SR512CorridorCongestionManagementSpecs.pdf
PDF 6 MB Posted
- Attached to
- SR 512, Corridor Congestion Management
- Solicitation number
- XE3758, FA Proj 0053(897)
- Issued by
- Pierce County, Washington
About this file
This is a project specification document for the Washington State Department of Transportation (WSDOT) detailing SR 512 Corridor Congestion Management improvements in Pierce County. The project encompasses improvements to State Route 512 from milepost 0.27 to milepost 2.65, with primary work including full-depth reconstruction at the SR 7 on-ramp to SR 512 junction, removal and replacement of ramp illumination systems, installation of a Wavetronix data collection station, replacement of pavement markings, and implementation of traffic control measures. The project consists of 30 bid items and is classified as Work Class 4 asphalt concrete paving with a project duration of 15 working days. The specification document establishes technical standards, material requirements, and construction procedures that bidders must follow to meet WSDOT standards for the corridor improvement work.
The specifications address technical requirements for materials, construction methodology, and performance standards necessary for successful project completion. Key technical areas covered include asphalt concrete paving specifications, illumination system installation standards, pavement marking requirements, and traffic control protocols. The document provides detailed measurement and payment provisions for each of the 30 bid items, establishing the framework for contractor compensation based on actual work performed. All work must comply with WSDOT's current specifications and applicable Washington State transportation standards, with the contractor responsible for quality assurance throughout the 15-day construction period.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For Construction of:
F. A. PROJECT NO. 0053(897)
Washington State1 Department of Transportation2 Olympia, Washington 985043
SR 5126
CORRIDOR7
CONGESTION MANAGEMENT8
25C5129
PIERCE COUNTY10
Notice to All Planholders14 The Engineer assigned to answer questions regarding these bid documents, show 15 this project to prospective bidders, and act as the Contracting Agency’s 16 representative who directly supervises the engineering and administration of this 17 project is:18
Justin Janke, P.E.21 1305 Tacoma Ave. S22 Tacoma, WA 9840223 Phone: (253) 677-519924 Email: justin.janke@wsdot.wa.gov25
Troy Cowan, P.E.30
Olympic Region Administrator31
As the Engineer in direct responsible charge of developing these contract provisions, 35 I certify these provisions have been developed or incorporated into this project under 36 my supervision or as a result of certified specifications provided by other licensed 37 professionals.38
SR 512
CORRIDOR
CONGESTION MANAGEMENT
25C512 A
CONTENTS 1
INTRODUCTION--------------------------------------------------------------------------------------- 1 5
SPECIAL PROVISIONS 6
DIVISION 1 7
GENERAL REQUIREMENTS 8
DESCRIPTION OF WORK -------------------------------------------------------------------------- 1 9 BID PROCEDURES AND CONDITIONS -------------------------------------------------------- 1 10 Examination of Plans, Specifications and Site of Work ------------------------------------ 1 11 General ------------------------------------------------------------------------------------------------ 2 12 Preparation of Proposal ---------------------------------------------------------------------------- 2 13 Delivery of Proposal -------------------------------------------------------------------------------- 3 14 Public Opening of Proposals --------------------------------------------------------------------- 3 15 Date Of Opening Bids ------------------------------------------------------------------------------ 3 16 SCOPE OF THE WORK ----------------------------------------------------------------------------- 3 17 Coordination of Contract Documents, Plans, Special Provisions, Specifications, and 18
Addenda -------------------------------------------------------------------------------------------- 3 19 CONTROL OF WORK -------------------------------------------------------------------------------- 4 20 Conformity with and Deviations from Plans and Stakes ----------------------------------- 4 21 Contractor Surveying - Roadway ---------------------------------------------------------------- 4 22 Cooperation with Other Contractors ------------------------------------------------------------ 7 23 Speed Safety Camera System Vendor --------------------------------------------------------- 7 24 CONTROL OF MATERIAL--------------------------------------------------------------------------- 8 25 Buy America Requirements ----------------------------------------------------------------------- 8 26
LEGAL RELATIONS AND RESPONSIBILITIES TO THE PUBLIC ----------------------- 12 27
Laws To Be Observed ---------------------------------------------------------------------------- 12 28 Unmanned Aircraft Systems (UAS) ----------------------------------------------------------- 12 29 Environmental Regulations --------------------------------------------------------------------- 12 30 Environmental Commitments ------------------------------------------------------------------- 12 31 Payment --------------------------------------------------------------------------------------------- 13 32 Air Quality ------------------------------------------------------------------------------------------- 13 33 Asbestos Containing Material ------------------------------------------------------------------ 13 34
PAGE
CONGESTION MANAGEMENT
25C512 B
U.S. Fish and Wildlife Service and National Marine Fisheries Service ----------------- 13 1 Load Limits ------------------------------------------------------------------------------------------ 13 2 High-Visibility Apparel ---------------------------------------------------------------------------- 13 3 Traffic Control Personnel ------------------------------------------------------------------------ 13 4 Wages ------------------------------------------------------------------------------------------------ 14 5 General ---------------------------------------------------------------------------------------------- 14 6 Requirements For Nondiscrimination --------------------------------------------------------- 14 7 Federal Small Business Enterprise Participation ------------------------------------------ 22 8 Regulatory Authorities ---------------------------------------------------------------------------- 30 9 Nondiscrimination Authorities ------------------------------------------------------------------- 30 10 Federal Agency Inspection ---------------------------------------------------------------------- 31 11 Required Federal Aid Provisions -------------------------------------------------------------- 31 12 Temporary Water Pollution Prevention ------------------------------------------------------- 32 13 Spill Prevention, Control, and Countermeasures Plan ----------------------------------- 32 14 Utilities and Similar Facilities ------------------------------------------------------------------- 32 15 PROSECUTION AND PROGRESS ------------------------------------------------------------- 34 16 Subcontracting ------------------------------------------------------------------------------------- 34 17 Subcontractor Approval -------------------------------------------------------------------------- 35 18 Payments to Subcontractors and Lower-Tier Subcontractors -------------------------- 35 19 Payment Reporting ------------------------------------------------------------------------------- 35 20 Submittal of Executed Subcontracts ---------------------------------------------------------- 36 21 Progress Schedule -------------------------------------------------------------------------------- 36 22 Weekly Meeting ------------------------------------------------------------------------------------ 36 23 Prosecution Of Work ----------------------------------------------------------------------------- 36 24 Time For Completion ----------------------------------------------------------------------------- 36 25 Suspension of Work ------------------------------------------------------------------------------ 36 26 Liquidated Damages ------------------------------------------------------------------------------ 37 27 MEASUREMENT AND PAYMENT --------------------------------------------------------------- 38 28 Weighing Equipment ----------------------------------------------------------------------------- 38 29 General Requirements for Weighing Equipment ------------------------------------------- 38 30 Electronic Delivery Management System (E-Ticketing) ---------------------------------- 38 31 Payment --------------------------------------------------------------------------------------------- 39 32 Payments-------------------------------------------------------------------------------------------- 39 33 Retainage ------------------------------------------------------------------------------------------- 39 34
CONGESTION MANAGEMENT
25C512 C
DIVISION 2 1
TEMPORARY FEATURES 2
Public Convenience and Safety ---------------------------------------------------------------- 39 3 Construction Requirements --------------------------------------------------------------------- 39 4 Construction Under Traffic ---------------------------------------------------------------------- 39 5 Temporary Traffic Control ------------------------------------------------------------------------ 43 6 Materials --------------------------------------------------------------------------------------------- 43 7 Sequential Arrow Signs -------------------------------------------------------------------------- 43 8 Radar Speed Display Sign ---------------------------------------------------------------------- 44 9 Construction Requirements --------------------------------------------------------------------- 45 10 Traffic Control Management -------------------------------------------------------------------- 46 11 Traffic Control Devices --------------------------------------------------------------------------- 47 12 Radar Speed Display Sign ---------------------------------------------------------------------- 47 13 Sequential Arrow Signs (Arrow Boards) ----------------------------------------------------- 47 14 Payment --------------------------------------------------------------------------------------------- 48 15 Item Bids With Lump Sum for Incidentals --------------------------------------------------- 48 16
DIVISION 3 17
EARTHWORK 18
Removal of Structures and Obstructions ---------------------------------------------------- 49 19 Description ------------------------------------------------------------------------------------------ 49 20 Construction Requirements --------------------------------------------------------------------- 49 21 Removing Miscellaneous Traffic Items ------------------------------------------------------- 49 22 Removal and Disposal of Asbestos Material ------------------------------------------------ 49 23 Payment --------------------------------------------------------------------------------------------- 50 24 Roadway Excavation and Embankment ----------------------------------------------------- 50 25 Measurement --------------------------------------------------------------------------------------- 50 26
DIVISION 5 27
SURFACE TREATMENTS AND PAVEMENTS 28
HOT MIX ASPHALT --------------------------------------------------------------------------------- 50 29 Description ------------------------------------------------------------------------------------------ 51 30 Materials --------------------------------------------------------------------------------------------- 51 31 Mix Design – Obtaining Project Approval ---------------------------------------------------- 51 32 ESAL's -------------------------------------------------------------------------------------------------- 51 33 HMA Tolerances, Specification Limits and Adjustments ------------------------------------ 51 34
CONGESTION MANAGEMENT
25C512 D
Construction Requirements --------------------------------------------------------------------- 51 1 HMA Compaction Acceptance -------------------------------------------------------------------- 51 2 Joints ------------------------------------------------------------------------------------------------- 52 3 Payment --------------------------------------------------------------------------------------------- 52 4 Asphalt Cost Price Adjustment ----------------------------------------------------------------- 52 5
DIVISION 6 6
STRUCTURES 7
CONCRETE STRUCTURES ---------------------------------------------------------------------- 54 8 Construction Requirements --------------------------------------------------------------------- 54 9 Ready-Mix Concrete ------------------------------------------------------------------------------ 54 10 Acceptance of Concrete ------------------------------------------------------------------------- 56 11
DIVISION 8 12
MISCELLANEOUS CONSTRUCTION 13
EROSION CONTROL AND WATER POLLUTION CONTROL --------------------------- 57 14
Construction Requirements --------------------------------------------------------------------- 57 15 General ---------------------------------------------------------------------------------------------- 57 16
ILLUMINATION, TRAFFIC SIGNAL SYSTEMS, INTELLIGENT TRANSPORTATION 17
SYSTEMS, AND ELECTRICAL ------------------------------------------------------------- 57 18 Materials --------------------------------------------------------------------------------------------- 57 19 Conduit, Innerduct, and Outerduct ------------------------------------------------------------ 58 20 Fiber Optic Cable, Electrical Conductors, and Cable ------------------------------------- 58 21 Vehicle Detector ----------------------------------------------------------------------------------- 58 22 Equipment List And Drawings ------------------------------------------------------------------ 59 23 Construction Requirements --------------------------------------------------------------------- 59 24 General ---------------------------------------------------------------------------------------------- 59 25 Existing System Disruption and Restoration ------------------------------------------------ 60 26 Payment --------------------------------------------------------------------------------------------- 62 27 PERMANENT SIGNING --------------------------------------------------------------------------- 62 28 Materials --------------------------------------------------------------------------------------------- 62 29 Manufacturers for Steel Roadside Sign Supports ----------------------------------------- 64 30
DIVISION 9 31
MATERIALS 32
APPENDICES ---------------------------------------------------------------------------------------- 64 33 STANDARD PLANS --------------------------------------------------------------------------------- 65 34
CONGESTION MANAGEMENT
25C512 1
INTRODUCTION 1
This Contract shall be constructed in accordance with the 2026 Standard Specifications for 3 Road, Bridge, and Municipal Construction. 4
SPECIAL PROVISIONS 6
Several types of Special Provisions are included in this contract; General, Region, Bridges 8 and Structures, and Project Specific. Special Provisions types are differentiated as follows: 9
(date) General Special Provision 11 (******) Notes a revision to a General Special Provision 12 and also notes a Project Specific Special 13 Provision. 14 (Regions1 date) Region Special Provision 15
General Special Provisions are similar to Standard Specifications in that they typically apply 17 to many projects, usually in more than one Region. Usually, the only difference from one 18 project to another is the inclusion of variable project data, inserted as a “fill-in”. 19 Region Special Provisions are commonly applicable within the designated Region. Region 21 designations are as follows: 22
Regions1 24 ER Eastern Region 25 NCR North Central Region 26 NWR Northwest Region 27 OR Olympic Region 28 SCR South Central Region 29 SWR Southwest Region 30 WSF Washington State Ferries Division 31
Project Specific Special Provisions normally appear only in the contract for which they were 33 developed. 34
Division 1 36 General Requirements 37
DESCRIPTION OF WORK 39
(March 13, 1995) 41 This Contract provides for the improvement of *** SR 512 MP 0.27 to MP 2.65 in Pierce 42 County, by performing full-depth reconstruction at the end of the SR7 on-ramp to SR 512, 43 removing and replacing the ramp illumination system, installing a Wavetronix data station, 44 replacing pavement markings, implementing traffic control *** and other work, all in 45 accordance with the attached Contract Plans, these Contract Provisions, and the Standard 46 Specifications. 47 Bid Procedures and Conditions 49 Examination of Plans, Specifications and Site of Work 51
CONGESTION MANAGEMENT
25C512 2
General 1
Section 1-02.4(1) is supplemented with the following: 3
(September 3, 2019) 5 The Reference Information for this project is available for review by the bidder at the 6 following location: 7
*** ftp.wsdot.wa.gov - /contracts/ *** 9
The Reference Information includes the following: 11
*** 13
1) Base Maps 14
2) Plan Sheet Files 15
3) Quantity Tabulations 16 *** 17
Preparation of Proposal 19 (November 20, 2023) 21 The fourth and fifth paragraphs of Section 1-02.6 are deleted. 22 Section 1-02.6 is supplemented with the following: 24
(November 4, 2025) 26 Bidder Questionnaire 27 The Bidder shall submit with their Bid a Bidder Questionnaire form (WSDOT Form #272-28 022). This shall be filled out for each firm who submitted a bid or quote in attempt to 29 participate in the project whether they were successful or not and include the following 30 information: 31
1. Firm name; 33
2. Firm address including ZIP code; 35
3. Firm’s status as a DBE or non-DBE; 37
4. NAICS code applicable to each scope of work the firm sought to perform in its 39 bid; 40
5. Age of the firm; and 42
6. The annual gross receipts of the firm. The Bidder may obtain this information by 44 asking each firm to indicate into what gross receipts bracket they fit (less than 45 $1 million; $1-3 million; $3-6 million; $6-10 million; $10-20 million; $20-30.72 46 million; or greater than $30.72 million) rather than requesting an exact figure 47 from the firm. 48
This form shall be received at the same location and no later than the time required for 50 the delivery of the Proposal. Failure to comply with this requirement will cause this Bid to 51 be considered irregular in accordance with Section 1-02.13. 52 https://ftp.wsdot.wa.gov/contracts/
CONGESTION MANAGEMENT
25C512 3
The Contractor may correct errors to items 2 through 6 above on the Bidder Questionnaire 2 form for a period up to 48 hours after bid opening. Bidder Questionnaire forms that are 3 still incorrect after the correction period will be determined irregular. New 4 Firm/Subcontractors may not be added to the form during the correction period. A Bidder 5 Questionnaire form that fails to list a Firm/Subcontractor that appears on a different form 6 will be considered irregular in accordance with Section 1-02.13. 7
Delivery of Proposal 9 The first paragraph of Section 1-02.9 is revised to read: 11
(April 9, 2026) 13 For projects scheduled for Bid opening in Olympia, the Proposal shall be sealed and 14 submitted in the envelope provided with it to the address provided below or shall be 15 submitted electronically via Bidx.com through AASHTOWare Project Bids™ software 16 “BidExpress®.” The Bidder shall fill in all blanks on this envelope to ensure proper 17 handling and delivery. Bids are to be received no later than 11:00:59 A.M. Pacific time on 18 the date of Bid opening: 19
Washington State Department of Transportation 21 Room A101 22 1655 2nd Ave SW 23 Tumwater WA 98512 24
Public Opening of Proposals 26 Section 1-02.12 is supplemented with the following: 28
(August 3, 2015) 30 Date of Opening Bids 31 The bid opening date for this project is *** Wednesday, July 22, 2026 ***. Bids received 32 will be publicly opened and read after 11:00:59 A. M. Pacific Time on this date. 33
Scope of the Work 35 Coordination of Contract Documents, Plans, Special Provisions, 37 Specifications, and Addenda 38 Section 1-04.2 is supplemented with the following: 40
(November 20, 2023) 42 Document Control 43 This specification applies to project documentation and correspondence that occurs after 44 execution of the Contract. The Contractor shall submit all project documentation and 45 correspondence for this Contract in electronic format utilizing the WSDOT Unifier system. 46 Documents that are received by means other than the WSDOT Unifier system will be 47 rejected, except as allowed by this special provision or specifically approved by the 48 Engineer. 49
CONGESTION MANAGEMENT
25C512 4
The Engineer may reject documents that are deemed unsuitable. This includes 1 documents that are illegible, unreadable, locked, etc. Forms that require further 2 information from WSDOT must be unlocked. 3 The Contractor shall submit to the Contracting Agency a Unifier Access Request Form 5 (WSDOT Form 134-092) to WSDOT e-Construction Support (e-6 ConstructionSupport@wsdot.wa.gov) designating all individuals requiring access to 7 WSDOT Unifier no later than 5 days following Contract Award. Training for WSDOT 8 Unifier will be provided by WSDOT at no cost to the Contractor. Throughout the life of the 9 Project, all changes to the Contractor’s personnel who require access to the WSDOT 10 Unifier system shall be submitted on a Unifier Access Request Form. 11 All signed documents shall be in PDF format and will require an electronic signature. An 13 electronic signature is defined as a symbol, or process attached to or logically associated 14 with a record and executed or adopted by a person with the intent to sign the record. All 15 signed documents shall be in PDF format. 16 WSDOT has provided an application to be used to apply electronic signatures to the 18 following documents: 19
Change Orders that are not Minor Change Orders 21 421-009 Release – Retained Percentage (Except Landscaping) 22 134-146 Final Contract Voucher Certificate 23
When the Contract specifies that documentation is to be submitted through other web-25 based systems, such as the Diversity Management and Compliance System, or email 26 addresses, the Contractor shall utilize those systems and email addresses accordingly. 27 Before a Completion Date will be established by the Contracting Agency, all contractor 29 active tasks in Unifier shall be closed out or acknowledged. 30 All costs for submitting project documentation electronically shall be included in the 32 Contract prices for the Bid items of Work involved. 33
Control of Work 35 Conformity with and Deviations from Plans and Stakes 37 Section 1-05.4 is supplemented with the following: 39
(January 13, 2021) 41 Contractor Surveying - Roadway 42 The Contracting Agency has provided primary survey control in the Plans. 43 The Contractor shall be responsible for setting, maintaining, and resetting all alignment 45 stakes, slope stakes, and grades necessary for the construction of the roadbed, drainage, 46 surfacing, paving, channelization and pavement marking, illumination and signals, 47 guardrails and barriers, and signing. Except for the survey control data to be furnished 48 by the Contracting Agency, calculations, surveying, and measuring required for setting 49 and maintaining the necessary lines and grades shall be the Contractor's responsibility. 50 mailto:e-ConstructionSupport@wsdot.wa.gov mailto:e-ConstructionSupport@wsdot.wa.gov
CONGESTION MANAGEMENT
25C512 5
The Contractor shall inform the Engineer when monuments are discovered that were not 1 identified in the Plans and construction activity may disturb or damage the monuments. 2 All monuments noted on the plans “DO NOT DISTURB” shall be protected throughout the 3 length of the project or be replaced at the Contractors expense. 4 Detailed survey records shall be maintained, including a description of the work 6 performed on each shift, the methods utilized, and the control points used. The record 7 shall be adequate to allow the survey to be reproduced. A copy of each day's record shall 8 be provided to the Engineer within three working days after the end of the shift. 9 The meaning of words and terms used in this provision shall be as listed in "Definitions of 11 Surveying and Associated Terms" current edition, published by the American Congress 12 on Surveying and Mapping and the American Society of Civil Engineers. 13 The survey work shall include but not be limited to the following: 15
1. Verify the primary horizontal and vertical control furnished by the Contracting 17 Agency, and expand into secondary control by adding stakes and hubs as well 18 as additional survey control needed for the project. Provide descriptions of 19 secondary control to the Contracting Agency. The description shall include 20 coordinates and elevations of all secondary control points. 21
2. Establish, the centerlines of all alignments, by placing hubs, stakes, or marks on 23 centerline or on offsets to centerline at all curve points (PCs, PTs, and PIs) and 24 at points on the alignments spaced no further than 50 feet. 25
3. Establish clearing limits, placing stakes at all angle points and at intermediate 27 points not more than 50 feet apart. The clearing and grubbing limits shall be 5 28 feet beyond the toe of a fill and 10 feet beyond the top of a cut unless otherwise 29 shown in the Plans. 30
4. Establish grading limits, placing slope stakes at centerline increments not more 32 than 50 feet apart. Establish offset reference to all slope stakes. If Global 33 Positioning Satellite (GPS) Machine Controls are used to provide grade control, 34 then slope stakes may be omitted at the discretion of the Contractor 35
5. Establish the horizontal and vertical location of all drainage features, placing 37 offset stakes to all drainage structures and to pipes at a horizontal interval not 38 greater than 25 feet. 39
6. Establish roadbed and surfacing elevations by placing stakes at the top of 41 subgrade and at the top of each course of surfacing. Subgrade and surfacing 42 stakes shall be set at horizontal intervals not greater than 50 feet in tangent 43 sections, 25 feet in curve sections with a radius less than 300 feet, and at 10-44 foot intervals in intersection radii with a radius less than 10 feet. Transversely, 45 stakes shall be placed at all locations where the roadway slope changes and at 46 additional points such that the transverse spacing of stakes is not more than 12 47 feet. If GPS Machine Controls are used to provide grade control, then roadbed 48 and surfacing stakes may be omitted at the discretion of the Contractor. 49
7. Establish intermediate elevation benchmarks as needed to check work 51 throughout the project. 52
CONGESTION MANAGEMENT
25C512 6
8. Provide references for paving pins at 25-foot intervals or provide simultaneous 2 surveying to establish location and elevation of paving pins as they are being 3 placed. 4
9. For all other types of construction included in this provision, (including but not 6 limited to channelization and pavement marking, illumination and signals, 7 guardrails and barriers, and signing) provide staking and layout as necessary to 8 adequately locate, construct, and check the specific construction activity. 9
10. Contractor shall determine if changes are needed to the profiles or roadway 11 sections shown in the Contract Plans in order to achieve proper smoothness 12 and drainage where matching into existing features, such as a smooth transition 13 from new pavement to existing pavement. The Contractor shall submit these 14 changes to the Engineer for review and approval 10 days prior to the beginning 15 of work. 16
The Contractor shall provide the Contracting Agency copies of any calculations and 18 staking data when requested by the Engineer. 19 The Contractor shall ensure a surveying accuracy within the following tolerances: 21
Vertical Horizontal 23 Slope stakes ±0.10 feet ±0.10 feet 24 Subgrade grade stakes set 25
0.04 feet below grade ±0.01 feet ±0.5 feet 26 (parallel to alignment) 27 ±0.1 feet 28 (normal to alignment) 29 Stationing on roadway N/A ±0.1 feet 31 Alignment on roadway N/A ±0.04 feet 32 Surfacing grade stakes ±0.01 feet ±0.5 feet 33 (parallel to alignment) 34 ±0.1 feet 35 (normal to alignment) 36 Roadway paving pins for 38 surfacing or paving ±0.01 feet ±0.2 feet 39
(parallel to alignment) 40 ±0.1 feet 41 (normal to alignment) 42
The Contracting Agency may spot-check the Contractor's surveying. These spot-checks 44 will not change the requirements for normal checking by the Contractor. 45 When staking roadway alignment and stationing, the Contractor shall perform 47 independent checks from different secondary control to ensure that the points staked are 48 within the specified survey accuracy tolerances. 49 The Contractor shall calculate coordinates for the alignment. The Contracting Agency will 51 verify these coordinates prior to issuing approval to the Contractor for commencing with 52
CONGESTION MANAGEMENT
25C512 7 the work. The Contracting Agency will require up to seven calendar days from the date 1 the data is received. 2 Contract work to be performed using contractor-provided stakes shall not begin until the 4 stakes are approved by the Contracting Agency. Such approval shall not relieve the 5 Contractor of responsibility for the accuracy of the stakes. 6
Stakes shall be marked in accordance with Standard Plan A10.10. When stakes are 8 needed that are not described in the Plans, then those stakes shall be marked, at no 9 additional cost to the Contracting Agency as ordered by the Engineer. 10 Payment 12 Payment will be made for the following bid item when included in the proposal: 13
"Roadway Surveying", lump sum. 15
The lump sum contract price for "Roadway Surveying" shall be full pay for all labor, 17 equipment, materials, and supervision utilized to perform the Work specified, including 18 any resurveying, checking, correction of errors, replacement of missing or damaged 19 stakes, and coordination efforts. 20
Cooperation with Other Contractors 22 Section 1-05.14 is supplemented with the following: 24
(March 20, 2025) 26 Speed Safety Camera System Vendor 27 Coordination with a vendor managed by the Contracting Agency to provide portable 28 Speed Safety Camera Systems (SSCS) when workers are present within the work zone 29 may be required. If a SSCS is used on this Contract, the SSCS vendor’s field personnel 30 will need to enter the temporary traffic control zone to place and remove required signage 31 and equipment to implement the automated speed enforcement. The SSCS vendor may 32 document the work zone traffic control setup provided by the Contractor to confirm 33 workers are present prior to commencing operations with the SSCS. 34 The Engineer will set up a coordination meeting between the Contractor’s designated 36 traffic control manager, traffic control supervisor, the Contracting Agency, and the SSCS 37 vendor’s field personnel a minimum of 5 working days prior to the first anticipated 38 implementation date of the SSCS. At a minimum, coordination will include the following: 39
1. The anticipated date and time the SSCS vendor will be on site. 41
2. The expected work area location and temporary traffic control or staged traffic 43 plan that will be in place when the vendor will be on site, including the location(s) 44 of any Contractor-provided Radar Speed Display Sign (RSDS) if included in the 45 project. 46
3. Location for the SSCS vendor’s enforcement unit, photo enforcement sign, and 48
RSDS (may be vendor-provided if one is not provided by the Contractor). 49
4. Provide contact information between Contractor’s traffic control manager, traffic 51 control supervisor, Contracting Agency staff, and SSCS vendor. 52
CONGESTION MANAGEMENT
25C512 8
Control of Material 2 Section 1-06 is supplemented with the following: 4 Buy America Requirements 6
(October 1, 2025) 8 General Requirements 9 In accordance with Buy America requirements contained in 23 CFR 635.410 and 2 CFR 10 184, the following materials must be produced in the United States: 11
1. All Iron or Steel Products used in the project. This means all manufacturing 13 processes, from the initial melting stage through the application of coatings, 14 occurred in the United States. 15
2. All Manufactured Products used in the project. This means the manufactured 17 product was manufactured (final assembly) in the United States. 18
3. All Construction Materials used in the project. This means that all manufacturing 20 processes for the construction material occurred in the United States. 21
An article, material, or supply will be classified in one of four categories: 1) Iron or Steel 23 Product, 2) Manufactured Product, 3) Construction Material, or 4) Excluded Material. Only 24 a single category will apply to an item except as follows: 25
1. With respect to precast concrete products that are classified as Manufactured 27 Products, the components of precast concrete products that consist wholly or 28 predominantly of iron, steel, or combination of both shall meet the requirements 29 for and be tracked as an Iron or Steel Product. The item shall also meet the 30 requirements for and be tracked as a Manufactured Product. 31
2. With respect to intelligent transportation systems and other electronic hardware 33 systems that are classified as Manufactured Products, the cabinets or other 34 enclosures of such systems that consist wholly or predominantly of iron, steel, 35 or a combination of both, shall meet the requirements for and be tracked as an 36 Iron or Steel Products. The item shall also meet the requirements for and be 37 tracked as a Manufactured Product. 38
Some contract items are composed of multiple parts that may fall into different categories. 40 Individual components will be categorized as a Construction Material, a Manufactured 41 Product, an Iron or Steel Product, or an excluded material based on their composition 42 when they arrive at the staging area or work site. 43 Definitions 45
1. Construction Material: Defined as any article, material, or supply brought to the 46 construction site for incorporation into the final product. Construction materials 47 include an article, material, or supply that is or consists primarily of: 48
a. Non-ferrous metals including all manufacturing processes, from initial smelting 50 or melting through final shaping, coating, and assembly; 51
CONGESTION MANAGEMENT
25C512 9
b. Plastic and polymer-based products including all manufacturing processes, from 1 initial combination of constituent plastic or polymer-based inputs, or, where 2 applicable, constituent composite materials, until the item is in its final form); 3
c. Glass including all manufacturing processes, from initial batching and melting of 5 raw materials through annealing, cooling, and cutting); 6
d. Fiber optic cable (includes drop cable) including all manufacturing processes, 8 from initial ribboning (if applicable), through buffering, fiber stranding and 9 jacketing, (fiber optic cable also includes the standards for glass and optical 10 fiber); 11
e. Optical fiber including all manufacturing processes, from the initial preform 13 fabrication stage, though the completion of the draw; 14
f. Lumber including all manufacturing processes, from initial debarking through 16 treatment and planing; 17
g. Drywall including all manufacturing processes, from initial blending of mined or 19 synthetic gypsum plaster and additives through cutting and drying of 20 sandwiched panels; or 21
h. Engineered wood including all manufacturing processes from the initial 23 combination of constituent materials until the wood product is in its final form. 24 If a Construction Material is not manufactured in the United States it shall be 26 considered a Foreign Construction Material. 27
2. Excluded Material: A material where Buy America requirements do not apply. This 29 includes the following: 30
a. Materials excluded by Section 70917(c) of the Buy America, Build America Act 32 with respect to aggregates this includes cement and cementitious materials, 33 aggregates such as stone, sand, or gravel or aggregate binding agents or 34 additives. These materials shall be classified as excluded materials based on 35 the composition when brought to the work site. It also includes combinations of 36 these excluded materials when mixtures of Excluded Materials are delivered to 37 the work site without final form for incorporation into the project (i.e. wet concrete 38 and HMA). If they are formed prior to delivery, they are a Manufactured Product 39 and not an Excluded Material. 40
b. Temporary materials that are not being permanently incorporated into the 42 project. 43
c. Raw or minimal processed materials where the article, material, or supply does 45 not fall into any of the categories, as it is not a Manufactured Product, an Iron or 46 Steel Product, or a Construction Material and when these materials are 47 delivered to the work site without final form for incorporation into the product (i.e. 48 seed mix and topsoil). If they are formed prior to delivery, and are not an Iron or 49 Steel Product or a Construction Material, they are a Manufactured Product and 50 not an Excluded Material. 51
CONGESTION MANAGEMENT
25C512 10
3. Iron or Steel Product: An article, material, or supply that consist of wholly or 1 predominantly of iron or steel or a combination of both. To be considered 2 predominantly of iron or steel or a combination of both means that the cost of the iron 3 and steel content exceeds 50 percent of the total cost of all its components. The 4 cost of iron and steel is based on a good faith estimate of the cost of the iron or steel 5 components. 6
4. Manufactured Product: A Manufactured Product includes any item produced as a 8 result of the manufacturing process. Items that should be treated as a manufactured 9 product (rather than a construction material) are: 1) items that consist of two or more 10 of the listed construction materials that have been combined together through a 11 manufacturing process, and 2) items that include at least one of the listed 12 construction materials as defined above, combined with a material that is not listed 13 through a manufacturing process. 14
If a product is not an Iron or Steel Product, a Construction Material, or an Excluded 16
Material, it is a Manufactured Product. 17 If a Manufactured Material is not manufactured in the United States, it shall be 19 considered a Foreign Manufactured Product. 20
5. United States: To further define the coverage, a domestic product is a manufactured 22 steel construction material that was produced in one of the 50 states, the District of 23 Columbia, Puerto Rico, or in the territories and possessions of the United States. 24
Iron or Steel Product Requirements 26 Iron or Steel Products that are permanently incorporated into the project shall consist of 27 American-made materials only. Buy America requirements do not apply to temporary steel 28 or iron items, e.g., temporary sheet piling, temporary bridges, steel scaffolding and 29 falsework. 30 Minor amounts of foreign steel and iron may be utilized in this project provided the cost 32 of the foreign material used does not exceed one-tenth of one percent of the total contract 33 cost or $2,500.00, whichever is greater. 34 American-made material is defined as material having all manufacturing processes 36 occurring domestically. 37 If domestically produced steel billets or iron ingots are exported outside of the United 39 States, as defined above, for any manufacturing process then the resulting product does 40 not conform to the Buy America requirements. Additionally, products manufactured 41 domestically from foreign source steel billets or iron ingots do not conform to the Buy 42 America requirements because the initial melting and mixing of alloys to create the 43 material occurred in a foreign country. 44 Manufacturing begins with the initial melting and mixing and continues through the coating 46 stage. Any process which modifies the chemical content, the physical size or shape, or 47 the final finish is considered a manufacturing process. The processes include rolling, 48 extruding, machining, bending, grinding, drilling, welding, and coating. The action of 49 applying a coating to steel or iron is deemed a manufacturing process. Coating includes 50 epoxy coating, galvanizing, aluminizing, painting, and any other coating that protects or 51
CONGESTION MANAGEMENT
25C512 11 enhances the value of steel or iron. Any process from the original reduction from ore to 1 the finished product constitutes a manufacturing process for iron. 2 Due to a nationwide waiver, Buy America requirements do not apply to raw materials (iron 4 ore and alloys), scrap (recycled steel or iron), and pig iron ore processed, pelletized, and 5 reduced iron ore. 6 The following are considered to be steel manufacturing processes: 8
1. Production of steel by any of the following processes: 10
a. Open hearth furnace. 12
b. Basic oxygen. 14
c. Electric furnace. 16
d. Direct reduction. 18
2. Rolling, heat treating, and any other similar processing. 20
3. Fabrication of the products: 22
a. Spinning wire into cable or strand. 24
b. Corrugating and rolling into culverts. 26
c. Shop fabrication. 28
A certification of materials origin will be required for all iron or steel products prior to such 30 items being incorporated into the permanent work. The Contractor will not receive 31 payment until the certification is received by the Engineer. The certification shall be on 32 WSDOT Form 350-109 provided by the Engineer, or such other form approved by the 33 Contracting Agency, provided it contains the same information as WSDOT Form 350-109. 34 Manufactured Products and Construction Material Requirements 36 A Contractor provided certification of materials origin will be required before each 37 progress estimate or payment. The Contractor will not receive payment until the 38 certification is received by the Engineer. The Contractor shall certify that all Manufactured 39 Products and all Construction Materials installed during the current progress estimate 40 period meet the Buy America requirements. The certification shall be on WSDOT Form 41 350-108 provided by the Engineer, or such other form approved by the Contracting 42 Agency, provided it contains the same information as WSDOT Form 350-108. 43
Iron or Steel Products in a Manufactured Product 45 In addition to providing the certification of materials origin for the Manufactured 46 Product, the iron or steel products in a manufactured product are subject to the Buy 47 America requirements as follows: 48
1. When a precast concrete product is classified as a Manufactured Product, 50 the components that are an Iron or Steel Product shall follow the “Iron or 51 Steel Requirements” of this Specification. 52
CONGESTION MANAGEMENT
25C512 12
2. When an electronic hardware system such as an intelligent transportation 2 system is classified as a Manufactured Product, the cabinets and the other 3 enclosures of such systems that are an Iron or Steel Product shall follow 4 the “Iron or Steel Requirements” of this Specification. 5
Waiver for De Minimis Costs 7 Minor amounts of Foreign Construction Materials and Foreign Manufactured Products 8 may be utilized in this project, provided that the total cost of the Foreign Construction 9 Materials and Foreign Manufactured Products does not exceed $1,000,000 and does not 10 exceed 5 percent of the total applicable material costs calculated as follows: 11 𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑜𝑜𝑜𝑜 𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹 𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶 𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀 + 𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑜𝑜𝑜𝑜 𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹 𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀 𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃
𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇 𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎 𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 < 0.05 13
The total applicable material costs shall be the sum of the costs of all Construction 15 Materials, all Iron or Steel Products, and all Manufactured Products. Total applicable 16 material costs does not include Excluded Materials. 17
Legal Relations and Responsibilities to the Public 19 Laws to be Observed 21 Section 1-07.1 is supplemented with the following: 23
(March 9, 2026) 25 Unmanned Aircraft Systems (UAS) 26 The procurement and/or use of any drone (UAS) on this Contract shall comply with the 27 following directives: 28
• National Defense Authorization Act (NDAA) – American Security Drone Act of 30 2023 (ASDA, Pub. L. No. 118-31). 31
• Office of Management and Budget Memorandum M-26-02 – Restrictions on 33 using federal funds to purchase or operate prohibited foreign UAS. 34 Contractors, subcontractors, and lower-tier subcontractors shall not procure, operate, 36 maintain, or process data from prohibited UAS manufactured or assembled by “covered 37 foreign entities” as defined in the Federal Acquisition Security Council (FASC) in the 38 performance of this Contract. 39
Environmental Regulations 41 Section 1-07.5 is supplemented with the following: 43
(September 20, 2010) 45 Environmental Commitments 46 The following Provisions summarize the requirements, in addition to those required 47 elsewhere in the Contract, imposed upon the Contracting Agency by the various 48 documents referenced in the Special Provision Permits and Licenses. Throughout the 49 work, the Contractor shall comply with the following requirements: 50
CONGESTION MANAGEMENT
25C512 13
(April 1, 2019) 1 No *** Staging area or fueling of equipment *** is allowed within *** 200 *** feet of *** 2 any waters of State including wetlands ***. 3
(August 3, 2009) 5 Payment 6 All costs to comply with this special provision for the environmental commitments and 7 requirements are incidental to the contract and are the responsibility of the Contractor. 8 The Contractor shall include all related costs in the associated bid prices of the contract. 9
Air Quality 11
Asbestos Containing Material 13
Section 1-07.5(4)C is supplemented with the following: 15
(October 4, 2021) 17 Asbestos Good Faith Investigation 18 An asbestos Good Faith Investigation (GFI) has been conducted for this project 19 and it has been determined to a reasonable certainty that no known Asbestos 20 Containing Material (ACM) will be disturbed by the work on this project. The 21 asbestos GFI has been provided as Appendix *** B ***. 22
U.S. Fish and Wildlife Service and National Marine Fisheries Service 24
Section 1-07.5(6) is supplemented with the following: 26
(April 2, 2018) 28 The following Provisions summarize the requirements, in addition to those required 29 elsewhere in the Contract, imposed upon the Contracting Agency by the U.S. 30 Fish/Wildlife Services and the National Marine Fisheries Service. Throughout the 31 work, the Contractor shall comply with the following requirements: 32
(April 2, 2018) 34 The Contractor shall provide concrete truck chute cleanout areas to contain 35 fresh concrete and wash water. The Contractor shall dispose of the waste 36 material at a facility permitted to take such waste. 37
Load Limits 39 Section 1-07.7 is supplemented with the following: 41
(March 13, 1995) 43 If the sources of materials provided by the Contractor necessitates hauling over roads 44 other than State Highways, the Contractor shall, at the Contractor's expense, make all 45 arrangements for the use of the haul routes. 46
High-Visibility Apparel 48
Traffic Control Personnel 50
Section 1-07.8(1) is revised to read: 52
CONGESTION MANAGEMENT
25C512 14
(September 16, 2025) 2 All personnel performing the Work described in Section 2-04 (including traffic control 3 supervisors, flaggers, and others performing traffic control labor of any kind) shall 4 comply with the following: 5
1. During daylight hours with clear visibility, workers shall wear a high-visibility 7 ANSI/ISEA 107 Type R Class 2 or 3 garment with background material that 8 are fluorescent yellow-green, fluorescent orange-red, or fluorescent red in 9 color; and a high visibility hardhat that is white, yellow, yellow-green, 10 orange, or red in color; and 11
2. During hours of darkness (½ hour before sunset to ½ hour after sunrise) or 13 other low-visibility conditions (snow, fog, etc.), workers shall wear a high-14 visibility ANSI/ISEA 107 Type R Class 2 or 3 garment with background 15 material that are fluorescent yellow-green, fluorescent orange-red, or 16 fluorescent red in color; a high-visibility lower garment meeting ANSI/ISEA 17 107 Class E, and a high visibility hardhat marked with at least 12 square 18 inches of retroreflective material applied to provide 360 degrees of visibility. 19
Wages 21
General 23
Section 1-07.9(1) is supplemented with the following: 25
(January 6, 2026) 27 The Federal wage rates incorporated in this contract have been established by the 28 Secretary of Labor under United States Department of Labor General Decision No. 29
WA20260001. 30
The State rates incorporated in this contract are applicable to all construction 32 activities associated with this contract. 33
Requirements for Nondiscrimination 35 Section 1-07.11 is supplemented with the following: 37
(May 5, 2025) 39 Requirement for Affirmative Action to Ensure Equal Employment Opportunity 40 In accordance with 41 CFR § 60-4.2, the clauses contained in 1-4 below are required to 42 be included in this Contract. Nothing in this contract alters the Contractor’s responsibility 43 to comply with all applicable Federal regulations, including but not limited to 41 CFR part 44 60 as currently existing or later amended. 45
1. The Contractor's attention is called to the “Equal Opportunity Clause and the 47
Standard Federal Equal Employment Opportunity Construction Contract 48 Specifications” set forth herein. 49
CONGESTION MANAGEMENT
25C512 15
2. The goals and timetables for minority and female participation set by the Office of 1 Federal Contract Compliance Programs, expressed in percentage terms for the 2 Contractor's aggregate work force in each construction craft and in each trade on all 3 construction work in the covered area, are as follows: 4
Women - Statewide 6
Timetable Goal 8
Until further notice 6.9% 10 Minorities - by Standard Metropolitan Statistical Area (SMSA) 11 Spokane, WA: 13
SMSA Counties: 14 Spokane, WA 2.8 15
WA Spokane. 16 Non-SMSA Counties 3.0 17
WA Adams; WA Asotin; WA Columbia; WA Ferry; WA Garfield; WA 18 Lincoln, WA Pend Oreille; WA Stevens; WA Whitman. 19
Richland, WA 21
SMSA Counties: 22 Richland Kennewick, WA 5.4 23
WA Benton; WA Franklin. 24 Non-SMSA Counties 3.6 25
WA Walla Walla. 26 Yakima, WA: 28
SMSA Counties: 29 Yakima, WA 9.7 30
WA Yakima. 31 Non-SMSA Counties 7.2 32
WA Chelan; WA Douglas; WA Grant; WA Kittitas; WA Okanogan. 33 Seattle, WA: 35
SMSA Counties: 36 Seattle Everett, WA 7.2 37
WA King; WA Snohomish. 38 Tacoma, WA 6.2 39
WA Pierce. 40 Non-SMSA Counties 6.1 41
WA Clallam; WA Grays Harbor; WA Island; WA Jefferson; WA Kitsap; 42 WA Lewis; WA Mason; WA Pacific; WA San Juan; WA Skagit; WA 43 Thurston; WA Whatcom. 44
Portland, OR: 46
SMSA Counties: 47 Portland, OR-WA 4.5 48
WA Clark. 49 Non-SMSA Counties 3.8 50
WA Cowlitz; WA Klickitat; WA Skamania; WA Wahkiakum. 51
CONGESTION MANAGEMENT
25C512 16
These goals are applicable to each nonexempt Contractor’s total on-site construction 1 workforce, regardless of whether or not part of that workforce is performing work on 2 a Federal, or federally assisted project, contract, or subcontract until further notice. 3 Compliance with these goals and timetables is enforced by the Office of Federal 4 Contract compliance Programs.