STATEMENT OF WORK EAGLE.docx
DOCX document 16 KB Posted
- Attached to
- CGC EAGLE FUEL DISPOSAL AND TANK CLEANING
- Solicitation number
- 70Z080-21-Q-P45F8000
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PROVISIONAL FAR CLAUSES EAGLE.docx | DOCX document | |
| SYNOPSIS EAGLE.docx | DOCX document | |
| RFQ SF18 Eagle.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCG BARQUE EAGLE (WIX 327)
Fuel Disposal & Tank Cleaning
1. Scope: The intent of this work item is to open, clean and dispose waste fuel oil listed in Table 1 to allow unit to refill with clean diesel fuel oil.
2. Safety: Fuel oil tanks are considered IDLH and shall be cleaned and tested to ensure safe for entry of personnel to enter and clean.
Hazardous Material: Tanks contain ballast water and/fuel oil products.
3. References/Dwgs:
CG SFLC Std. Spec 0000 CG SFLC Std. Spec 0740
4. Protective Measures: The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness. Specific areas/equipment/components to be protected include, but are not limited to:
· Topside coatings.
· Interior passageways, work spaces, berthing areas, etc.
· HAZMAT spill protection.
5. Requirements:
5.1 Open, Clean & Inspect tanks in Table 1. Tanks shall be cleaned to a point where no sludge fuel oil contamination is visible.
5.2 Remove & dispose of contaminated ballast water/oil in tanks listed in Table 1 i.a.w. local/state/federal law.
5.3 Tank Closure: Contractor shall make final inspection in the presence of CG Inspector to ensure all debris, tools, rags, etc. are removed from tank.
5.4 Contractor shall be responsible for providing ventilation equipment and Marine Chemist services to ensure spaces are safe for entry as required.
Table 1: Tank Details
| Tank number & Contents |
| Capacity |
| Actual volume in tank |
| Access/Location |
| Action Required |
| 4-19-1-F Fuel Tank |
| 2,200 gals. |
| 2,200 gals. |
Clean/Inspect
| 4-19-2-F Fuel Tank |
| 2,200 gals. |
| 2,200 gals. |
Clean/Inspect
| 4-68-0-F Fuel Tank |
| 4,366 gals. |
| 4,366 gals. |
Clean/Inspect
| 4-75-0-F Fuel Tank |
| 6,321 gals. |
| 6,321 gals. |
Clean/Inspect