Tab 04 SOW.pdf

PDF 117 KB Posted

Attached to
Vacuum-Rated Ejector Driven Reactant Manifold Assembly
Solicitation number
Not on record
Issued by

About this file

This is a Statement of Work (SOW) for NASA's Sustained Energy for the Lunar surface ENabled by Electrochemistry (SELENE) Project, with Teledyne Energy Systems, Inc. (TESI) as the contractor.

The SOW requires TESI to manufacture a vacuum-rated ejector-driven reactant (EDR) manifold assembly suitable for use as a component in a complete 64-cell EDR fuel cell stack. The primary tasks include conducting a manufacturing readiness review with presentation to NASA Glenn Research Center (GRC); placing purchase orders for all long lead time items and providing confirmation documentation; and preparing a manufacturing report upon completion that documents the manifold and includes reactant flow performance curves. Program management activities include a kick-off meeting within two weeks of contract award and biweekly, monthly, or as-needed status update meetings via teleconference. Four deliverables are required: a kick-off presentation (within 2 weeks of award), a manufacturing readiness review presentation (month 3), a procurement of long lead time items report (month 4), and an EDR manifold manufacturing report (month 5). All deliverables must be delivered electronically to the Contracting Officer (CO) and Contracting Officer's Representative (COR). The total contract period spans five months from award, with four defined milestones corresponding to each deliverable submission.

View the file

Other files

File Type Posted
Tab 07 Capability Statement.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 Statement of Work NASA’s Sustained Energy for the Lunar surface ENabled by Electrochemistry (SELENE) Project is developing a regenerative fuel cell (RFC) energy storage system that can be used to enable a sustained human presence on the lunar surface due to its ability to store significant amounts of energy for less mass than traditional battery systems. A key feature of an RFC system is the fuel cell (FC) that converts gaseous hydrogen and oxygen into water and useable electrical energy.

NASA’s SELENE Project is interested in testing the ejector-driven reactant (EDR) FC technology developed by Teledyne Energy Systems, Inc. (TESI) in a vacuum environment in order to generate crucial data and knowledge to inform RFC system design and possible integration into the system.

To address NASA’s needs, TESI shall execute the following statement of work (SOW).

1.1 Manufacture a Vacuum-Rated EDR Manifold Assembly

TESI shall manufacture an EDR manifold assembly rated for a vacuum environment that can potentially be used as a component of a complete 64-cell EDR FC stack. TESI shall provide data related to the completion of the manufacturing readiness review, purchase order placement for long lead time items, and manifold manufacturing report (containing reactant flow performance curves of the completed hardware).

1.1.1 Manufacturing Readiness Review

TESI shall conduct a manufacturing readiness review of the EDR manifold assembly and provide the presentation to NASA GRC.

1.1.2 Procurement of Long Lead Time Items

After the manufacturing readiness review, TESI shall provide a report to NASA GRC confirming that purchase orders have been placed for all long lead time items.

1.1.3 EDR Manifold Manufacturing Report

Upon the completion of the EDR manifold assembly, TESI shall prepare a manufacturing report documenting the completed manifold and reactant performance curves.

1.2 Program Management

Meetings shall be held throughout the execution of the SOW to provide updates on progress and finalize critical decisions for the remainder of the program. The meeting schedule is listed below in Table 1.

Table 1: Meeting Schedule

MEETING FREQUENCY/DATE DURATION LOCATION

Kick-Off Meeting

Within 2 weeks after contract award

Date and time to be mutually agreed upon by the Contractor and COR.

2 Hours

Location to be mutually agreed upon by the Contractor and

COR

Status Updates Biweekly, monthly, or as needed

1 Hour Via Telecon

2 Deliverables

Item No.

Task Ref.

Deliverable Description

Qty. Due Date Delivery Instructions

2.1 1.2 Kick-Off Presentation 1 EA Within 2 weeks after contract award

Delivered to COR and CO electronically (preferably via email)

2.2 1.1.1 Manufacturing Readiness Review Presentation

1 EA Month 3 Delivered to COR and CO electronically (preferably via email)

2.3 1.1.2 Procurement of Long Lead Time Items Report

1 EA Month 4 Delivered to COR and CO electronically (preferably via email)

2.4 1.1.3 EDR Manifold Manufacturing Report

1 EA Month 5 Delivered to COR and CO electronically (preferably via email)

3 Milestones

Milestone No.

SOW

Section

Description Objective Success Criteria Achievement

Date

1 1.2 Kick-Off Presentation Submission of the kick-off presentation

1 month after award

2 1.1.1 Manufacturing Readiness Review Presentation

Submission of the manufacturing readiness presentation

3 Months after award

3 1.1.2 Procurement of Long Lead Time Items Report

Submission of long lead time purchase order report

4 Months after award

4 1.1.3 EDR Manifold Manufacturing Report

Delivery of the manifold manufacturing report

5 Months after award