This document is a Statement of Work (SOW) for the rental of a 21,000-gallon frac tank to support hydro water-jetting operations on a 140-foot U.S. Coast Guard vessel. The work is to be performed at the U.S. Coast Guard Yard in Baltimore, MD between June 24, 2024 and August 5, 2024, with the final period of performance determined by the Yard Point of Contact (POC) and Ship Superintendent. The contractor must provide the frac tank, which must meet specific requirements, for 10 consecutive days during this timeframe. The contractor will be responsible for any damage caused by the work and must be available 7 days a week for repairs or replacement. The related federal contract opportunity is a Request for Quote (RFQ) for the frac tank rental, with award to be made on a Lowest Priced Technically Acceptable basis. Quotes must be submitted by June 10, 2024 and payment will be made on a Net 30 basis after the work is completed and accepted.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FAR CLAUSES.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK P/R: 2124404Y6174M98002
POC: Paint Shop Foreman Donnie Legg Cell: (410) 636-3166 Email: b.legg@uscg.mil
Ship Superintendent James Johnston Cell: (410) 636-3095 Email: james.c.johnston@uscg.mil
Location: USCG Yard, 2401 Hawkins Point Rd, Baltimore, MD 21226
1. GENERAL REQUIREMENTS: The work consists of providing equipment as required iaw the description below. Located at 2401 Hawkins Point Road Baltimore MD 21226 49’ Busl.
1.1 Government intended use is for hydro water-jetting exterior surfaces of Coast Guard 140-foot vessel while in an enclosed containment. The work will include hydro water-jetting operations of the entire underwater hull exterior surface of the vessel. Any normal damages cause by the above work task will be at no cost to the Government. Any damage found outside normal wear and tear must be presented to Contracting Officer for approval prior to repair work being completed.
2. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK: Upon acceptance the contractor shall provide the equipment for 10 consecutive days sometime between 06/24/24 and 08/05/24. Final period of performance will be determined by the Yard POC / Ship Superintendent.
3. Description of Equipment: Description: One 21K Fixed axle vapor tight lined tank. An inspection report finding the equipment to be in good working order must be completed prior to delivery & forwarded to the Contracting Officer.
· 21K Fixed axle vapor tight lined tank – 304 stainless steel 21,000-gallon frac tank with “V” shaped floor for easy cleaning. Measurements of 45’x 8.5’x 11’, 3-4 22” manway access. Butterfly valve drains with NPT threads, non-slip stairway w/handrails and guardrails, OSHA compliant. Relief valve: vent/hatch equipped with pressure relief valve 4 or 16oz psi for pressure, 0.4oz psi for vacuum.
If at any time the equipment is deemed non-functioning, Contractor has 24 hours to either replace or have equipment up and functioning. Contractor must be available 7 days a week for repairs or replacement.
4. Delivery: Equipment must be delivered to the USCG Yard 2401 Hawkins Point Road Baltimore Maryland 21226. Receiving lot between Bldgs 80 and 88, 7:00am and 9:00am. Access to the Yard during the rental period is coordinated through the Yard POC. All personnel shall receive visitor’s passes and clearance from USCG Coast Guard Yard Security located at the Main Gate. List of personnel requiring access shall be provided to the Yard POC twenty-four (24) hours prior to requiring access. Personnel will be required to provide full name, picture I.D. (valid driver’s license preferred), and date of birth. For Non-US citizen’s, a passport will be required. The following forms of IDS are authorized: CAC, Foreign Passport containing appropriate visas, TWIC, Green Cards, US Passport, or MOST state IDs.
5. Pick Up: Request automatic pick up after 10 days unless optional days are authorized by Contracting Officer. Only the Contracting Officer may modify the contract. A contract modification must be executed prior to an extension occurring.
6. Schedule Period: 10 consecutive days sometime between 6/24/24 & 08/05/24. Final period of performance will be determined by the Yard POC / Shop Superintendent.
7. Damage to Government Property: The Contractor shall be held liable for any damage to government property caused by the Contractor. Any concerns must be brought to the attention of the POC.
6. Definitions and Acronyms: NA
8. CONTRACT DEFINITIONS:
1. CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.
2. CONTRACTING OFFICER. A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.
3. Safety Standards: Contractors must follow applicable OSHA guidelines.
9. ORAL MODIFICATION: No oral statement of any person other than the contracting officer shall in any manner or degree, modifies or otherwise affect the terms of this contract.