Statement of Work 2126406Y6175K78001 154 D. Tarr Crane Support Galveston TX.docx
DOCX document 24 KB Posted
- Solicitation number
- 70Z04026Q60398
About this file
This is a Statement of Work for crane and rigging services supporting the USCGC Daniel Tarr, a 154-foot Coast Guard cutter, at USCG Base Galveston, Texas (3000 Fort Point Road, Galveston, TX 77550). The primary objective is to provide Subject Matter Expert crane and rigging services for incline testing of the vessel during a two-day period from May 19-20, 2026, with an optional third day on May 21, 2026 contingent on weather conditions.
The work scope includes three primary tasking elements: on May 19 (12:00 PM - 4:00 PM), loading Coast Guard-provided weights up to 5,000 pounds each onto the vessel using a crane capable of lifting at approximately 30 feet from the pier edge; on May 20 (7:30 AM - 3:00 PM), removing and reinstalling the vessel's gangway, moving loaded weights across the deck (minimum nine movements), and removing weights from the vessel; and on May 21 (optional, 7:30 AM - 3:00 PM), providing contingency support if weather prevents satisfactory testing on May 20. The contractor must furnish all equipment and services, follow 29 CFR 1915 (OSHA Shipyard Industry Standards) and applicable safety regulations, provide all personnel safety equipment meeting OSHA standards (hard hats, safety glasses with side shields, safety harnesses), and maintain communication through the Contracting Officer and CG Yard Baltimore Personnel. Work authorization and contract commencement require a signed order from a warranted Contracting Officer only.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT of WORK For Crane and Rigging Services – USCGC DANIEL TARR Incline Procurement Request: 2126406Y6175K78001
USCGC 154’ DANIEL TARR
Yard POC: Aaron Bloch (410) 299-0825 Tentative Start/Finish Date: 5/19/26-5/21/26 Period of Performance: 2 days w/ option day (21st) due to potential weather May 19 – 12:00 pm. to 4:00 pm.
May 20 – 07:30 am to approximately 3:00 pm.
Optional: May 21 – 07:30 am to approximately 3:00 pm.
Location:
USCG BASE GALVESTON
3000 FORT POINT RD
GALVESTON, TX 77550
Provide contractual support for The United States Coast Guard, serving as a Subject Matter Expert in your Craft performing the following below for USCGC FRC 154’ Daniel Tarr:
Tasking:
1) May 19 (12:00 – 4:00) Provide crane and rigging services as required to load weights up to 5000 lbs each (CG PROVIDED), on board USCGC TARR. Crane must be capable of lifting weights at approximately 30 feet from the edge of the pier
2) May20 (07:30 – 3:00) Provide crane and rigging services to assist cutter with removal of gangway and other miscellaneous items as required. Provide crane and rigging services to move weights, loaded onto cutter previously, across the deck of the cutter, minimum of 9 weight movements. Provide crane and rigging services to remove weights from the vessel after the cross-deck movements. Provide crane and rigging services to assist the cutter with installation of gangway and other miscellaneous items as requested
3) OPTIONAL: May21 (07:30 – 3:00) Optional day should weather conditions prevent satisfactory testing conditions on May20.
General Information:
All Services must be performed in the direction of, by and with USCG Yard Baltimore Engineering Team.
All work shall be completed in a timely and efficient manner. The contractor shall communicate all work or changes via Contracting Officer and CG Yard Baltimore Personnel.
FAR 52.237-1 Site Visit: Offerors or quoters are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award.
Controlled Unclassified Information: JCP certification is required for United States (U.S.) or Canadian contractors who wish to obtain access to unclassified technical data disclosing militarily critical technology with military or space application that is under the control of, or in the possession of the U.S. Department of Defense (DOD) or the Canadian Department of National Defense (DND).
ORAL MODIFICATION: No oral statement of any person other than the contracting officer shall in any manner or degree, modify, or otherwise affect the terms of this contract.
ACCEPTANCE CRITERIA: Criteria evaluated for payment approval. The government will review work in its entirety prior to issuing invoice approval.
CONTRACTOR FURNISHED ITEMS, SERVICES AND RESPONSIBILITIES:
General: The Contractor shall furnish all equipment and services required to perform work under this SOW, other than those explicitly addressed in government furnished services.
The Contractor shall report to the designated work site on the date specified on the written notification by the Contracting Officer in the form of a signed order. No other individual has the authority to direct the Contractor to begin work, other than a warranted Contracting Officer. Pending Coast Guard Yard production schedules, services may be required on an intermittent basis within the period and quantity specified.
Contractor Equipment: vehicles and tanks which holds or can hold hazardous materials that is left on CG Yard premises must have the Contractor’s contact information placed in the driver’s side window indicating the Emergency Contact Number (answered 24/7/365) for the owner/operator of the vehicle. If a tank is left on the premises, the Emergency Contact Number (answered 24/7/365) for the owner/operator of the tank must be painted on the tank in a prominent location. The government will not assume liability for any vehicles/tanks left on CG YARD property. The COR/SS will coordinate the location with the Yard Environmental/Security/Materials Handling.
General: The Contractor will be required to follow 29 CFR 1915 (OSHA Shipyard Industry Standard), 16 CFR1303, 29 CFR 1910, 29 CFR 1915.1025, 29 CFR 1926.62, 15 U.S.C. 2601, while performing this work at the U.S. Coast Guard Yard and abroad.
Safety Equipment: The area where this work taking place requires hard hats, safety harnesses and safety glasses always. The Contractor will provide all required personnel safety equipment for their employees, including, but not limited to, safety helmet and safety glasses with side shields. All safety equipment shall meet OSHA standards. The Contractor shall follow all applicable OSHA guidelines and regulations. It is also required that all COVID safety practices are followed.
File details come from the government source that posted it. Updated .