SPRRA224R0074 Questions and Responses.pdf
PDF 72 KB Posted
- Solicitation number
- SPRRA224R0074
- Issued by
-
Defense Logistics Agency Aviation
About this file
This document appears to be a set of Questions and Answers related to a federal contract opportunity for an Environmental Control Unit (ECU) for the Bradley Fighting Vehicle. The key details are:
The solicitation number is SPRRA2-24-R-0074, a small business set-aside opportunity issued by the Defense Logistics Agency Aviation. The agency is requesting drawings, technical data, and pricing for the ECU system, including field modification kits. Respondents had questions about the required drawings, with the agency confirming that additional drawings were provided via secure file transfer. The agency also stated the official solicitation will be posted by the end of July. No other details about product specifications, delivery, pricing, or evaluation criteria were provided in this particular set of questions and responses.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SPRRA224R0074-0003.pdf | ||
| Solicitation AMD 001 SPRRA224R0074 (ECU)_CS Signed.pdf | ||
| Solicitation SPRRA224R0074 CS Signed.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPRRA2-24-R-0074 Questions and Answers as of 6/28/24
Q: Good morning and I hope this email finds you both well! Could you please also provide the Top-Level Drawing for PN 12620762? It looks it was not included with the TDP. Do you know what other documentation will be provided to us during the official solicitation?
A: Additional drawings were provided via DoD SAFE.
Q: Good morning and I hope you had a great weekend. I'm writing to confirm that you received our response. Additionally, do you have any information on when the official solicitation will be released?
A: We have received your response, and the official solicitation will be posted by the end of July. Have a good day!
Q: Just for clarification, are these 3 drawings mentioned specifically for
Field Modification kits only, or are you requiring new kits for the entire installation, which would require the full bill of materials to be quoted/ordered – is that correct?
A: Yes, the installation drawings are instructions on how to install the ECU system onto the vehicle as a Field Modification (post vehicle production).
Q: Good morning Team, After reviewing the data package for the ECU:
Attached is the list of drawings that were not included/part of the drawing package given to OPDT in support of the ECU requirement.
Once you provide OPDT with the missing drawings we will then go through each drawing and identify if there are any additional drawings missing/still needed. If you can get these to us as soon as possible that would be great as I currently have some material items out for quotes.
A: Additional drawings were sent via DoD SAFE.