This document outlines requirements for a design-build project to renovate office space for the Office of Personnel Management in the Fort Lauderdale Courthouse. The contractor will provide design and construction services to convert 1646 square feet into offices, workstations, an IT room, storage, and other spaces. Architectural, security, network, and mechanical requirements are specified. The General Services Administration will issue a request for proposal on March 26, 2021, with a pre-proposal site visit on April 21. The period of performance is 210 days. The project budget is $250,000 to $500,000 and is 100% set aside for service-disabled veteran-owned small businesses. Interested parties should monitor the System for Award Management and the listed point of contact for updates.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work for
Design-Build (DB) Contract
PROJECT IDENTIFICATION
Project Name: Fort Lauderdale OPM New Office Build Up
Building Name: Fort Lauderdale FB - Courthouse
Building Address: 299 East Broward Boulevard Fort Lauderdale, FL 33301
Building #: FL0079ZZ
Scope Writer: Judith Ramos
07/18/2018
1 PROJECT DESCRIPTION
1.1 Project Type
This is an Alteration project.
The Design/Build Contractor (DB) shall provide Design and Construction for 1646 sf of space that will be occupied by the Office of Personnel Management at the third floor suite 324 of the Fort Lauderdale Courthouse. The DB contractor shall provide design and construction services to accomplish the project goals as defined in this document.
This work will be performed on an occupied floor in an occupied building. Meet applicable codes as well as GSA and agency design guides. Design the building systems as a compatible extension of the existing systems. The DB contractor will provide signed and sealed drawings for GSA review and approval. Provide cost estimates that support and validate the Estimated Construction Cost
1.2 Project Goals and Objectives
GOALS:
• Design 1646 sf of office space. The space distribution shall follow the following guidelines:
Type of Use Qty SF
Private Office 1 150
Private Office 1 120
Work Station 6 36
IT Room 1 80
Storage File 1 150
Interview Room 1 100
Conference Room 1 200
Reception Area 1 100
Office Machine Area 1 60
Circulation Area 1 470
The office design shall consider all MEP requirements to provide a functional space according to the attached proposed floor plan. Additionally the design shall address the following constrains:
Architectural:
• Perimeter walls, file storage room and LAN room wall shall be slab to slab and the material shall be resistant to unauthorized entry.
• Walls, ceiling and doors shall be made of a material that offers a minimum
STC of 45 or better. The STC rating of these rooms shall be tested to meet the requirement prior to occupancy.
• Entry doors with metal frame assembly shall be flush, solid core 1 3/4” thick or hollow steel construction. Door hinges shall be located on the interior side of the perimeter. One way film or blinds shall be provided at all entry doors.
• Interior Doors shall be flush solid core 1 3/4” thick or hollow steel construction. Doors shall be designed to preclude removal
• Doors to interview rooms, offices, or common workspaces must contain either a doorlite or have a sidelite.
• Exterior windows glass shall be at a minimum thermally tempered and heat strengthened. The DB contractor shall provide alternate pricing to provide hurricane resistant glass to the perimeter windows.
• Door Paint shall be low VOC semi-gloss oil based with no formaldehyde.
• Finishes TBD during first design review. The DB contractor shall provide a minimum of two choices for tenant agency decision.
Door Locks
• All three (3) exterior doors shall be equipped with a minimum 6-pin tumbler off-master deadbolt lock. In addition, the main entry door shall be augmented with a
KABA E-Plex 5800 series cipher lock and a HES 1006 electric strike or equivalent, and have an automatic door closer.
• The LAN Room Door shall be equipped with a Kaba Simplex 1000 manual cipher lock or equal.
• Doors to all private offices should be equipped with off-master key locks (a minimum of two keys provided)
Network System:
• The network cable system shall provide the connectivity of multiple microcomputers, printers and or terminals through a LAN environment. The network interface shall have the capability to support 1000 MBPS Ethernet through the network cabling. The network connections shall comply with the attached floor plans and abide by ANSI/ TIA/EIA 568-D series
• Horizontal cable shall be installed in accordance with the ANSI/TIA-569-D
“Telecommunications Pathways and Spaces” standard.
• All drops shall be labeled and administered in accordance with ANSI/TIA/EIA
606-A-2002 standard
• Install, test, terminate and label each work area with one tri faceplate outlet (one data and one split phone as shown in the attached floor plan.
• Terminate phone cable onto 66 blocks on ¾ inch plywood wall located in TR shown in floor plan.
• Provide 19” wide floor standing data rack for each data patch panel termination and equipment. And terminate data cable on Category 6 rated patch panel
(equipment type shall be recognized by name)
• Data rack must be secured to floor and located 4ft from back wall and equidistant from side walls.
• Provide ladder racks on TR for proper cable management
• Ground all cable and equipment in accordance to TIA- 607-B
• Install, terminate, test and label cable TV/satellite cable with RG-6 rated cable as shown in floor plan.
• Provide hard copy test results for all data cable installations on level III tester
• Provide patch cables (x at 2 meter and x at 3 meter) rated category 6.
• Provide xRG-6 coaxial cable adapters 10ft in length terminated with F-type connectors
• Provide xWA equipment and phone adapters
• Quantities will be determined at the first design review stage.
Specific LAN Room Design Requirements
• 180 sf with a minimum ceiling height of 8.5 ft. Lan Room shall be located around the center of the service area in order to minimize horizontal cable lengths to a maximum of 90m.
• No false ceiling
• Door 3”W x 80” H
• Floor must be static and dust free
• HVAC to maintain a temperature between 64-75 F and humidity between 30 and
55%. The approximate heat load of the area will be 7000W
• Sprinkler heads shall be caged
• Grounding according to TIA- 607-B standard
• Minimum lighting requirements 50 fc measured 3ft AFF. Lighting to be located on ceiling
• Paint color TBD during first design review.
• Lighting power to be separate from LAN equipment
• Provide a minimum of two dedicated non-switched 3-wire 120V duplex electrical outlets on separate branch circuits for equipment power.
• Provide independent outlets at 6ft intervals around the perimeter walls. Outlets shall be marked and identified.
• The 66 block for phone cable shall be mounted on plywood.
Intrusion Detection System
• The DB contractor shall supply and install one Bosch D9412Gv3 Control panel or equal in the LAN closet.
• The DB contractor shall supply and install one 12 volt DC LED keypad compatible to the Bosh control panel near the Main Entry Door, wiring connection and conduit as indicated in the security plan.
• The DB contractor shall supply and install three (3) GE 2700 Series Industrial
Door Contacts or equal. One at the Main Entrance and one at each terrace doors.
• The DB contractor shall supply and install a minimum of seven (7) GE Mirror
Optic AP669 ceiling mounted motion sensors as indicated in the security plan.
Motion sensor coverage is required for all walls abutting common or neighboring tenant space and any perimeter door. Place sensors as appropriate.
Approximate locations are shown on the security plan drawing.
• The DB contractor shall supply and install a minimum of four (4) duress buttons that are tied into the control panels as indicated in the security plan. Locations
TBD during first design review.
• The DB contractor will supply and install one (1) Aiphone JOS-1V audio/video intercom system at the main entry or equal. The base station will be connected to the main entry electric strike for remote release capability.
• The electrical power for the security system shall be tied to the building’s existing electrical power.
• Temporary battery backup shall be provided to power the IDS system to supply a minimum of 48 hours of backup power in case of an electrical outage.
• An analog POTS telephone line shall be required for the alarm panel.
OBJECTIVES:
Provide signed and sealed construction documents. Upon approval, execute the construction portion of the project. Provide as-built drawings as needed.
1.3 Project Delivery Approach
Work shall be performed by a qualified Design-Build contractor who follows the Design-
Build project delivery method. The Design Build contractor is responsible for Design services provided by the Architect-Engineer firm during Project Design phase as well as
Construction services provided during the Project Construction Phase.
1.4 Reference Material
Design and construction work shall comply, as a minimum, with the latest edition and most restrictive of all applicable national and local codes and standards that govern this building in Fort Lauderdale, FL. The following items are found in the appendix of this document to aid the DB as reference material as it relates to the building conditions:
• Existing building floor plans
• OPM tentative floor plan
2 GENERAL REQUIREMENTS
The requirements set forth in this section apply to all stages and phases of the project as described in the Scope of Services section below. Some of the requirements of this section may be subject to exercise of contract option(s).
2.1 Contract Parties and Contract Work
The parties to this contract are the Contractor, hereinafter referred to as the Design-
Build (DB) Contractor, and the United States Government. For purposes of this contract, the office representing the Government is the General Services Administration (GSA), Southeast Sunbelt (R04) Region, Public Buildings Service hereinafter referred to as the
GSA. The individual authorized to act on the behalf of the GSA in the administration of this contract is the GSA Contracting Officer. The GSA Contracting Officer may delegate certain of his or her authorities to others, and if so, will notify the DB Contractor in writing of the specific authorities delegated to, and limitations placed upon, named authorized representatives. The DB Contractor shall not take any direction, or act upon any information, from individuals other than those having the requisite authority as confirmed by the GSA Contracting Officer’s written notification. This contract includes both Design services and Construction work, all to be performed by the DB Contractor.
Design services include providing Design and Construction Document services, construction administration services, as-build records, inspection services and reports.
Construction Stage work includes performing construction in conformance with the specified period of performance. The DB Contractor shall proceed with the Design services upon receipt of the GSA notice to proceed with that portion of the work. The
GSA will issue a notice to proceed with the Construction work upon completion of the
Design Stage services and the GSA approval of the DB Contractor Construction
Document submission. The specific activities, tasks, and deliverables required of the DB
Contractor are further delineated in this Statement of Work.
2.2 Project Delivery Team Roles and Responsibilities
In the performance of the requirements of this contract, the DB Contractor shall work in concert with other parties on the Project Delivery Team. The Project Delivery Team will include the GSA personnel, customer agency representatives, and other stakeholders.
The GSA will develop, periodically update, and maintain throughout the course of the project, a listing of the Project Delivery Team membership and respective roles and responsibilities. The GSA may engage other parties to perform specialized duties and requirements as appropriate for the project.
2.3 Budget
The estimated range for construction costs is between $250,000.00 and $500,000.00 which includes the DB Contractor fixed prices for Design Stage services.
2.4 Schedule / POP
Funding for the project has been secured. Project design duration is estimated at 90 calendar day and construction at 120 days for a 210 days total POP. Milestones relating to the DB effort are listed in Section 4 of this document.
2.5 DB Contractor Team
The DB Contractor shall provide experts in disciplines listed in PBS-P100, Facilities
Standards for the Public Buildings Service, and as otherwise required in this section, with credentials as indicated, as they apply to this project. The DB Contractor shall provide sufficient staff of project managers, architects, design engineers, superintendents, inspection and testing engineers, cost engineers, clerical and accounting personnel, etc. to perform the required work.
At a minimum, the DB Contractor key team members shall consist of the following:
• Project Manager
• Architectural Designer
• Engineering Designers – Electrical, Mechanical, Fire Protection
• Construction Duperintendent
The DB Contractor shall utilize the personnel named in its offer to perform the services required under this contract. In the event that any of the personnel named in the DB
Contractor accepted proposal (incorporated into this contract by reference) become unavailable, the DB Contractor shall promptly submit a complete written resume for a proposed substitution, any other information necessary for the GSA to approve or disapprove, and a detailed explanation of the circumstances necessitating the proposed substitution.
In addition to the key team members identified above, the DB Contractor shall provide administrative, clerical, and technical personnel as necessary to perform the services required under this contract. During the performance of the services required under this contract, the DB contractor shall obtain the GSA written consent before making any substitution for subcontractors and outside associates or consultants specifically identified and agreed to during negotiations. See FAR 52.236-5, Material and
Workmanship, regarding removal of any employee deemed incompetent, careless, or otherwise objectionable. See also FAR 52.244-4 regarding subcontractors and outside associates and consultants.
2.6 Performance Objectives
2.6.1 Standards and Criteria Documents
2.6.1.1 Applicability
All services must be conducted in accordance with the documents listed below. The applicable version of each document shall be the version current at the time of award of this contract. In the event of a conflict between the requirements stated in these documents and requirements provided elsewhere in this Statement of Work, the requirements in the Statement of Work will prevail.
2.7 Document List
PBS-P100, Facilities Standards for the Public Buildings Service, including all applicable standards, criteria and guides listed therein Design Stage submissions must comply with PBS-P100 Appendix A unless otherwise indicated in this Statement of Work. The following documents are in addition to those contained in PBS-P100.
• PBS P-120, Project Estimating Requirements for the Public Buildings Service
2.8 Sustainable Design/LEED®
The GSA is committed to incorporating principles of sustainable design and energy efficiency into all of its building projects.
Green Purchasing Plan
The GSA is required to buy recovered materials as designated by the U.S.
Environmental Protection Agency (EPA) through the comprehensive procurement guidelines (CPG). Information can be obtained about the EPA list of designated products and accompanying recycled–content recommendations on the internet at www.epa.gov/cpg. Additional requirements for use of biobased, rapidly renewable content, and recycled content materials are as per P100 2010 page 94.
Miscellaneous Green Requirements
In addition, the contractor shall develop the design in a way that implements the following environmental objectives:
http://www.epa.gov/cpg
• Eliminate or reduce the generation of hazardous waste and the need for special material processing (including special handling, storage, treatment, and disposal)
• Promote the use of nonhazardous and recovered materials
• Realize life-cycle cost savings
• Promote cost-effective waste reduction when creating plans, drawings, specifications, standards, and other product descriptions authorizing material substitutions, extensions of shelf-life, and process improvements
• Promote waste reduction through the use of duplexing (two-sides copying and printing) and electronic communications
C&D Waste Management Requirements
GSA's minimum requirement is to divert 50% of C&D waste from landfills/incinerators, with a higher goal of 70% diversion. The design specifications completed by the A/E must be consistent with these goals. The A/E must include the template Construction
Waste Management and Disposal specification in the design. This document is a template and must be tailored to the project. The A/E must also include the C&D Waste
Management Report form as an attachment to the specification. Templates for both of these documents are attached to this document.
Waste Management Plan
A waste management plan shall be submitted at the completion of construction documents phase of the project or within 14 days of date established for the
Construction Notice-to-Proceed. The plan includes at the minimum the following requirements:
1. Describe strategies for minimizing waste
2. During project planning, include a bulk estimate in weight (tons) or volume
(cubic yards) of waste diverted and anticipated weight/volume for materials going to landfill.
3. Anticipated recycling revenue: Shall be factored into contractor bid and contractor should provide an estimate of the recycling proceeds amount.
4. Final rates based upon weight (tons).
5. List of diversion facilities and disposal activities to be used. (Include name, location, and phone number)
Waste Management Monthly Reports
Contractors are required to submit a monthly waste management report that details the amount of C&D waste by material diverted/recycled as well as the amount sent to landfill on the project. These reports shall be submitted to the GSA PM and/or COR in electronic format.
2.7.1 Fire Protection/Life Safety
Except as otherwise indicated in referenced programming documents, fire protection and life safety design requirements must comply with PBS-P100, Chapter 7. As provided in PBS-P100 Chapter 7, NFPA 101 is the primary applicable standard. In cases where NFPA is silent on an issue, and IBC addresses the issue, the IBC requirement will apply.
2.9 Cost Management
2.9.1 Cost Estimating
The estimated cost of the work (ECW) as provided in the DB Contractor proposal, including any modifications thereto as a result of final contract negotiation, shall serve as the baseline construction budget for the project at the time of award of the DB contract.
2.9.2 Construction Cost Management
This contract is for a firm fixed price for all design and construction services.
2.10 Project Management Responsibilities
2.10.1 Communications
The DB Contractor contractual responsibility is to the GSA only and not to other contractors, tenants agency or local community interests where the project is located.
The DB Contractor shall direct all questions and requests from tenant agencies and local community interests to the GSA. Prior to contacting any parties other than the
GSA regional personnel, the DB Contractor shall confirm all meetings and/or communications with the GSA. The DB Contractor shall not release any oral, written or graphic information regarding this project to outside sources without obtaining prior consent from the GSA. All requests for information concerning the project must be referred to the GSA for response.
2.10.2 Project Schedule
Before starting any other work, the DB Contractor shall develop and provide a schedule in Microsoft Project® or other approved scheduling software for completion of all Design
Stage activities, tasks, and submissions required herein, leading up to and including the final construction documents submission(s). After the DB Contractor receives notice to proceed with the Construction Stage work, the DB Contractor shall provide and maintain a detailed schedule in Microsoft Project® for completion of all Construction Stage activities, tasks, and submissions required herein.
2.10.3 Project Progress Meetings
During the Design Stage, the DB Contractor shall host project meetings, with the GSA group as required to keep all parties appraised of the design progress/status and impending activities. The DB Contractor shall also host special project technical meetings as needed involving Project Delivery Team technical disciplines
2.10.4 Meeting Agendas, Attendance, Minutes and Correspondence
The DB Contractor shall prepare and distribute an agenda for each DB Contractor hosted project meeting, in advance of the meeting date. DB Contractor representation at all meetings shall include those individuals having knowledge of the agenda topics and authority to make decisions and commit resources. The DB Contractor shall provide minutes of all DB Contractor hosted project meetings to all attendees identifying new and unresolved old action items and associated responsible parties. Minutes must be provided within seven calendar days after each meeting. The DB Contractor shall reply to correspondence from the GSA within 7 calendar days.
2.10.5 Design Quality Assurance
The GSA requires that DB Contractor design submissions undergo two general types of design review: owner’s review and codes and standards review.
2.10.5.1 Owner’s Review
GSA will perform owner’s reviews and provide thorough and detailed written review comments. The purpose is to ensure that established requirements of the project are satisfied.
2.10.5.2 Constructability
Constructability of the project as designed is the sole responsibility of the DB
Contractor. To ensure that the design can be constructed within schedule and budget and that the sequencing of construction is planned for optimum efficiency, the DB
Contractor should assure that:
• Materials, processes, equipment and labor are appropriate and available.
• Construction work required is in conformance with standard construction practices, and equipment, products, materials, fixtures, etc. are readily available in the marketplace, to the maximum extent possible.
• Building systems are compatible and viable.
• Drawings and specifications are complete and thoroughly coordinated among disciplines.
• Defects, omissions, inconsistencies, conflicts, and ambiguities in documents are identified.
• Site and building access, logistics, available storage and tenant occupancy requirements are accommodated.
• Existing conditions are shown correctly and adequately.
• Construction options and unit prices are logical, thoroughly described and understandable.
• Construction details are appropriate, complete, thoroughly described and workable.
• General requirements items are thorough and properly addressed.
• Construction documents provide for continuous use of all building systems
(including phone, data, fire alarm, security etc.) during all construction.
2.11 Electronic/Print Media
2.11.1 Computer Aided Design (CAD) Standards
Starting with the design submission all drawing materials provided by the DB
Contractor, including final as-built drawings must conform to the GSA PBS computer aided design (CAD) standards. Go to http://www.gsa.gov/cifm for requirements.
2.11.2 Other Electronic Documents
In addition to any hardcopy submission requirements, design submissions must also be submitted in an electronic format. All electronic media must be in a form readable by standard office automation applications.
2.11.3 Plans and Specifications
Provide 3 hardcopy sets of plans and specifications to GSA.
2.12 SECURITY CLEARANCE REQUIREMENTS
A. The Contractor shall agree to insert terms that conform substantially to the language of this clause, including the following, in all subcontracts.
B. The Contractor shall not be allowed to maintain keys to Tenant Agency (TA) space or permitted to have access to TA space without the approval of the TA, Physical
Security Unit
C. It is the responsibility of the Contractor to ensure all contractor personnel are in full compliance with applicable Immigration and Naturalization Service, US Department of Justice, Employee Eligibility Verification requirements, such as those set forth in Title
8, U.S. Code, Section 274a.
D. A background investigation, the scope of which will be at the discretion of the
TA, will be conducted on these individuals. At the discretion of the TA, contract individuals may also be interviewed by the TA (or TA contract investigators) regarding foreign travel, associates, residences or other matters of concern to the TA in deciding whether to grant access to its facilities, property, or information, and may be requested to undergo a polygraph examination to fully resolve any security concerns. Refusal or failure to accurately complete the forms, to be interviewed, or to undergo a polygraph examination to resolve any questionable matters will be deemed reasonable cause for denial of access to TA facilities, property or information. Lack of candor may also be a strong factor for denial of access.
E. Access to TA facilities, property or information, will be granted only where such access is clearly consistent with the mission and responsibilities of the TA. If, for any reason, a contract individual is denied access to any TA facility, property or information, the TA will not disclose to the contractor the reason for denial and will only make such disclosure to the affected contractor employee pursuant to the provisions of the
Freedom of Information or Privacy Acts. The TA will not be liable for any expense in the replacement of the individual or any costs incurred by the contractor as a result of such denial. It is the policy of the TA that these individuals already employed by the contracting organization/ individual (i.e., that the individual’s employment not hinge upon an access or security clearance determination by the TA) and the TA will assume no liability between the contracting organization and its employees as a result of this procedure.
F. The TA reserves the right to revoke any contract individual's access to its facilities, property or information, where such access is no longer clearly consistent with the TA's mission and responsibilities, and the contractor agrees to immediately remove that individual from the work site in such circumstances. In cases of access revocation, the TA will inform the individual of the basis for the revocation unless to do so would reveal classified or sensitive information; and provide the individual an opportunity to explain, rebut or refute such basis in writing. Access will remain revoked pending prompt review of any such submission by the individual.
G. The TA reserves the right to reinvestigate contract individuals on a periodic basis (usually every five years) or where facts or information indicate the continued access may no longer be clearly consistent with the TA’s mission and responsibilities. The scope of any reinvestigation will be at the sole discretion of the
TA. Refusal or failure to accurately complete any necessary forms, to be interviewed, or to undergo a polygraph examination to resolve any questionable matters during a reinvestigation will be deemed reasonable cause for revocation of access to TA facilities, property or information.
H. It is the responsibility of the Contractor to ensure all contractor personnel are in full compliance with applicable Immigration and Naturalization Service, US Department of
Justice, Employee Eligibility Verification requirements, such as those set forth in Title 8, U.S. Code, Section 274a.
2.13 Record Keeping
The DB is responsible for preparing correspondence and other documentation and maintaining accurate and detailed records of the project's progress. The DB is responsible to maintain records so as to facilitate document storage and retrieval. Refer to the Scope of Services section below for detailed requirements for project documentation.
2.14 Construction General Requirements
The construction specifications must be prepared following the GSA MasterFormat
2004 Version and must include Division 1 General Requirements. Additional
Construction Stage requirements are provided in the Construction Stage section of the
Scope of Services below.
3 SCOPE OF SERVICES
The DB Contractor shall perform all services described in this Scope of Services
(including services required under exercised options, if any) in accordance with applicable requirements and provisions set forth in the General Requirements above.
3.1 Design Stage
Conduct a Kick-Off Meeting with principal Project Delivery Team members and stakeholders prior to the start of work on the design. This time shall also be used by the
Project Delivery Team for field investigation. The meeting will facilitate analysis of building systems and components as applicable
3.1.1. Analyses and Calculations
Conduct analyses and provide supporting documentation for systems Selections as applicable.
3.1.4 Final CD (100% Design) Submissions
For all construction work to be self-performed and for each planned construction subcontract work package, prepare and submit separate final CD submissions in accordance with PBSP100 construction document submission requirements as they pertain to the scope of the construction work. The submission must consist of plans, specifications, cost estimates, and design narrative, including calculations. For all construction work to be self-performed and for each planned construction subcontract work package, provide a final construction specification, including Division 1 General
Requirements sections emphasizing project phasing, contractor requirements and project specific construction management issues. The construction specification must be prepared following the GSA MasterFormat 2004 Version and must include Division 1
General Requirements.
3.2 Construction Stage
Upon receipt of notice to proceed with the Construction Stage work, the DB Contractor shall perform all services described in this section as a part of the Construction Stage work.
3.2.1 Construction Delivery Phase
3.2.1.1 Construction Start Coordination
3.2.1.1.1 Pre-Construction Conference
Participate in the pre-construction conference.
3.2.1.2 Construction Administration
The AE of record will perform a final inspection of the installation and architectural finishes
3.2.1.2.1 Schedule of Values
Prepare and submit schedule of values for the GSA approval.
3.2.1.2.2 Construction Delivery Phase Recordkeeping
Contractor shall maintain project records inclusive but not limited to: daily logs, certified payroll, RFI logs, project correspondence.
3.2.1.2.3 Construction Progress Reporting
The contractor shall maintain all construction reports records included but not limited to :
material MSDS, inspection reports, testing reports.
3.2.1.2.4 Construction Safety Program
Contractor shall implement and maintain a safety program.
3.2.1.2.5 Project Progress Meetings
Contractor will hold weekly project progress meetings with the contract PM and additional stakeholders as needed.
3.2.1.2.6 Construction Schedules
The DB Contractor shall provide and maintain construction schedules in MS project.
The schedule shall calculate the project’s critical path, show float activities and dependencies. The schedule shall be updated monthly before submitting application for payment
3.2.1.2.7 Submittal Processing
Prepare and submit a submittal schedule. Ensure that all subcontractors understand, agree to, and conform with their respective roles, responsibilities, and timeliness requirements for submittal processing. Promptly correct and resubmit any submittals returned unapproved, allowing sufficient time for re-review in order to maintain the project schedule. Upon receipt of submittal approvals, coordinate as necessary with all involved subcontractors. Refer to FAR 52.236-21, Specifications and Drawings for
Construction, for further submittal and shop drawing review requirements. Expedite the processing of submittals to minimize approval times.
3.2.1.2.8 Inspections and Testing
Conduct inspections and tests as required.
3.2.1.2.9 Clarifications/Requests for Information/Change Orders
Each RFI must include a specific description of the issue requiring clarification, citing the specific related contract documents requiring clarification. RFI’s should only be submitted after performing due diligence to confirm that the contract requirements in question are in fact unclear or otherwise inadequate. Upon receipt of the response to each RFI submitted, coordinate the response with all involved subcontractors to ensure understanding and appropriate action. Provisions for use of the GSA share of shared savings will apply if the GSA agrees that additional work to be performed by the DB
Contractor as a result of resolution of an RFI is beyond the scope of work upon which the ECW was previously based. See the clause entitled Design-Build Contract
Guaranteed Maximum Price with Construction Contingency Allowance.
3.2.1.2.10 DB Contractor As-Built Drawings and Specifications
The DB Contractor shall update CAD drawings (as-built drawings) and electronic specifications (as-built specifications) to document changes that occur during construction.
3.2.1.2.11 DB Contractor Payment Requests
Update the construction schedules monthly prior to each payment request. Provide documentation evidencing the cost of work performed to be included in the payment request. Allowability of costs shall be in accordance with FAR 31.105 and 31.2. Before submitting each payment request, meet with GSA to review the advance copy of the construction progress report. Ensure that GSA is in agreement as to the progress of the construction work and the value of the work completed. Based upon agreed value of work completed, submit monthly payment requests to the GSA.
3.2.1.2.12 Construction Checklists
Complete the construction checklists as the work is accomplished.
3.2.1.3 Turnover Process
3.2.1.3.1 Substantial Completion
Prior to substantial completion, assist the GSA in conducting a pre-final walk-through with tenant agency.
3.2.1.3.2 Punch-List
After the GSA and local building authority’s certification that the work or each designated portion thereof is substantially complete conduct a final inspection and preparing a punch-list documenting remaining work. Participate in conducting follow-up inspections to administer resolution of punch-list items, involving the tenant agencies and other stakeholders as appropriate.
3.2.1.3.3 Warranties, Guarantees and Certificates
Prepare and submit warranties, guarantees, and certificates, ensuring that the GSA rights and responsibilities are clearly defined.
3.2.1.3.4 Final As-Built Drawings and Specifications
The DB Contractor shall prepare and submit final CAD as-built drawings and electronic as-built specifications for review and approval at the completion of the construction.
3.3 Closeout Stage
3.3.3 DB Contract Closeout
• Resolve all remaining punch-list items.
• Submit release of claims.
4 ADMINISTRATION
4.1 Submission, Review and DB Contractor Fixed Price Table
The table below lists the Design Stage activities and corresponding GSA review periods as described in the Scope of Services under Section 3 above, and itemizes the total negotiated Design Stage DB Contractor fixed price amounts by phase and submission as the basis for payment
Submission Submission Due Within
Review Period DB Contractor Fixed Price
50 % Construction Documents 45 days 7 days 90 % Construction Documents 30 days 7 days
100 % Construction Documents 7 days -
4.2 Payment for Construction Delivery Phase Work
Refer to FAR 52.232-5 Payments under Fixed-Price Construction Contracts and FAR
52.232-27 Prompt Payment for Construction Contracts.
4.3 Travel
Unless otherwise indicated in the Scope of Services sections, the DB Contractor is responsible for travel costs to support the requirements contained in this Statement of
Work, including all progress meetings, workshops, reviews, and site visits. The DB
Contractor shall assume all travel will be within the vicinity of the project site except as specifically indicated otherwise in the Scope of Services section.
4.4 Reproduction and Delivery
Printing, reproduction and delivery costs necessary for execution of this contract are included the contract price.