STATEMENT OF WORK-Replace Pilot Planet Roof Top Unit 3.pdf

PDF 157 KB Posted

Attached to
Replace 17. 5 Ton Roof Top Unit 3 -Athens GA.
Solicitation number
12405B23Q0519
Issued by

About this file

This statement of work outlines requirements for replacing an existing 17.5 ton roof top unit at the United States National Poultry Research Center in Athens, Georgia. The contractor will remove the existing Carrier unit and install a new Carrier model 50FC-M2A2A6-0A0A0 or equivalent, including any necessary curb adapters. The new unit must be connected to and programmed within the existing Automated Logic Controls BAS. The contractor must dispose of the existing unit and refrigerant according to EPA standards. Additional requirements include providing all necessary equipment and labor, following OSHA safety standards, and complying with USDA physical security and safety regulations. Work may be performed during normal business hours from 8am to 4pm Monday through Friday. The related federal contract opportunity is solicitation number 12405B23Q0519 for replacing the roof top unit through the Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Replace Building 1 Pilot Plant Roof Top Unit 3 United States National Poultry Research Center

07/13/2023

GENERAL

SCOPE OF WORK. This contract is located at the USNPRC at 950 College Station Road Athens GA, 30605. The contract requirements are defined in this Statement of Work (SOW). The Contractor is to install and replace Building 1 Pilot Plant Roof Top Unit 3.

The purpose of this SOW is to solicit bids for replacing RTU 3 for Pilot Plant in Building 1

Replace RTU #3 on Pilot Plant roof.

• Existing unit is a Carrier 17.5 ton package RTU.

• Replace with Carrier model: 50FC-M2A2A6-0A0A0 or equivalent.

• Install curb adapter as needed.

• Unit shall be connected and programed to existing Automated Logic Controls BAS.

• Startup and test.

• A crane will be needed for removal and replacement of new unit.

• Dispose of existing unit and refrigerant per EPA standards.

• Work can be performed during normal business hours M-F.

• All OSHA safety standards shall be followed.

PHYSICAL SECURITY. Contractor will be required to follow all USDA physical security and safety rule/regulations.

HOURS OF OPERATION. Normal Hours. The USNPRC is open Monday through Friday from 8am until 4pm except for Government holidays.

GOVERNMENT-FURNISHED PROPERTY AND SERVICES

No Government-furnished property will be provided. Government-furnished utilities will be provided where available.

CONTRACTOR-FURNISHED ITEMS AND SERVICES

GENERAL. Contractor shall furnish everything required to perform this Statement of Work.

CLEAN-UP. The Contractor is responsible for cleanup of any work site.

File details come from the government source that posted it. Updated .