Tabulation of Bids - FW - WHRI 13(1).pdf
PDF 698 KB Posted
- Attached to
- White River National Wildlife Refuge
- Solicitation number
- 693C73-20-C-000027
About this file
This document contains a tabulation of bids report and award notice for a federal contract opportunity. The report details bids received on July 30, 2020 for the rehabilitation of Jack's Bay Landing Road (Route 13) within the Dale Bumpers White River National Wildlife Refuge in Arkansas. The apparent low bid of $1,667,590 was submitted by LaForge and Budd Construction Company, with a material incentive of $45,050, for a total awarded contract value of $1,712,640. The contract was awarded on August 26, 2020 under solicitation number 693C73-20-C-000027 by the Department of Transportation Federal Highway Administration. The project scope involves road and culvert rehabilitation work, erosion control measures, signage and other site improvements. The engineer's estimate was $1,480,000, making the low bid approximately 12.68% higher.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tabulation of Bids Report Date: 07/30/20
1 out of 8
Project No: FW-WHRI 13(1)
Project Name: Rehabilitation of Jack's Bay Landing Road (Route 13)
Schedule: A
Schedule Type: Base
Solcitation No: 693C73-20-B-000022
Division: Eastern Federal Lands
State: AR County: Arkansas
Federal Land: Dale Bumpers White River National Wildlife Refuge Opened at: Sterling, VA
Opened by: Shawn C. Long
Date: 07/30/20
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: Yuliya Kent
Title: Contract Specialist
Date: 07/30/2020
Contract Awarded to: LaForge and Budd Construction Company, Inc. Award Date: 08/26/2020
Contractor Comment Bid Amount Responsive
La Forge and Budd Construction Company, Inc. $1,667,590.00 2020 North 21st Street Parsons Kansas 67357
GC Works, Inc. $1,988,570.25 1820 SW 3rd Avenue Miami Florida 33129
Construction Solutions Group, LLC $2,190,947.30 5512 Elk Valley Estates Dr St. Louis Missouri 63128
Engineer's Estimate $1,480,000.00
2 out of 8
Project No: FW-WHRI 13(1)
Project Name: Rehabilitation of Jack's Bay Landing Road (Route 13)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0020 15101-0000 MOBILIZATION
La Forge and Budd Construction Company, Inc. Lump Sum $185,000.00 GC Works, Inc. Lump Sum $209,020.00 Construction Solutions Group, LLC Lump Sum $85,000.00 Engineer's Estimate ALL LPSM Lump Sum $104,100.00
A0040 15201-0000 CONSTRUCTION SURVEY AND STAKING
La Forge and Budd Construction Company, Inc. Lump Sum $40,000.00 GC Works, Inc. Lump Sum $39,044.00 Construction Solutions Group, LLC Lump Sum $35,500.00 Engineer's Estimate ALL LPSM Lump Sum $29,600.00
A0060 15401-0000 CONTRACTOR TESTING
La Forge and Budd Construction Company, Inc. Lump Sum $40,000.00 GC Works, Inc. Lump Sum $37,752.00 Construction Solutions Group, LLC Lump Sum $35,500.00 Engineer's Estimate ALL LPSM Lump Sum $29,600.00
A0080 15702-5000 SOIL EROSION CONTROL, TEMPORARY DIVERSION BERM (STATION 36+33)
La Forge and Budd Construction Company, Inc. Lump Sum $15,000.00 GC Works, Inc. Lump Sum $37,752.00 Construction Solutions Group, LLC Lump Sum $24,850.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00
A0100 15702-5000 SOIL EROSION CONTROL, TEMPORARY DIVERSION BERM (STATION 60+26)
La Forge and Budd Construction Company, Inc. Lump Sum $25,000.00 GC Works, Inc. Lump Sum $37,752.00 Construction Solutions Group, LLC Lump Sum $22,365.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00
A0120 15705-0100 SOIL EROSION CONTROL, SILT FENCE
La Forge and Budd Construction Company, Inc. $3.00 $9,300.00 GC Works, Inc. $2.50 $7,750.00 Construction Solutions Group, LLC $19.17 $59,427.00 Engineer's Estimate 3,100 LNFT $9.00 $27,900.00
3 out of 8
Project No: FW-WHRI 13(1)
Project Name: Rehabilitation of Jack's Bay Landing Road (Route 13)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0140 15705-0500 SOIL EROSION CONTROL, TEMPORARY CULVERT PIPE (FLEXIBLE TUBING)
La Forge and Budd Construction Company, Inc. $100.00 $15,000.00 GC Works, Inc. $188.75 $28,312.50 Construction Solutions Group, LLC $56.80 $8,520.00 Engineer's Estimate 150 LNFT $30.00 $4,500.00
A0160 15706-2200 SOIL EROSION CONTROL, FILTER BAG (STATION 36+33)
La Forge and Budd Construction Company, Inc. $2,500.00 $2,500.00 GC Works, Inc. $4,404.50 $4,404.50 Construction Solutions Group, LLC $4,970.00 $4,970.00 Engineer's Estimate 1 EACH $1,200.00 $1,200.00
A0180 15706-2200 SOIL EROSION CONTROL, FILTER BAG (STATION 60+26)
La Forge and Budd Construction Company, Inc. $2,500.00 $2,500.00 GC Works, Inc. $4,404.50 $4,404.50 Construction Solutions Group, LLC $4,970.00 $4,970.00 Engineer's Estimate 1 EACH $1,200.00 $1,200.00
A0200 20220-1000 REMOVAL, INDIVIDUAL TREE
La Forge and Budd Construction Company, Inc. $2,000.00 $2,000.00 GC Works, Inc. $3,146.00 $3,146.00 Construction Solutions Group, LLC $2,130.00 $2,130.00 Engineer's Estimate 1 EACH $1,000.00 $1,000.00
A0220 20301-1100 REMOVAL OF GATE
La Forge and Budd Construction Company, Inc. $1,000.00 $3,000.00 GC Works, Inc. $1,887.50 $5,662.50 Construction Solutions Group, LLC $2,130.00 $6,390.00 Engineer's Estimate 3 EACH $1,200.00 $3,600.00
A0240 20301-1200 REMOVAL OF HEADWALL (AND WINGWALLS)
La Forge and Budd Construction Company, Inc. $8,000.00 $16,000.00 GC Works, Inc. $9,438.00 $18,876.00 Construction Solutions Group, LLC $2,485.00 $4,970.00 Engineer's Estimate 2 EACH $930.00 $1,860.00
4 out of 8
Project No: FW-WHRI 13(1)
Project Name: Rehabilitation of Jack's Bay Landing Road (Route 13)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0260 20301-2400 REMOVAL OF SIGN
La Forge and Budd Construction Company, Inc. $300.00 $2,100.00 GC Works, Inc. $188.75 $1,321.25 Construction Solutions Group, LLC $710.00 $4,970.00 Engineer's Estimate 7 EACH $260.00 $1,820.00
A0280 20302-2100 REMOVAL OF PIPE CULVERT
La Forge and Budd Construction Company, Inc. $30.00 $10,500.00 GC Works, Inc. $113.25 $39,637.50 Construction Solutions Group, LLC $31.24 $10,934.00 Engineer's Estimate 350 LNFT $32.00 $11,200.00
A0300 20401-0000 ROADWAY EXCAVATION
La Forge and Budd Construction Company, Inc. $35.00 $6,475.00 GC Works, Inc. $82.00 $15,170.00 Construction Solutions Group, LLC $28.40 $5,254.00 Engineer's Estimate 185 CUYD $60.00 $11,100.00
A0320 20403-0000 UNCLASSIFIED BORROW
La Forge and Budd Construction Company, Inc. $50.00 $3,000.00 GC Works, Inc. $82.00 $4,920.00 Construction Solutions Group, LLC $28.40 $1,704.00 Engineer's Estimate 60 CUYD $60.00 $3,600.00
A0340 20425-1000 DITCH, EXCAVATION
La Forge and Budd Construction Company, Inc. $18.00 $5,040.00 GC Works, Inc. $56.75 $15,890.00 Construction Solutions Group, LLC $25.56 $7,156.80 Engineer's Estimate 280 LNFT $45.00 $12,600.00
A0360 20701-0200 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 1, TYPE B
La Forge and Budd Construction Company, Inc. $3.00 $2,100.00 GC Works, Inc. $3.50 $2,450.00 Construction Solutions Group, LLC $6.75 $4,725.00 Engineer's Estimate 700 SQYD $4.00 $2,800.00
5 out of 8
Project No: FW-WHRI 13(1)
Project Name: Rehabilitation of Jack's Bay Landing Road (Route 13)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0380 20701-1000 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 2, TYPE E
La Forge and Budd Construction Company, Inc. $2.50 $120,000.00 GC Works, Inc. $3.50 $168,000.00 Construction Solutions Group, LLC $4.62 $221,760.00 Engineer's Estimate 48,000 SQYD $5.00 $240,000.00
A0400 30101-0000 AGGREGATE BASE
La Forge and Budd Construction Company, Inc. $50.00 $12,500.00 GC Works, Inc. $53.50 $13,375.00 Construction Solutions Group, LLC $78.10 $19,525.00 Engineer's Estimate 250 TON $90.00 $22,500.00
A0440 30110-0000 AGGREGATE SURFACE COURSE
La Forge and Budd Construction Company, Inc. $53.00 $901,000.00 GC Works, Inc. $53.50 $909,500.00 Construction Solutions Group, LLC $74.55 $1,267,350.00 Engineer's Estimate 17,000 TON $35.00 $595,000.00
A0460 30302-1000 DITCH RECONDITIONING
La Forge and Budd Construction Company, Inc. $7.00 $17,500.00 GC Works, Inc. $19.00 $47,500.00 Construction Solutions Group, LLC $22.72 $56,800.00 Engineer's Estimate 2,500 LNFT $10.00 $25,000.00
A0480 60103-0000 CONCRETE, HEADWALL (AND WINGWALLS)
La Forge and Budd Construction Company, Inc. $15,000.00 $30,000.00 GC Works, Inc. $10,696.50 $21,393.00 Construction Solutions Group, LLC $23,430.00 $46,860.00 Engineer's Estimate 2 EACH $35,000.00 $70,000.00
A0500 60201-0800 24-INCH PIPE CULVERT
La Forge and Budd Construction Company, Inc. $125.00 $11,250.00 GC Works, Inc. $283.25 $25,492.50 Construction Solutions Group, LLC $99.40 $8,946.00 Engineer's Estimate 90 LNFT $110.00 $9,900.00
6 out of 8
Project No: FW-WHRI 13(1)
Project Name: Rehabilitation of Jack's Bay Landing Road (Route 13)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0520 60201-1000 36-INCH PIPE CULVERT
La Forge and Budd Construction Company, Inc. $175.00 $12,250.00 GC Works, Inc. $314.50 $22,015.00 Construction Solutions Group, LLC $220.10 $15,407.00 Engineer's Estimate 70 LNFT $120.00 $8,400.00
A0540 60201-1100 42-INCH PIPE CULVERT
La Forge and Budd Construction Company, Inc. $180.00 $6,300.00 GC Works, Inc. $377.50 $13,212.50 Construction Solutions Group, LLC $340.80 $11,928.00 Engineer's Estimate 35 LNFT $130.00 $4,550.00
A0560 60202-0200 18-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT
La Forge and Budd Construction Company, Inc. $150.00 $4,500.00 GC Works, Inc. $188.75 $5,662.50 Construction Solutions Group, LLC $95.85 $2,875.50 Engineer's Estimate 30 LNFT $110.00 $3,300.00
A0580 60202-0400 24-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT
La Forge and Budd Construction Company, Inc. $160.00 $10,400.00 GC Works, Inc. $377.50 $24,537.50 Construction Solutions Group, LLC $156.20 $10,153.00 Engineer's Estimate 65 LNFT $120.00 $7,800.00
A0600 60221-3000 10 FEET SPAN, 5 FEET RISE REINFORCED CONCRETE BOX CULVERT, SINGLE BARREL
La Forge and Budd Construction Company, Inc. $2,000.00 $60,000.00 GC Works, Inc. $1,887.50 $56,625.00 Construction Solutions Group, LLC $2,485.00 $74,550.00 Engineer's Estimate 30 LNFT $3,000.00 $90,000.00
A0620 61902-1900 GATE, METAL, 26 FEET WIDTH
La Forge and Budd Construction Company, Inc. $5,000.00 $15,000.00 GC Works, Inc. $18,876.00 $56,628.00 Construction Solutions Group, LLC $7,100.00 $21,300.00 Engineer's Estimate 3 EACH $5,500.00 $16,500.00
7 out of 8
Project No: FW-WHRI 13(1)
Project Name: Rehabilitation of Jack's Bay Landing Road (Route 13)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0640 61904-0000 BOLLARD POST
La Forge and Budd Construction Company, Inc. $250.00 $9,000.00 GC Works, Inc. $377.50 $13,590.00 Construction Solutions Group, LLC $355.00 $12,780.00 Engineer's Estimate 36 EACH $325.00 $11,700.00
A0660 62502-0000 TURF ESTABLISHMENT
La Forge and Budd Construction Company, Inc. $4.00 $3,200.00 GC Works, Inc. $7.50 $6,000.00 Construction Solutions Group, LLC $10.65 $8,520.00 Engineer's Estimate 800 SQYD $7.00 $5,600.00
A0680 62903-0000 CELLULAR CONFINEMENT SYSTEM
La Forge and Budd Construction Company, Inc. $25.00 $17,500.00 GC Works, Inc. $56.75 $39,725.00 Construction Solutions Group, LLC $35.50 $24,850.00 Engineer's Estimate 700 SQYD $90.00 $63,000.00
A0700 63304-0900 SIGNS, ALUMINUM PANELS, TYPE 3 SHEETING
La Forge and Budd Construction Company, Inc. $125.00 $37,500.00 GC Works, Inc. $69.25 $20,775.00 Construction Solutions Group, LLC $49.70 $14,910.00 Engineer's Estimate 300 SQFT $65.00 $19,500.00
A0720 63503-0300 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
La Forge and Budd Construction Company, Inc. $75.00 $2,625.00 GC Works, Inc. $157.50 $5,512.50 Construction Solutions Group, LLC $213.00 $7,455.00 Engineer's Estimate 35 LNFT $75.00 $2,625.00
A0740 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
La Forge and Budd Construction Company, Inc. $30.00 $2,550.00 GC Works, Inc. $44.00 $3,740.00 Construction Solutions Group, LLC $85.20 $7,242.00 Engineer's Estimate 85 SQFT $17.00 $1,445.00
8 out of 8
Project No: FW-WHRI 13(1)
Project Name: Rehabilitation of Jack's Bay Landing Road (Route 13)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0760 63701-0000 FIELD OFFICE
La Forge and Budd Construction Company, Inc. $10,000.00 $10,000.00 GC Works, Inc. $22,022.00 $22,022.00 Construction Solutions Group, LLC $28,400.00 $28,400.00 Engineer's Estimate 1 EACH $15,500.00 $15,500.00
Total Schedule - All Items
La Forge and Budd Construction Company, Inc. $1,667,590.00 GC Works, Inc. $1,988,570.25 Construction Solutions Group, LLC $2,190,947.30 Engineer's Estimate $1,480,000.00
Bid Error Report
1 out of 2
Project No: FW-WHRI 13(1)
Project Name: Rehabilitation of Jack's Bay Landing Road (Route 13)
Schedule: A
Schedule Type: Base
Bid Item Check Pass
Bidder Line Item Number Bidder's Extension Computed Extension
No Line Item Errors Found
Bid Error Report
2 out of 2
Project No: FW-WHRI 13(1)
Project Name: Rehabilitation of Jack's Bay Landing Road (Route 13)
Schedule: A
Schedule Type: Base
Bid Total Check Pass
Bidder Bidder's Bid Amount Computed Bid Amount Error
GC Works, Inc. $1,988,570.25 $1,988,570.25
Construction Solutions Group, LLC $2,191,447.30 $2,190,947.30 X
La Forge and Budd Construction Company, Inc. $1,667,590.00 $1,667,590.00
The apparent low bidder is 12.68% above the engineer's estimate.