WORK LOCATION
SUNDANCE PARKING LOT VAULT TOILET PLAN 13
SUNDANCE PARKING LOT
THIEL ROAD
GENERAL NOTES:
1. CONTRACTOR IS RESPONSIBLE FOR ALL PUBLIC AND PRIVATE UTILITY LOCATES. COORDINATE WITH MONTANA 811 AND ANY OTHER NECESSARY ENTITIES.
2. CONTRACTOR TO SUPPLY CONCRETE VAULT TOILET.
3. CONTRACTOR TO EXCAVATE FOR VAULT TOILET PLACEMENT.
4. CONTRACTOR TO FIELD VERIFY ELEVATIONS OF THE EXISTING PARKING LOT AND ENSURE THAT THE FLOOR OF THE CONCRETE VAULT TOILET IS PLACED AT AN
ELEVATION 2' HIGHER THAN THE 1% ANNUAL CHANCE FLOOD ELEVATION.
5. GOVERNMENT SHALL PROVIDE A CONTROL POINT WITH A KNOWN ELEVATION FOR CONTRACTOR TO BASE ELEVATIONS ON.
6. BED THE VAULT TOILET WITH 8-INCHES OF 1.5"-MINUS CRUSHED AGGREGATE BASE COURSE (CABC) COMPACTED TO 95% OF THE MAXIMUM DRY DENSITY PER ASTM
D-698.
7. COMPACT THE SUBGRADE T0 95% OF THE MAXIMUM DRY DENSITY PER ASTM D-698.
8. CONTRACTOR TO RE-USE SUITABLE CUT MATERIAL FROM EXCAVATION FOR THE VAULT TOILET AS FILL MATERIAL TO MEET GRADE. CONTRACTING OFFICER
REPRESENTATIVE (COR) TO APPROVE OF ALL FILL MATERIALS PRIOR TO PLACEMENT.
9. CONTRACTOR TO SUPPLY 3"-MINUS FILL MATERIAL AS NEEDED TO MEET THE DRAWINGS AND SPECIFICATIONS. FILL MATERIAL SHALL BE COMPACTED TO 95% OF
THE MAXIMUM DRY DENSITY PER ASTM D-698.
10. 1.5"-MINUS CRUSHED AGGREGATE BASE COURSE SHALL BE COMPACTED TO 95% OF THE MAXIMUM DRY DENSITY PER ASTM D-698.
11. CONSULT WITH THE CONTRACTING OFFICER REPRESENTATIVE (COR) FOR THE REMOVAL AND REPLACEMENT LOCATIONS OF LANDSCAPE ROCK.
12. DISTURBANCE OF EXISTING VEGETATION SHALL BE MINIMIZED TO THE GREATEST EXTENT POSSIBLE. ALL AREAS DISTURBED BY CONSTRUCTION ACTIVITIES SHALL
BE REPAIRED.
13. CONTRACTOR SHALL PROVIDE ALL SIGNAGE TO CLOSE THE CONSTRUCTION AREA.
SUNDANCE VAULT TOILET PLAN 21A
GENERAL NOTES:
1. CONTRACTOR IS RESPONSIBLE FOR ALL PUBLIC AND PRIVATE UTILITY LOCATES. COORDINATE WITH
MONTANA 811 AND ANY OTHER NECESSARY ENTITIES.
2. CONTRACTOR TO SUPPLY CONCRETE VAULT TOILET.
3. CONTRACTOR TO EXCAVATE FOR VAULT TOILET PLACEMENT.
4. CONTRACTOR TO FIELD VERIFY ELEVATIONS OF THE EXISTING PARKING LOT AND ENSURE THAT THE FLOOR
OF THE CONCRETE VAULT TOILET IS PLACED AT AN ELEVATION 2' HIGHER THAN THE 1% ANNUAL CHANCE
FLOOD ELEVATION.
5. GOVERNMENT SHALL PROVIDE A CONTROL POINT WITH A KNOWN ELEVATION FOR CONTRACTOR TO BASE
ELEVATIONS ON.
6. BED THE VAULT TOILET WITH 8-INCHES OF 1.5"-MINUS CRUSHED AGGREGATE BASE COURSE (CABC)
COMPACTED TO 95% OF THE MAXIMUM DRY DENSITY PER ASTM D-698.
7. COMPACT THE SUBGRADE T0 95% OF THE MAXIMUM DRY DENSITY PER ASTM D-698.
8. CONTRACTOR TO RE-USE SUITABLE CUT MATERIAL FROM EXCAVATION FOR THE VAULT TOILET AS FILL
MATERIAL TO MEET GRADE. CONTRACTING OFFICER REPRESENTATIVE (COR) TO APPROVE OF ALL FILL
MATERIALS PRIOR TO PLACEMENT.
9. CONTRACTOR TO SUPPLY 3"-MINUS FILL MATERIAL AS NEEDED TO MEET THE DRAWINGS AND SPECIFICATIONS. FILL MATERIAL SHALL BE COMPACTED TO 95% OF THE MAXIMUM DRY DENSITY PER ASTM D-698.
10. 1.5"-MINUS CRUSHED AGGREGATE BASE COURSE SHALL BE COMPACTED TO 95% OF THE MAXIMUM DRY
DENSITY PER ASTM D-698.
11. CONSULT WITH THE CONTRACTING OFFICER REPRESENTATIVE (COR) FOR THE REMOVAL AND REPLACEMENT
LOCATIONS OF LANDSCAPE ROCK.
12. DISTURBANCE OF EXISTING VEGETATION SHALL BE MINIMIZED TO THE GREATEST EXTENT POSSIBLE. ALL
AREAS DISTURBED BY CONSTRUCTION ACTIVITIES SHALL BE REPAIRED.
VAULT TOILET DETAIL1A
CONCRETE SIDEWALK DETAIL2A
GENERAL NOTES:
1. CONTRACTOR IS RESPONSIBLE FOR ALL PUBLIC AND PRIVATE UTILITY LOCATES. COORDINATE WITH MONTANA 811 AND ANY OTHER NECESSARY ENTITIES.
2. CONTRACTOR TO SUPPLY CONCRETE VAULT TOILET.
3. CONTRACTOR TO EXCAVATE FOR VAULT TOILET PLACEMENT.
4. CONTRACTOR TO FIELD VERIFY ELEVATIONS OF THE EXISTING PARKING LOT AND ENSURE THAT THE FLOOR OF THE CONCRETE VAULT TOILET IS PLACED AT AN
ELEVATION 2' HIGHER THAN THE 1% ANNUAL CHANCE FLOOD ELEVATION.
5. GOVERNMENT SHALL PROVIDE A CONTROL POINT WITH A KNOWN ELEVATION FOR CONTRACTOR TO BASE ELEVATIONS ON.
6. BED THE VAULT TOILET WITH 8-INCHES OF 1.5"-MINUS CRUSHED AGGREGATE BASE COURSE (CABC) COMPACTED TO 95% OF THE MAXIMUM DRY DENSITY PER ASTM
D-698.
7. COMPACT THE SUBGRADE T0 95% OF THE MAXIMUM DRY DENSITY PER ASTM D-698.
8. CONTRACTOR TO RE-USE SUITABLE CUT MATERIAL FROM EXCAVATION FOR THE VAULT TOILET AS FILL MATERIAL TO MEET GRADE. CONTRACTING OFFICER
REPRESENTATIVE (COR) TO APPROVE OF ALL FILL MATERIALS PRIOR TO PLACEMENT.
9. CONTRACTOR TO SUPPLY 3"-MINUS FILL MATERIAL AS NEEDED TO MEET THE DRAWINGS AND SPECIFICATIONS. FILL MATERIAL SHALL BE COMPACTED TO 95% OF
THE MAXIMUM DRY DENSITY PER ASTM D-698.
10. 1.5"-MINUS CRUSHED AGGREGATE BASE COURSE SHALL BE COMPACTED TO 95% OF THE MAXIMUM DRY DENSITY PER ASTM D-698.
11. CONSULT WITH THE CONTRACTING OFFICER REPRESENTATIVE (COR) FOR THE REMOVAL AND REPLACEMENT LOCATIONS OF LANDSCAPE ROCK.
12. DISTURBANCE OF EXISTING VEGETATION SHALL BE MINIMIZED TO THE GREATEST EXTENT POSSIBLE. ALL AREAS DISTURBED BY CONSTRUCTION ACTIVITIES SHALL
BE REPAIRED.
| Sundance Vault Toilet - 1 - Cover Sheet-Layout1 |
| Sheets and Views |
| Layout1 |
| Sundance Vault Toilet - 2 - Project Maps-MAP |
| Sheets and Views |
| MAP |
| Sundance Vault Toilet - 3 - Plan Sheet 1-Layout1 |
| Sheets and Views |
| Layout1 |
| Sundance Vault Toilet - 4 - Plan Sheet 2-Layout1 |
| Sheets and Views |
| Layout1 |
| Sundance Vault Toilet - 5 - Detail Sheet 1-Layout1 |
| Sheets and Views |
| Layout1 |
File details come from the government source that posted it. Updated .