Statement of Work Specification.pdf
PDF 1 MB Posted
- Attached to
- CGC Tahoma Depot Availability
- Solicitation number
- 70Z080-22-Q-MECP0017
About this file
This document outlines the requirements for a depot availability contract for the Coast Guard Cutter Tahoma. The solicitation seeks maintenance and repair services including renewal of electrical grade sheet deck covering, preservation of exterior non-skid decks, installation of one-step epoxy deck covering in various spaces, renewal of piping insulation, and renewal of a deck penetration sleeve. The period of performance is from September 28, 2022 to November 4, 2022 at the Coast Guard facility in Everett, Washington. Services required include surface preparation, coating and non-skid application, deck covering installation, insulation removal and installation, and sleeve renewal in accordance with Coast Guard technical specifications and drawings provided.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 1.pdf | ||
| Schedule of Services.pdf | ||
| CGC Tahoma Depot Availability.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC TAHOMA (WMEC 908)
SPECIFICATION FOR DOCKSIDE REPAIRS
FY2022
Developed By: Brandon M Horacek
(Rev-0, 15 Jun 2022)
USCGC TAHOMA (WMEC-270B) DOCKSIDE AVAILABILITY FY2022
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property ................................................................................. vi Consolidated List of Critical Inspection Items ........................................................................................... vii Principal Characteristics ............................................................................................................................ viii General Requirements WORK ITEM 1: Electrical Grade Sheet (Dielectric) Deck Covering, Renew WORK ITEM 2: Decks - Exterior, Preserve, Mil-Spec/Flight Deck System WORK ITEM 3: One-Step Epoxy Deck Covering, Renew WORK ITEM 4: Piping Insulation, Renew WORK ITEM 5: Deck Penetration Sleeve, Renew iii (Rev-0)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
iv (Rev-0)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.
All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.
COAST GUARD DRAWINGS
Coast Guard Drawing 905 WMEC 508-001, Rev C, Pipe & Mchry Insul. Schedule
Coast Guard Drawing 905 WMEC 514-020, Rev E, CHW & HW System Diagram
Coast Guard Drawing 905 WMEC 634-001, Rev D, Deck Covering Schedule
Coast Guard Drawing 905 WMEC 505-008, Rev B, Bulkhead, Deck, and Shell Piping Penetrations
Coast Guard Drawing 905 WMEC 521-006, Rev B, Firemain 01 Level & Above – Arr and Det
Coast Guard Drawing 905 WMEC 801-003, Rev H, General Arrangement-02/Pilothouse & Above
Coast Guard Drawing 905 WMEC 801-004, Rev F, General Arrangement-01 Level
Coast Guard Drawing 905 WMEC 801-005, Rev F, General Arrangement Main Deck
Coast Guard Drawing 905 WMEC 801-005, Rev F, General Arrangement-Main Deck
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors
Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2020, Install Interior
Deck Covering Systems
OTHER REFERENCES
ASTM International (ASTM) C552, 2021, Standard Specification for Cellular Glass Thermal Insulation
ASTM International (ASTM) F683, 2021, Standard Practice for Selection and Application of Thermal
Insulation for Piping and Machinery
MIL-PRF-24613A, Nov 2007, Deck Covering Materials, Interior, Cosmetic Polymeric
MIL-PRF-24667, March 2018, Coating system, Non-Skid, for Roll, Spray, or Self-Adhering Application
MIL-PRF-32514, June 2021, Insulation, Anti-Sweat, Refrigerant, Thermal Foam
NAVSEA Drawing 804-5959214, Rev-, Piping Insulation - Installation Details v (Rev-0)
QPL-24667, April 2021, Qualified Product List (Military) of Products Qualified Under Detail
Specification MIL-PRF-24667, Coating System, Non-Skid, for Roll, Spray, or Self-Adhering
Application
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2020, Power Tool Cleaning to Bare Metal
The Society for Protective Coatings (SSPC)/NACE International (NACE), Joint Surface Preparation
Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Blast Cleaning vi (Rev-0)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED COST
($/UNIT)
N Fantail Coating System, MIL-
PRF-24667 Type I, Comp. G
N/A 1 kt. 12,250.00 vii (Rev-0)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.1.4
(Inspection report particulars)):
Work
Item Title
2 Decks - Exterior, Preserve, Mil-Spec/Flight Deck System viii (Rev-0)
PRINCIPAL CHARACTERISTICS
270' WMEC (B-CLASS)
PHYSICAL
Length overall 270' 0"
Length between perpendiculars 255' 0"
Beam molded 38' 0"
Depth molded, main deck amidships, 01 level amidships
23' 7"
31' 4"
Full load displacement 1,886 long tons
Draft, full load to baseline amidships 14' 2"
Highest projection above baseline
*height approximated
≈ 110' 0"
Shore tie voltage requirements 2 cables, 400A / 450V, 3 phase
Frame spacing 1' 0"
MACHINERY
Main propulsion 2 ALCO Model 18-251-F Diesel Engines, 3,650 BHP each
Ship’s service generators 2 Caterpillar Model D-398-TA Diesel-driven KATO 6P6-1350 Generators. 475
KW each @ 0.8 power factor, 450VAC, 3 phase, 60 cycle
Emergency generators Caterpillar Model D-348-TA Diesel-driven KATO 4P4-1900. 475KW @ 0.8 power factor, 450VAC, 3 phase, 60 cycle
Number of propellers 2
Propeller diameter 9' 0"
Number of blades, each 4
Pitch Controllable
Shaft RPM 260
Shaft diameter 10.55" at exit of hull
Anchor & chain Two 4,000 lb Navy Stockless Anchors, 8 shots of chain each
TANK CAPACITIES
Diesel fuel total (95%) 79,950 gal.
JP-5 total (95%) 19,626 gal.
Potable water total (100%) 8,553 gal.
Hydraulic & lube oil total (95%) 2,561 gal.
1 (Rev-0)
00000_0222_FLT
REC_00000_FLT_Commercial Project @ CG Facility (0121)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and
'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is
Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements of this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
2 (Rev-0)
3.1.1 NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents. Contractors can apply to NAVSEA headquarters directly for copies.
3.2 Fire watch requirements. The Contractor must refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec
0000, in accomplishing the following task:
Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.
Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.
3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec
6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.
3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).
3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.
3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.
Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:
ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.
ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.
3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.
For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).
3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;
for each additional 1000 square feet, perform an additional area measurement. A “measurements” for coating thickness is defined as follows:
SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.
SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must be moved to a new location within a 1.5 inch diameter circle defining the spot.
3 (Rev-0)
3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.
3.4.1 HY-130 material substitution. The Contractor must be aware that HY-130 steel plating is no longer commercially available. For the purpose of performing flight deck repairs on US Coast Guard WMEC-270 “B-
Class” cutters, Weldox 900 steel plating has been approved as a replacement for HY-130. Due to the similarity in material properties and weldability of HY-130 and Weldox 900, all welding procedures and welder qualifications for welding Weldox 900 must be the same as those outlined in NAVSEA TP 1688 as applicable for welding HY-
130.
3.4.2 Standard spec modification. For any welding involving HY-130 on the flight deck of WMEC-270 “B-Class” cutters, perform all welding and allied processes, and non-destructive evaluation (NDE) in accordance with
NAVSEA TP 1688. The Contractor must be aware that the welding requirements specified in this document take precedence over paragraph 3.3.6 of SFLC Standard Spec 0000 for the purpose of welding involving HY-130.
3.4.3 Approval to weld HY-130. To obtain Coast Guard approval to weld on HY-130 steel for WMEC-270 “B-
Class” cutters, the Contractor must provide written Performance Qualification Records (PQR’s) for each process to be used. The PQR’s must be approved by one of the regulatory agencies affirming that the WPS meets the welding requirements of NAVSEA TP 1688. In addition, the Contractor must ensure that all subcontractors, prior to performing welding operations, have qualified procedures by meeting all the requirements set forth in this document.
NOTE
NAVSEA approval is NOT required for welding procedures submitted but the procedures must be reviewed and shown to satisfy the requirements set forth in
NAVSEA TP 1688, by a welding regulatory agency. The requirements for welding
Weldox 900 are considered the same as those for welding HY-130.
3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 Contractor operated (non USCG) facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at
Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.
3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The
Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility
Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be
4 (Rev-0) provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System
(NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’
Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out;
ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous
Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental
Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix B, Requirements For
Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).
3.5.6 Additional Requirements. The Contractor must be aware of the following:
3.5.6.1 No Contractor or Subcontractor must have the authority to sign a Hazardous Waste Manifest using the
Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast
Guard facility without COR or KO-approval.
3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor must prepare for and comply with local and state regulations.
3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor must furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.
3.6 Local Policy. The Contractor must refer to site (e.g. Base) Regulations and Instructions for details regarding local policies (e.g. crane services, parking, or facility usage).
3.6.1 PNSY requires DBID’s credentials for access. Both the ‘Security List’ and ‘DBID’s Request Form’ can be obtained electronically from the COR. After approval, the contractors will then be issued a badge/DBIDs credentials prior to coming on base. This must be done in person at the ID/Pass Office, near Gate 1, with corresponding Identification shown on the ‘Security List’ and an additional photo ID. The shipyard badge will then be swapped out for a visitor badge while performing work upon the cutter.
NOTE
Wait times can be up to 3 hours or more for the initial badge. The badge office recommends using the smartphone app “QLESS” to make an appointment in advance.
3.6.2 Separate COVID-19 precautionary/mitigation requirements will also be applicable on the shipyard and on
TAHOMA. Although the specific requirements may vary based on the current exposure risk level, all personnel
5 (Rev-0) may be required to attest/provide proof of vaccination, conduct a COVID test within 3 days prior to entering the facility/ship with ‘negative’ results, be required to wear cloth masks at all times (other than expressly permitted not for safety concerns), observe social distancing, and/or maintain a heighten degree of sanitation standards.
3.6.3 This availability is to be conducted at an US Navy facility. The Contractor must comply with all US Naval facility instructions (e.g. NAVFAC P-307 for Weight Handling Program Management, etc.).
3.7 SFLC Standard Specification approved changes. The Contractor must be aware that the following are approved changes to published SFLC 2020 Edition Standard Specifications and supersede published content:
3.7.1 SFLC Standard Specification 8636. Add missing paragraphs between 3.2 and 3.5 of Std Spec 8636 as follows:
“3.3 Access cut boundaries. The Contractor shall ensure that access cuts comply with the requirements and restrictions detailed in the following and in SFLC Std Spec 0740, and referenced codes.
3.3.1 Location of boundaries. Boundaries of access cuts and closure plates shall, in general, be located between principal ship framing, bulkheads, and other structural members and shall be at least three inches from any of these members or from the toes of other welds. A reduction in this three inch minimum may be approved by the
KO on a case by case basis provided sufficient clearance is maintained for welding and inspection requirements.
The boundaries of access cuts and closure plates should land on existing butts or seams, wherever practicable. The boundaries of prior access cuts should be utilized wherever possible. Boundaries may extend across one or more frames as required for the size of the opening.
3.3.2 Access hole dimensions and arrangements. Holes or access cuts shall be the minimum size necessary and shall be in accordance with the following:
Rectangular access cuts and closure plates welded into primary hull structure shall be at least 12 inches wide in the lesser dimension.
For circular access cuts, the minimum diameter shall be 4T, where T = thickness of the involved structural member, but not less than three inches.
Circular closure plates for access cuts less than two feet in diameter shall be dished 1/16 to 1/8 inch to allow for shrinkage when welded.
Corners of rectangular access cuts and closure plates shall have a minimum radius of 6 inches except when a boundary lands on an existing hull longitudinal seam or transverse butt weld.
Corners at an existing seam or butt shall intersect at a 90 degree angle.
Cuts that are to cross existing butts or seams shall do so at an angle of 90 degrees plus or minus 15 degrees.
In primary hull structure, existing welds forming the boundary of a cut shall be cut back 3 inches beyond the toe of the access cut, except that the cut back shall not intersect or cross an existing weld, frame, or structural member. In which case, the cut back may be reduced to a minimum of two inches in length.
Existing welds crossed by the cut shall not be cut back.
3.3.3 Primary hull structure. Primary Hull Structure includes the shell, main strength decks, principal longitudinal bulkheads, vertical keel, deep web girders and stiffeners designed to withstand the ship bending stress.
3.3.4 Mechanically fastened joints. Welding closer than six inches to a mechanically fastened joint should be avoided. When access cuts cross or come within six inches of a mechanically fastened joint, the fasteners shall be checked for tightness and if necessary, loose fasteners shall be seal welded or removed, and replaced for a distance of 6 inches beyond the edge of the cut. When a cut crosses a mechanically fastened seam the cut plates
6 (Rev-0) shall be repaired using single V welds backed with glass tape (MIL-C-20079) to prevent fusion between the mechanically fastened plates.
3.4 Ship integrity maintenance. The Contractor shall maintain safety and ship integrity by installing temporary guarding and coaming, in addition to weathertight and watertight closures. Remove these temporary fabrications after closing the hull access, and grind surfaces flush in way of removals. For shell plating cuts made at or below the waterline where temporary closures are impractical, the Contractor shall secure each vulnerable compartment and subdivision to minimize potential damage to the extent permitted by the scope and urgency of the work.
3.4.1 Guarding. Install temporary guards in accordance with 29 CFR 1915.73.
3.4.2 Coaming. Ensure that in areas where flammable liquids may be stored, a 4 inch high metal coaming shall be installed on the surface of the deck with tack welds and fully sealed with caulking compound. The coaming shall encircle the access cut in the deck.
3.4.3 Weathertight and contamination closures. Fabricate temporary closures, using fire retardant material, before cutting access openings and install closures whenever access is not in use. Closures shall be:
Constructed to protect the access from inclement weather and entry of contaminants (shall include a coaming or dam on the deck to redirect rain runoff away from the opening).
Fitted with fasteners that permit rapid installation and removal.
Able to support a minimum of 150 pounds per square foot for horizontal deck closures.
Where the access opening is in way of a removed hatch, scuttle or door, the closure shall be configured to allow normal passage of ship’s personnel and equipment.
3.4.4 Watertight closures. Ensure that access openings created four feet or less above the maximum anticipated waterline shall include temporary watertight closures when the vessel is waterborne.
NOTE
NAVSEA S0600-AA-PRO-160/CH16 provides requirements for design, fabrication, and installation of temporary watertight closures.”
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
7 (Rev-0)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
VESSEL NAME HULL # WORK ITEM
WORK ITEM TITLE
LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME
NAME OF CG REPRESENTATIVE SIGNATURE UNIT DATE/TIME
8 (Rev-0)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
VESSEL NAME HULL #
WORK ITEM
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE
TIME
ACTIVITY (SURFACE
PREPARATION, PRIMER COAT,
BARRIER COAT, TOP COAT,
ETC…)
LOCATION (FRAME &
DECK, RELATION TO
EQUIPMENT, ETC.)
TEMPERATURE % REL.
HUMID-
ITY
DEW
PT.
SURFACE AMBIENT ΔT
| DP -
SURFACE |
9 (Rev-0)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
VESSEL NAME HULL # WORK ITEM
LOCATION OF WORK (FRAME REFERENCES) AREA (SQFT)
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS
PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS
DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:
10 (Rev-0)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT
QA RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO
SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Mean Mils Reading (IAW ASTM D4417-Method B for above 10 readings (by column):
Mean Reading
(mils)
11 (Rev-0)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
VESSEL NAME HULL # WORK ITEM
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.
DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)
12 (Rev-0)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
VESSEL NAME HULL #
WORK ITEM
COATING MFG PRODUCT NAME
BATC
H #
INDUCTI
ON TIME
COATING SYSTEM
SEQUENCE
(PRIMER/TOUCHUP/3RD
COAT, ETC.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.
SPOT 1 2 3 4 5
AVERAGE
VALUE
*BASE METAL READING
(BMR)
*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
APPLICATION METHOD (AIRLESS,
CONVENTIONAL SPRAY, ROLLED)
AVERAGE DFT
13 (Rev-0)
4.2 Tank and Void Assessment form.
14 (Rev-0)
15 (Rev-0)
S22_0026_63430_BMG_0222_908
WORK ITEM 1: Electrical Grade Sheet (Dielectric) Deck Covering, Renew
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to renew Electrical Grade Sheet
(Dielectric) deck covering in the areas listed in Table 1 and as designated by the Coast Guard Inspector.
1.2 Government-furnished property.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 905 WMEC 634-001, Rev D, Deck Covering Schedule
Coast Guard Drawing 905 WMEC 801-003, Rev H, General Arrangement-02/Pilothouse &
Above
Coast Guard Drawing 905 WMEC 801-004, Rev F, General Arrangement-01 Level
Coast Guard Drawing 905 WMEC 801-005, Rev F, General Arrangement-Main Deck
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements
Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2020, Install
Interior Deck Covering Systems
OTHER REFERENCES
None.
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):
None.
3.1.2 Tech Rep.
16 (Rev-0)
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec
0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:
Switchboards
Operating consoles
Vidmars
Workbenches
Desks
Electrical equipment
3.2 Deck covering installation particulars. The Contractor must perform all tasks specified in SFLC Std
Spec 6341 and herein, to install a new deck covering system in the location(s) specified. Refer to Coast
Guard Drawings listed in Section 2 (REFERENCES) for guidance.
TABLE 1 - DECKING SYSTEM PARTICULARS
LOCATION
AREA
(*SQFT)
SYSTEM/APPENDIX (SFLC STD
SPEC 6341)
COVE
BASE
CIC
(2-63-0-C) 800 Electrical Grade Sheet/Appendix A Yes
3.5 Visual inspection. The Contractor must perform a visual inspection of all exposed deck surfaces in accordance with SFLC Std Spec 6341, prior to priming deck surfaces. Submit a CFR.
3.6 Deck covering color. The Contractor must submit a deck covering color chart to Coast Guard
Inspector, for the purpose of color selection.
4. NOTES
This section is not applicable to this work item.
17 (Rev-0)
63121_0222_FLT
REC_63120_Dks_Exterior_FLT_270B WMEC (ALL) (0222)
S21_0018_63120_BMG_0222_908
WORK ITEM 2: Decks - Exterior, Preserve, Mil-Spec/Flight Deck System
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to preserve the following exterior deck surfaces:
Fan Tail, Main Deck (Steel Surfaces): Frame 207 to Stern.
1.2 Government-furnished property.
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
N Fan Tail Coating System, MIL-PRF-24667 Type I, Comp. G
N/A 1 kt. 12,250.00
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 905 WMEC 801-005, Rev F, General Arrangement-Main Deck
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures
OTHER REFERENCES
MIL-PRF-24667, March 2018, Coating system, Non-Skid, for Roll, Spray, or Self-Adhering
Application
QPL-24667, April 2021, Qualified Product List (Military) of Products Qualified Under Detail
Specification MIL-PRF-24667, Coating System, Non-Skid, for Roll, Spray, or Self-
Adhering Application
18 (Rev-0)
The Society for Protective Coatings (SSPC)/NACE International (NACE), Joint Surface
Preparation Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Blast Cleaning
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP
11), 2020, Power Tool Cleaning to Bare Metal
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):
3.4.2.1 Substrate inspection.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, (Vessel component, space, and equipment protection).
Adjacent vertical (beyond what is specified in paragraph 3.4.2 (Surface preparation and coating application)).
Ventilation intakes.
Deck fittings.
Deck equipment.
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, (Interferences). Known interferences include, but are not limited to the following:
Deck drain gratings.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.
3.3 Ultrasonic thickness (UT) measurement. The Contractor must take a total of 100 UT measurements in accordance with SFLC Std Spec 0740, Appendix C in locations designated by the Coast Guard Inspector and using Coast Guard Drawings in the References Section as guidance. Submit a CFR.
3.3.1 In addition to the UT measurements, take a total of 200 pit-depth measurements, using a suitable pit depth gauge, in accordance with SFLC Std Spec 0740.
3.4 Preservation requirements particulars. The Contractor must accomplish the following tasks. Use Coast
Guard Drawings 905 WMEC 801-003, 905 WMEC 801-004, and 905 WMEC 801-005 as guidance.
3.4.1 Pre-surface preparation wash. Prior to accomplishing surface preparation, accomplish low-pressure
19 (Rev-0)
(less than 5,000 psi) fresh water wash of all affected surfaces, to remove soluble chlorides and other surface contaminants. Capture, contain, and dispose of wash water for proper disposal in accordance with all Federal, state and local regulations.
3.4.2 Surface preparation and coating application. Prepare and coat the deck surfaces designated in paragraph 1.1 (Intent), including bitt and chock foundations, machinery rack guards and machinery foundations, hatches and hatch guards, stanchion sockets, vent pipes, angle coaming area, and approximately six inches up all adjacent vertical surfaces (as applicable); use the system specified in
Table 1. Ensure that the system is qualified as “UV/LSA”, as designated on QPL-24667.
TABLE 1 – NON-SKID DECK COATING SYSTEM
EXTERIOR
SURFACES TO
BE PRESERVED
SURFACE PREPERATION /
(ANCHOR PROFILE IN MILS)
COATING SYSTEM DFT (MILS) NOTES
Fan Tail SSPC-SP 10/NACE NO. 2 using grit conforming to MIL-A-22262 /
(3.0-6.0)
1) One Full Coat Primer
MIL-PRF-24667 Type I, Comp. G
2) Stripe Coat MIL-PRF-
24667 Type I, Comp. G
3) One Full Coat Primer
MIL-PRF-24667 Type I, Comp. G
4) One Coat Non-Skid
MIL-PRF-24667 Type I, Comp. G
Follow
Manuf.
Instructions
1, 2
1. Nonskid material is rolled on over primer within 48 hours for best adhesion.
2. Power tool cleaning to bare metal (SSPC-SP 11) may be used in areas that cannot be accessed by abrasive blasting.
3.4.2.1 Substrate inspection. After completion surface preparation and before coating application, perform a visual inspection, in the presence of a Coast Guard Inspector, of the prepared substrate, and submit a
CIR.
3.4.2.2 Color selection. Select and use Dark Gray (36076) as the finish/top coat color.
3.4.2.3 Non-skid exempted areas. Apply top color coating only (do not apply non-skid topcoat) over vertical surfaces, and the following areas:
Within two inches of deck fittings and protrusions.
Within six inches of deck coamings, bulkheads, and deck edges.
Within two inches of deck foundations (two inches measured from outermost portion of foundation, for example, foundation brackets on anchor windlass).
Waterways.
3.4.2.4 Non-skid surface appearance and texture. Ensure that the non-skid surface must show a pattern of peaks and ridges. The ridge profile must be continuous and reasonably uniform. Peaks and ridges must be generally in the same direction (fore and aft), approximately ½ to 1 inch apart, and approximately 1/16 to
3/32 inches high. All weld seams must be cross-rolled from a minimum of 3 inches on either side of the weld.
20 (Rev-0)
3.4.3 Containment. The Contractor must provide suitable means to contain generated dust, waste water, paint chips, and spent abrasives. When net barriers are used, the mesh size of the netting material must be small enough to ensure that the abrasives will be contained. In addition, net barriers, when used, must be overlapped where attached to stanchions, and anchored at the bottom for the entire net’s length between stanchions, to limit the clean–up and localize the blast media.
3.4.3.1 If a containment system is not used for surface preparation dust and debris and coating application overspray during pier side/dockside preservation, the following must be adhered to:
All surface preparation tools/equipment must be vacuum-shrouded.
Coatings must be applied by brushing or rolling.
3.4.3.2 If ambient condition parameters cannot be met for the full duration of preservation work, the
Contractor must provide suitable tenting and all equipment necessary to satisfy requirements in accordance with SFLC Std Spec 6310, Paragraph 3.1.5, at no additional cost to the Government.
3.4.4 Polyurethane coatings. The Contractor must be aware that two-part polyurethane primers, membranes, color toppings, and non-skid are not authorized for application on Coast Guard vessels, even if listed on QPL-24667.
3.5 Alternative non-skid coatings. If a Change Request has been authorized and released, the Contractor may select and apply one of the following:
A low temperature cure system, conforming to MIL-PRF-24667, Type VIII, Composition G.
A flexible membrane system, conforming to MIL-PRF-24667, Type III, Composition G, with the intermediate membrane.
NOTES
1. The low temperature system is only authorized for application at temperatures between 35-45 degrees F.
2. The Type III non-skid system with the intermediate membrane should only be used over deck surfaces that undergo a great deal of flexing, or over uneven deck surfaces where flatness is required.
3.6 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces).
3.6.1 Daily reports. At the conclusion of each work day coating has been applied, the Contractor must provide Daily Reports generated and signed by the Coating Tech Rep (if applicable).
3.6.1.1 Daily report contents. Daily reports must summarize work accomplished that current day, work to be accomplished the following day, any and all materials used during work that day, any and all readings taken and/or data collected (i.e. environmental readings, DFT, WFT, etc.) identifications of work locations, time and type of any inspections conducted with the results of such inspection(s) and must also include descriptions any events of non-conformance in relation to the specification, applicable references, standards, and technical data sheets (i.e. ASTM F718s)
3.6.1.2 Environmental Readings must be accomplished within agreed upon working hours according to the interval outlined in SFLC Std Spec 6310, Appendix D, paragraph D3.1.
21 (Rev-0)
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.7 Operational test, post repairs. After completion of work, the Contractor must thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition. Submit a CFR.
4. NOTES
4.1 Definitions.
4.1.1 Coaming. Vertical raised sections of deck plating around an opening that provide a frame and/or deflect water, such as around a hatch or gooseneck.
4.2 Unit responsibilities. The ship's force will be responsible for the following:
Removing the following equipment:
o CBL (Small Boat) and cradle o Portable pumps o Air compressor o Trash cans o Brow
Removing and reinstalling all deck drain gratings.
Ensuring no engine operation or stack emissions occur at any time during resurfacing.
Restricting access to the work area to only essential personnel.
22 (Rev-0)
S22_0015_63410_BMG_0222_908
S22_0014_63410_BMG_0222_908
S22_0012_63410_BMG_0222_908
WORK ITEM 3: One-Step Epoxy Deck Covering, Renew
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to renew Epoxy deck covering in the areas listed in Table 1 and as designated by the Coast Guard Inspector.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 905 WMEC 634-001, Rev D, Deck Covering Schedule
Coast Guard Drawing 905 WMEC 801-003, Rev H, General Arrangement-02/Pilothouse &
Above
Coast Guard Drawing 905 WMEC 801-004, Rev F, General Arrangement-01 Level
Coast Guard Drawing 905 WMEC 801-005, Rev F, General Arrangement-Main Deck
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2020, Install
Interior Deck Covering Systems
OTHER REFERENCES
MIL-PRF-24613A, Nov 2007, Deck Covering Materials, Interior, Cosmetic Polymeric
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):
23 (Rev-0)
None.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec
0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:
Existing deck covering system
Tool chests
Vidmars
Work benches
Storage lockers
Heads and toilets
3.2 Deck covering installation particulars. The Contractor must perform all tasks specified in SFLC Std
Spec 6341 and herein, to install a new deck covering system in the location(s) specified. Refer to Coast
Guard Drawings listed in Section 2 (REFERENCES) for guidance.
TABLE 1 - DECKING SYSTEM PARTICULARS
LOCATION
AREA
(SQFT)
SYSTEM/APPENDIX (SFLC
STD SPEC 6341)
COVE
BASE
SYSTEM
COLOR
Avionics
(01-103-0-Q)
Cosmetic Polymeric Epoxy
Resin, Type III (One-Step
Epoxy System)/Appendix A
Yes Blue
Trash Compactor Space
(1-186-3-Q)
Cosmetic Polymeric Epoxy
Resin, Type III (One-Step
Epoxy System)/Appendix A
Yes Blue
SPO Lounge
(2-165-2-L)
Cosmetic Polymeric Epoxy
Resin, Type III (One-Step
Epoxy System)/Appendix A
Yes Blue
Prop Shop Head
(3-160-2-L)
Cosmetic Polymeric Epoxy
Resin, Type III (One-Step
Epoxy System)/Appendix A
Yes Blue
Decon Shower
(01-94-2-L)
Cosmetic Polymeric Epoxy
Resin, Type III (One-Step
Epoxy System)/Appendix A
Yes Blue
SPO Sanitary Space
(2-165-0-L)
Cosmetic Polymeric Epoxy
Resin, Type III (One-Step
Epoxy System)/Appendix A
Yes Blue
Non-Rate Sanitary Space
(1-51-2-L)
Cosmetic Polymeric Epoxy
Resin, Type III (One-Step
Epoxy System)/Appendix A
Yes Blue
3.3 Underlayment requirements. The Contractor must install the new deck covering system(s) over new underlayment.
24 (Rev-0)
3.4 Ultrasonic thickness (UT) measurement. The Contractor must take a total of 200 UT measurements in accordance with SFLC Std Spec 0740, Appendix C in locations designated by the Coast Guard Inspector and using Coast Guard Drawings in the References Section as guidance. Submit a CFR.
3.5 Visual inspection. The Contractor must perform a visual inspection of all exposed deck surfaces in accordance with SFLC Std Spec 6341, prior to priming deck surfaces. Submit a CFR.
25 (Rev-0)
S21_0019_63501_BMG_0222_908
WORK ITEM 4: Piping Insulation, Renew
1. SCOPE
1.1 Intent. This work item describes the requirements for the…