Technical Exhibit 2 Maintenance Actions and Frequencies.docx
DOCX document 47 KB Posted
- Attached to
- DORM HVAC IN OSAN AIR BASE (LCS) Federal contract opportunity
- Solicitation number
- W90VN6-23-R-0019
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| TE 1 - Attachment 2 - Maintenance Actions and Frequencies May 2022.docx | DOCX document | |
| TE 1 - Attachment 1 - Workload Estimates (Facility Listing)(REV.05).xlsx | XLSX spreadsheet | |
| TE 1 - Attachment 3 - AFPMTL MASTER OSAN.pdf | ||
| Modification W90VN6-23-R-0019-0001 23 MAY 2023.pdf | ||
| Solicitation W90VN6-23-R-0019-0001 23 MAY 2023.pdf | ||
| Solicitation W90VN6-23-R-0019.pdf | ||
| Technical Exhibit 3 Consumables for Maintenance.docx | DOCX document | |
| Technical Exhibit 1 Workload Estimates -Facility List.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TECHNICAL EXHIBIT 2
MAINTENANCE ACTIONS AND FREQUENCIES FOR EACH SYSTEM
| Equipment |
| Maintenance/Repair Action |
| Freq |
Note: These units are mostly installed as packages inclusive of cooling and heating element inside. However, some of units might have a remote coil (i.e. duct mounted heat/cool coil) and separate air cooled condenser. In those cases, the contractor shall complete with any other applicable maintenance actions.
| Air Conditioning Machine, Package |
| 1. System understanding |
| 2Y |
| (Special purpose, Computer Room |
| 2. Thoroughly inspect and clean interior and exterior of machine with wet/ dry vacuum, |
| Air conditioning unit) |
| (remove panels). |
3. Clean drain-pan and note excessive corrosion, prepare and paint as necessary.
| * This unit is normally connected with |
| 4. Check condition of cooling and reheat coils. Use fin comb if needed to straighten fins. |
| outdoor air cooled condenser and |
| 5. A dirty coil should be cleaned using a coil cleaner solution and pressurized warm water. |
| shall be serviced simultaneously. |
| 6. Drain and clean humidifier drip pan, replace pan if applicable. Remove scale and paint, |
if necessary.
7. Lubricate motor and fan bearings, if not sealed. Check alignment of motor and fan.
| Up to 10 tons |
| Clean fan or blower. |
| Over 10 tons |
| 8. Check belt tension and condition. Adjust or replace as required. |
9. Replace pre-filters if needed.
10. Replace final filters if needed.
11. Check and adjust vibration eliminators. Replace if required.
12. Check and tighten all electrical terminals, connections, and disconnect switches.
13. Remove all trash or debris from work area.
| Air Cooled Condenser |
| 1. System Understanding |
| 2Y |
| (condenser fan(s), and fan motor(s)) |
| 2. Remove debris from air screen and clean underneath unit. |
| * Other components (i.e. compressor) |
| 3. Pressure wash coil with coil cleaning solution. |
| are at a separate location to be serviced |
| 4. Straighten fin tubes with fin comb. |
| simultaneously |
| 5. Check electrical connections for tightness. |
6. Check mounting for tightness.
7. Check for and remove all corrosion or rust from unit and supporting steel, prime and
| Up to 5 tons |
| paint as necessary. |
| 5 ton to 20 tons |
| 8. Check fan blades and belts, if installed. Clean fan blades as necessary. |
| 20 ton to 60 tons |
| 9. Clean up work area. |
| Over 60 tons |
| 10. Clean exterior of motor surfaces of soil accumulation. |
11. Lubricate bearings according to horsepower ratings:
12. Add grease - use top quality grade lithium base grease unless otherwise noted.
13. Check motor windings for accumulation of soil. Blow out with air if required, air pressure must not exceed 30 psig.
14. Check hold down bolts and grounding straps for tightness.
| Equipment |
| Maintenance/Repair Action |
| Freq |
| Heat Pumps |
| 1. System Understanding |
| 4Y |
2. Check mounting bolts and tighten if needed.
3. Check fan for vibration or excessive noise. Lubricate fan and motor if required.
4. Clean air intake and screens; change filters as necessary.
| Up to 5 tons |
| 5. Brush or pressure wash coil surfaces. Straighten fins with fin comb. |
| 5 ton to 20 tons |
| 6. Check all electrical connections and fused disconnect switches. |
| 20 ton to 60 tons |
| 7. Clean exterior of motor surfaces of soil accumulation. |
| Over 60 tons |
| 8. Lubricate bearings according to horsepower ratings: |
9. Add grease - use good grade lithium base grease unless otherwise noted.
10. Check motor windings for accumulation of soil. Blow out with air if required, air pressure must not exceed 30 psig.
11. Check hold down bolts and grounding straps for tightness.
12. Clean up work area.
| Air Handler |
| 1. System understanding |
| 4Y |
| See C1/C2 for remote coil and damper |
| 2. Check fan blades for dust buildup and clean if necessary. |
| To be serviced simultaneously. |
| 3. Check fan blades and moving parts for cracks and excessive wear. |
4. Check bearing collar set screws on fan shaft to make sure they are tight.
5. Check dampers for dirt accumulations, clean as necessary.
6. Check damper actuators and linkage for proper operation. Adjust linkage on dampers if out of alignment.
| Under 5000 CFM (Under 12 tons) |
| 7. Lubricate mechanical connections of dampers sparingly. |
| 5001 to 15,000 CFM (12 ton to 40 tons) |
| 8. Clean coils by brushing, blowing, vacuuming, or pressure washing. |
| 15,000 to 30,000 CFM (40 ton to 75 tons) |
| 9. Use fin comb to straighten coil fins. |
| Over 30,000 CFM (over 75 tons) |
| 10. Flush and clean condensate pans and drains, remove all rust. Prepare metal and |
paint. Hose down coils and drain pans and wash with an appropriate solution.
11. Check belts for wear and cracks, adjust tension or alignment, and replace belts when necessary. Multi-belt drives shall only be replaced with matched sets.
TE#2 - 1
| Equipment |
| Maintenance/Repair Action |
| Freq |
12. Check rigid couplings for alignment on direct drives, and for tightness of assembly.
Check flexible couplings for alignment and wear.
13. Vacuum interior of unit.
14. Lubricate fan shaft bearings while unit is running. Add grease slowly until slight bleeding is noted from the seals. Do not over lubricate. Remove old or excess lubricant.
15. Clean and wash permanent filters. Recharge wire mesh filters with oil.
16. Replace disposal filters.
17. Clean up work area.
18. Whole building of open and cleaning strainer inside, including FCU strainer.
19. Cover insulation.
| Remote Air Intake Damper |
| Remote Air Intake Damper |
| 4Y |
1. Check damper for freedom of movement and proper operation.
2. Observe damper operation through full operating range, by activating controller.
Adjust linkage on vanes if out of alignment.
3. Check damper surfaces for wear and clean vanes.
4. Check actuator/damper linkage for proper operation. Adjust if needed. Tighten operator arm set screws.
5. Lubricate mechanical connections sparingly. Wipe off excess.
6. Check actuator for proper operation. If it does not stroke properly, check for binding drive stem.
7. Check for air leaks around actuator and in air line between controller and actuator.
8. Lubricate actuator linkage sparingly. Wipe off excess lubricant. DO NOT LUBRICATE actuator/drive stem.
9. Clean off any corrosion or rust on damper frame and or damper blades, coat with proper type and color paint.
| Coil, Preheat, Reheat and etc., |
| Coil, Preheat, Reheat and etc., Remote Area |
| 2Y |
| Remote area |
| 1. Vacuum or blow out the fins, coils, etc. |
2. Clean and wash permanent filters. Recharge wire mesh filters with oil.
3. Replace disposal filters.
4. Check coils. Report any leaks.
5. Check for rust or corrosion around coil frame and coil mounting bracket. Clean, prepare for painting and coat with proper type paint as necessary.
| Equipment |
| Maintenance/Repair Action |
| Freq |
| Condensing Unit, Refrigeration |
| 1. System Understanding |
| 2Y |
| Up to 5 tons |
| 2. Remove debris from air screen and clean underneath unit. |
| 5 ton to 20 tons |
| 3. Pressure wash coil with coil cleaning solution. Rinse and neutralize (cleaning solution) |
| 20 tons to 60 tons |
| in accordance with manufacturer's recommendations. |
| Over 60 tons |
| 4. Straighten fin tubes with fin comb. |
5. Check electrical connections for tightness.
6. Check mounting for tightness.
7. Check all refrigeration lines for support and signs of wear.
8. Thoroughly inspect and clean interior and exterior of machine.
9. Clean and treat all rusted areas. Touch up prime and paint as needed.
10. Perform required lubrication and remove old or excess lubricant.
11. Clean motor with vacuum or low-pressure air (less than 40 psi). Check for obstructions in motor cooling and airflow.
12. Check fan blades for dust buildup and clean if necessary.
13. Check fan blades and moving parts for excessive wear.
14. Check bearing collar set screws on fan shaft to make sure they are tight, if applicable.
15. Clean up the work area and properly dispose of debris and waste.
| Equipment |
| Maintenance/Repair Action |
| Freq |
| Circulation Pump, Chiller Pump, Heating Pump, Hot Water Pump |
| 1. Inject Lubrication oil or grease. |
| 2Y |
2. Inspect Coupling. Replace worn, damaged, loose couplings.
3. Clean strainer inside.
4. Check hold down bolts and grounding straps for tightness.
| Fan Coil Unit (under window, ceiling |
| 1. System understanding |
| 2Y |
| hung, VAV box with Electric Heat) |
| 2. Check unit for noise and vibration. |
3. Check V-belt condition and tension. Adjust if needed, or replace.
4. Clean and wash permanent filters. Recharge wire mesh filters with oil.
5. Replace disposal filters.
6. Drain and clean condensate pan.
7. Lubricate fan shaft bearings (if not sealed).
8. Lubricate motor bearings sparingly using SAE 10W motor oil (if not sealed).
9. Clean coils by vacuuming or brushing.
10. Use fin comb to straighten coil fins.
11. Clean strainers for accumulation of dirt.
12. Clean fan blades and interior unit surfaces to remove soil.
13. Damp wipe exterior surfaces.
14. Clean surrounding floor area, and remove any dirt and debris from work area.
15. Clean and maintain whole building strainer. Replace if damaged, missing, or needed.
| For VAV boxes with heat coil: |
| 2Y |
1. Check to see that operating control-stat activates damper/control valve per design specifications. Report to the COR if malfunctioning.
2. Check damper linkage for tightness or damage. Lightly oil moving parts.
3. Inspect dampers for free movement in duct or mixing box. Replace felt or other type seals as required.
4. Inspect mixing box and connecting ducts for air leaks. Correct leaks with duct tape or tighten connections as required.
5. Inspect damper activators for tightness to mounting brackets.
6. Tighten electrical connections to servomotors. Clean vent ports.
7. If pneumatic actuator does not stroke properly, correct sticking valve stem or binding linkage. Replace diaphragm if necessary.
8. Inspect for air leaks around actuator and in air line between controller and actuator.
9. Check unit for noise and vibration.
10. Check V-belt condition and tension. Adjust or replace as necessary.
11. If filters are installed, Clean and wash permanent filters. Recharge wire mesh filters.
12. Replace disposable filters.
13. Lubricate fan shaft bearings if not sealed.
14. Lubricate motor bearings sparingly, using SAE 10w motor oil if not sealed.
15. Clean coils by vacuuming or brushing.
16. Clean fan blades and interior surfaces of unit to remove soil.
17. Damp wipe exterior surfaces.
18. Clean up work area.
| Equipment |
| Maintenance/Repair Action |
| Refrigeration Machine, Reciprocating |
| Major components (i.e. compressors, controls) will be maintained by the |
| 2Y |
| Or Scroll Compressor chiller |
| Government shop or other type of contract. The contractor shall maintain only air |
| Under 40 tons |
| condenser area |
40 - 80 tons
| 80 to150 tons |
| 1. Remove debris from air screen and clean underneath unit. |
2. Pressure wash coil with coil cleaning solution.
3. Straighten fin tubes with fin comb.
4. Check for and remove all corrosion or rust from unit and supporting steel, prime and paint as necessary.
5. Check fan blades. Clean fan blades as necessary.
| Refrigeration Machine, Rotary Screw |
| Major components (i.e. compressors, controls) will be maintained by the |
| 2Y |
| Chiller |
| Government shop or other type of contract. The contractor shall maintain only air |
| 100 to 200 tons |
| condenser area |
over 250 tons
1. Remove debris from air screen and clean underneath unit.
2. Pressure wash coil with coil cleaning solution.
3. Straighten fin tubes with fin comb.
4. Check for and remove all corrosion or rust from unit and supporting steel, prime and paint as necessary.
5. Check fan blades. Clean fan blades as necessary.
| Exhaust Fan, Heating Ventilator |
| 1. System Understanding. |
| 4Y |
| Energy Recovery Unit, |
| 2. Check fan blades for dust buildup and clean if necessary. |
3. Check fan blades and moving parts for cracks and excessive wear.
4. Check bearing collar set screws on fan shaft to make sure they are tight.
5. Check dampers for dirt accumulations, clean as necessary. Check felt and repair or replace as necessary.
6. Check damper actuators and linkage for proper operation. Adjust linkage on dampers if out of alignment.
7. Lubricate mechanical connections of dampers sparingly.
8. Clean coils by brushing, blowing, vacuuming, or pressure washing.
9. Use fin comb to straighten coil fins.
10. Flush and clean condensate pans and drains, remove all rust. Prepare metal and
Paint. Hose down coils and drain pans and wash with appropriate solution.
11. Check belts for wear, cracks, adjust tension or alignment, and replace belts when necessary.
12. Check rigid couplings for alignment on direct drives for tightness of assembly.
13. Vacuum interior of unit
14. Lubricate fan shaft bearings while unit is running. Add grease slowly until slight bleeding is noted from the seal, do not over lubricate. Remove old or excessive grease.
15. Clean and wash permanent filters. Recharge wire mesh filters with oil.
16. Replace disposal filters.
17. Clean up work area.
| Seasonal Inspection |
| Seasonal Inspection Requirements |
| 1. Inspect A/C Chiller equipment (before and after cooling season) |
| 2Y |
| 2. Inspect Chiller Pumps (before and after cooling season) |
| 2Y |
| 3. Inspect Split A/C (before and after cooling season) |
| 2Y |
| 4. Inspect Heating Pumps (before and after heating season) |
| 2Y |
| 5. Inspect Domestic Hot Water Pumps (before and after heating season) |
| 2Y |
Frequency:
| 2Y |
| Seasonal Inspection |
| 2Y |
| Semi-Annual |
| 4Y |
| Quarterly |