This is a Scope of Work document for a Request for Qualifications issued by the Town of Sterling, Connecticut, for a drinking water infrastructure project. The Town of Sterling is seeking qualified engineering, construction, and construction oversight firms to design and construct a new oxidation and filtration treatment system capable of processing 100 gallons per minute to remove iron and manganese from groundwater sources at the existing well site located at 304 Sterling Road. The project serves approximately 350 residents and the Sterling Community School. The RFQ was released on July 23, 2026, with a deadline for questions on August 12, 2026, and a submission deadline of August 28, 2026. Selection and notification of awarded firms will occur by September 16, 2026. The project timeline includes field investigation and design phases from September through December 2026, with construction bidding and construction activities scheduled for 2027. The scope of work encompasses survey work, detailed engineering design, permitting support, bid phase assistance, construction administration, full-time field inspections, commissioning, startup, operator training, and development of an Operations and Maintenance manual.

The project will be funded through the Connecticut Drinking Water Emerging Contaminants in Small or Disadvantaged Communities (EC SDC) program and/or the State of Connecticut Drinking Water State Revolving Fund (DW SRF), with all contracts subject to requirements of Section 22a-482-4 of the RCSA. All vendors are eligible to respond. Evaluation criteria include experience with DWSRF-funded projects, experience with similar treatment projects, understanding of project scope and approach, technical expertise and qualifications, project team capacity and key personnel qualifications, avoidance of conflicts of interest, schedule adherence, and cost competitiveness. The State of Connecticut will not be a party to the contract. Contact information for questions is provided through Judith Stumpo at jstumpo@sterlingct.us, Jack Joslyn at jjoslyn@sterlingct.gov, or Ashley StJean at astjean@sterlingct.us or 860-564-2904 Ext 117.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sterling_CT_Filtration_Scope of Work 7-23-26

Town of Sterling Water Treatment Project

-- REQUEST FOR QUALIFICATIONS --

Contact Information: Judith Stumpo, jstumpo@sterlingct.us

Jack Joslyn, jjoslyn@sterlingct.gov

Town of Sterling 1183 Plainfield Pike P.O. Box 157 Oneco, CT 06373

Scope of Work

1. Project Overview

The Town of Sterling, Connecticut, is looking for qualified engineering, construction, and construction oversight firms to provide services for a Drinking Water infrastructure project.

This project will be funded through the Connecticut Drinking Water Emerging

Contaminants in Small or Disadvantaged Communities (EC SDC) and/or the State of

Connecticut Drinking Water State Revolving Fund (DW SRF). The objective is to identify qualified firms for design and construction for a new oxidation and filtration treatment system to remove iron and manganese from groundwater sources at the existing well site

(304 Sterling Road).

Any contract awarded under this request for proposal is expected to be funded through EC-

SDC and DW SRF and will be subject to requirements of Subsections (h), (i) and (o) of

Section 22a-482-4 of the RCSA. The State of Connecticut will not be a party to this request or any resulting contract.

A Preliminary Engineering Report (PER) stamped September 2025 addresses issues with discolored water, due to elevated iron and manganese levels. A 100gpm oxidation & filtration treatment system was identified as the best alternative weighing in several factors. The population served by the Sterling Water System is approximately 350 residents and the Sterling Community School.

mailto:jstumpo@sterlingct.us mailto:jjoslyn@sterlingct.gov

2. Scope of Work This scope of work provides some details for firms to identify qualifications. This does not give all detail that will be part of the contracting process:

Design Phase:

• Meet with Sterling Board of Selectmen in an initial workshop meeting.

o (Sterling looking into town requirements for additional voting)

• Conduct Survey work to prepare base maps for the project.

• Collaborate with Sterling Board of Selectmen on review and revisions to the design.

• Detailed engineering design for oxidation and filtration system

Administrative:

• Permitting support (CT DPH Public Water System Construction Permit, NDDB review, chemical feed system application)

• Assist with applying for additional funding

• Bid phase assistance, construction administration, and construction observation services

Construction and Support:

• Hold a Preconstruction Conference

• Satisfy all requirements of federal and state funding agencies.

• Process change orders and contract documents as required.

• Full time field inspections during all construction activities

• Assistance with and coordination of, commissioning, startup, and operator training.

• Hold regular construction meetings with the Selectmen, WPCA and Contractor.

3. Deliverables

• All applicable certifications and deliverables for DWSRF cross-cutter requirements.

• Preliminary design report

• 60% and 90% design submittals

• Final design drawings and specifications

• Opinion of Probable Construction Costs

• Bid documents

• Permitting assistance, including development of the technical portions of permit applications and coordinating with permitting agencies to resolve comments.

• O&M manual

4. Evaluation Criteria

• Sterling will utilize an evaluation structure to assess proposals by balancing cost, technical/managerial capacity and experiential factors.

• Experience with DWSRF-funded projects

• Experience with similar treatment projects

• Understanding of project scope and approach

• Technical expertise and qualifications

• Capacity, project team and key personnel

• Avoidance of personal and organizational conflicts of interest

• Schedule adherence and cost competitiveness

5. Schedule Design: September 2026 – November 2026

Field investigation: September 2026 – December 2026

Construction bids: 2027

Construction: 2027

RFQ Release Date: July 23, 2026

Deadline for Questions: August 12, 2026

Submission Deadline: August 28, 2026

Selection and Notification: September 16, 2026