voids, unit weight;
g. Asphalt absorption by the aggregate;
h. Effective asphalt content as percent by weight of total mix;
i. Temperature of the mixture immediately upon completion of mixing;
j. Asphalt performance grade viscosity grade.
1.4 DELIVERY, STORAGE, AND HANDLING
Inspect materials delivered to the site for damage and store with a minimum of handling. Store aggregates in such a manner as to prevent segregation, contamination, or intermixing of the different aggregate sizes.
PART 2 PRODUCTS
2.1 MIX DESIGN
The Contractor shall develop the mix design. The asphalt mix shall be composed of a mixture of well-graded aggregate, mineral filler if required, and asphalt material. The aggregate fractions shall be sized, handled in separate size groups, and combined in such proportions that the resulting mixture meets the grading requirements of the job mix formula (JMF). No hot-mix asphalt for payment shall be produced until a JMF has been approved. The hot-mix asphalt shall be designed using procedures contained in AI MS-2 and the criteria shown in Table II. If the Tensile Strength Ratio (TSR) of the composite mixture, as determined by ASTM D4867/D4867M is less than 75, the aggregates shall be rejected or the asphalt mixture treated with an approved anti-stripping agent. The amount of anti-stripping agent added shall be sufficient to produce a TSR of not less than 75. If an antistrip agent is required, it shall be provided by the Contractor at no additional cost.
2.1.1 JMF Requirements
The job mix formula shall be submitted in writing by the Contractor for approval at least 14 days prior to the start of the test section and shall include as a minimum:
a. Percent passing each sieve size.
b. Percent of asphalt cement.
c. Percent of each aggregate and mineral filler to be used.
d. Asphalt viscosity grade, penetration grade, or performance grade.
e. Number of blows of hammer per side of molded specimen.
f. Laboratory mixing temperature.
g. Lab compaction temperature.
h. Temperature-viscosity relationship of the asphalt cement.
i. Plot of the combined gradation on the 0.45 power gradation chart, stating the nominal maximum size.
j. Graphical plots of stability, flow, air voids, voids in the mineral aggregate, and unit weight versus asphalt content as shown in AI MS-2.
k. Specific gravity and absorption of each aggregate.
l. Percent natural sand.
m. Percent particles with two or more fractured faces (in coarse aggregate).
n. Fine aggregate angularity.
o. Percent flat or elongated particles (in coarse aggregate).
p. Tensile Strength Ratio.
q. Antistrip agent (if required) and amount.
r. List of all modifiers and amount.
s. Percentage and properties (asphalt content, binder properties, and aggregate properties).
2.1.2 Adjustments to JMF
The JMF for each mixture shall be in effect until a new formula is approved in writing by the Contracting Officer. Should a change in sources of any materials be made, a new mix design shall be performed and a new JMF approved before the new material is used.
2.2 SOURCE QUALITY CONTROL
Employ a commercial laboratory approved by the Contracting Officer to perform testing. The laboratory used to develop the JMF and the laboratory used to perform all sampling and testing shall meet the requirements. A certification signed by the manager of the laboratory stating that it meets these requirements or clearly listing all deficiencies shall be submitted to the Contracting Officer prior to the start of construction. The certification shall contain as a minimum:
a. Qualifications of personnel; laboratory manager, supervising technician, and testing technicians.
b. A listing of equipment to be used in developing the job mix.
c. A copy of the laboratory's quality control system.
d. Evidence of participation in the AASHTO Materials Reference Laboratory (AMRL) program and ODOT materials certification for all materials.
PART 3 EXECUTION
3.1 PREPARATION
3.1.1 Preparation of Asphalt Binder Material
Asphalt shall be prepared, transported, and placed in accordance with ODOT Specifications (2009) Section 411.
3.2 FIELD QUALITY CONTROL
3.2.1 Testing
3.2.1.1 Bituminous Mix Tests
Test one sample for each 500 tons, or fraction thereof, of the uncompacted mix for extraction in accordance with ODOT Specifications (2009) Section ; perform a sieve analysis on each extraction sample. Test one sample for each 500 tons for each material blend of the compressed mixture as required by ODOT Specifications (2009) Section 708.
3.2.1.2 ( a.
)Pavement Courses Perform the following tests:
Thickness: Determine thickness of wearing courses from samples taken for the field density test. The maximum allowable deficiency at any point shall not be more than 1/4 inch less than the thickness for the indicated course. Average thickness of course or of combined courses shall be not less than the indicated thickness. Where a deficiency exceeds the specified tolerances, correct each such representative area or areas by removing the deficient pavement and replacing with new pavement.
c. Smoothness: Straightedge test the compacted surface of wearing course as work progresses. Apply straightedge parallel with and at right angles to the centerline after final rolling. Unevenness of variations in the wearing course shall not vary more than 1/8 inch in 10 feet. Correct each portion of the pavement showing irregularities greater than that specified.
d. Finished Grades: Finish grades of each course placed shall not vary from the finish elevations, profiles, and cross sections indicated by more than 1/2 inch. Finished surface of the final wearing course will be tested within 45 days after completion of final placement. Elevations not in conformance with the specified tolerance shall be noted on the plan in an approved manner. The survey shall be performed by a registered land surveyor. Correct deficient paved areas by removing existing work and replacing with new materials that meet the specifications. Skin patching for correcting low areas is prohibited.
e. Finish Surface Texture of Wearing Course: Visually check final surface texture for uniformity and reasonable compactness and tightness. Final wearing course with a surface texture having undesirable irregularities such as segregation, cavities, pulls or tears, checking, excessive exposure of coarse aggregates, sand streaks, indentations, ripples, or lack of uniformity shall be removed and replaced with new materials.
3.3 PROTECTION
Do not permit vehicular traffic, including heavy equipment, on pavement until surface temperature has cooled to at least 120 degrees F. Measure surface temperature by approved surface thermometers or other satisfactory methods.
-- End of Section --