RFP.SPRMM118RHB78.pdf

PDF 4 MB Posted

Attached to
PROCUREMENT OF AN AUDIO LEVEL METER WHICH IS A COMPONENT OF THE GPETE TEST PROGRAM
Solicitation number
SPRMM118RHB78
Issued by

About this file

RFP.SPRMM118RHB78

View the file

Other files

File Type Posted
18RHB78.AMEND0001.doc DOC document
Market_Survey.18RHB69.doc DOC document
SCAT_4737-NRL-PD-FINAL-SPRMM118RHB78.20180921.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTINUATION SHEET SPRMM1-18-R-HB78

Page 2A of 53

(PLEASE NOTE THAT SECTIONS B THROUGH H MAY NOT BE IN ALPHABETICAL ORDER.

PLEASE READ SOLICITATION IN ITS ENTIRETY).

SECTION A - GENERAL INFORMATION FOR OFFERORS

1. The purpose of this solicitation is to establish an indefinite-delivery type contract for the supplies listed in Section B, that will provide stock coverage for customers both overseas and in the United States, including Alaska and Hawaii, and our possessions.

2. Under this solicitation, the resulting contract will be a Firm-Fixed-Price, Indefinite-Quantity Contract issued under FAR Part 15, with three (3) one year base periods and two (2) one year option periods. The total contract period will be five years. The terms “year” or “contract year,” as used in this solicitation, mean a period of 365 days beginning on the contract start date and every 365 days thereafter, except for a leap year, in which the contract year shall be 366 days.

3. The method used to place orders under this contract will be: Delivery Orders placed by DLA Maritime at Mechanicsburg (DLA-Mech). DLA-Mech will issue delivery orders with the awardee for the supplies cited in Section B. This contract is not obligating any funds. Funding will be provided on each delivery order placed under the contract.

4. The proposals received in response to this solicitation will be evaluated under “Lowest Price Technically Acceptable” procedures as described in Section M of this solicitation.

5. Some clauses/provisions may not appear in the correct section (D-M), due to system constraints.

6. The stated contract minimum and maximum is as follows:

a. Stated Contract Minimum: $9,000.00

b. Stated Contract Maximum: $675,000.00

The minimum value is calculated as ten (10) percent of the estimated annual demand value (ADV) for this item. The maximum value is calculated as seven hundred and fifty (750) percent of the estimated ADV.

*Note: Contract period as defined in this clause means the extended contract shall be inclusive of any/all option periods.

7. Contract Data Requirements List (CDRL) – Offerors must take note of the CDRLs (Exhibit A) when preparing proposals.

8. Production Lot Testing of Two (2) units may be required. If required, the PLT units will be requested upon placement of the initial delivery order and will be due to NRL within 45 days after date of order or another agreed upon timeframe.

9. **Note Attachment 4 regarding MIL-STD-129, MIL-STD-130, and IUID marking**

CONTINUED ON NEXT PAGE

Page 2B of 53

10. Upon award the contractor shall affix a calibration label to each unit of General Purpose Electronic Test Equipment (GPETE), deliverable under the resulting contract. The calibration label shall include the date the instrument was calibrated by the contractor, and the correctness of calibration shall be certified by proposed signature thereon. Further, the contractor shall affix the next due date for calibration in accordance with the following interval: Minimum 12 months.

11. Upon award the contractor shall affix a warranty label to each unit of General Purpose Electronic Test Equipment (GPETE), deliverable under the resulting contract. The warranty label shall indicate the Nomenclature, Manufacturer, CAGE, Model Number, NSN, Contract Number, and Warranty expiration date.

12. One of more of the following Post Award conferences may be held at NAVSUP WSS Mechanicsburg at the discretion of the Contracting Officer: Guidance Conference and/or Provisioning Conference:

a. GUIDANCE CONFERENCE REQUIREMENTS – The contractor shall attend a Guidance Conference conducted at NAVSUPWSS Mechanicsburg. The purpose of this conference is review of provisioning requirements as outlined in MIL-PRF-49506. This conference is to be held no later than 120 days after award of contract and will normally be one day in duration.

b. PROVISIONING CONFERENCE REQUIREMENTS – The contractor will ensure that one unit deliverable under this contract will be available for the provisioning conference. The contractor will ensure that the unit is at the provisioning conference, and will provide a representative capable of disassembling/reassembling the unit to answer support/repair questions. In addition, the contractor will provide an administrative/contractual representative capable of answering administrative and/or contractual questions. The contractor shall also be responsible for the refurbishment/recalibration of the unit before delivering the unit to the Navy. The cost for supplying technical documentation and the cost of the last deliverable unit will be withheld until these requirements are satisfied.

SECTION B – SCHEDULE OF SUPPLIES

This solicitation is for the acquisition of items manufactured per stated specifications (SCAT 4737) provided as an attachment to this solicitation. Award will be made on an all or nothing basis.

1. Offerors shall provide their prices in the Section B Pricing Spreadsheet found below. NOTE: Pricing is not being requested until evaluation of Technical Proposals and Bid Sample Testing (if necessary) is complete. Offerors will be notified of their approval via email, which will specify the price proposal due date.

2. Section B Spreadsheet Information/Instructions.

CLIN NSN Item Description UM Specification Number

0001 To Be Assigned

SOUND LEVEL

METER EA

SCAT 4737 dated

21 SEP 2018

CONTINUED ON NEXT PAGE

Page 2C of 53

3. Section B – Pricing Spreadsheet.

CLIN NSN ADQ Quantity Ranges

FROM

Quantity Ranges

TO

Base Year

Base Year

Base Year

Option Year

Option Year

0001 To Be Assigned 30 1 10 11 20 21 30 31+

ADQ: Estimated Annual Demand Quantity

Quantity Ranges: Self-Explanatory (Offeror is authorized to quote alternate quantity ranges considered to be more advantageous to the Government)

Base Year One – Option Year Two: Offeror shall fill in each base year and each option year unit price for each quantity range. All unit prices shall be priced as FOB Origin. Unit prices proposed shall not include shipping costs.

4. Please identify the following, if different from your facility/cage. If locations are the same as offeror’s address, offeror can indicate “SAME”.

CAGE for performance: ________________ CAGE for inspection: ________________ CAGE for acceptance: ________________

SECTION D – PACKAGING AND MARKING

Packaging shall be in accordance with MIL-STD-2073 unless otherwise specified in the delivery order, as certain immediate use requirements may allow for commercial packaging in accordance with ASTM-D-3951

– Standard Practice for Commercial items. The MIL-STD-2073 packaging shall be in conformance with the Packaging Requirements Code as shown below:

PACKAGING REQUIREMENT CODE

PCK CTGY CD: ZZZ0

HM QUP ICQ PMT CD PM WM CUD CT UC LP IC UCL SP MK PACK UNIT PKWT

N 001 000 51 1 00 GB NA D ED A 00 B 03 EFF

UNIT PKCU OPI CAGE SPI NUMBER REV SPI DATE CONTAINER NSN

O

UNIQUE: N SUPPLEMENTAL INSTRUCTIONS

PPPM LEVEL: SHELF LIFE CD: 0 SHELF LIFE ACTION CD: 00

Page 2D of 53

SECTION E – INSPECTION AND ACCEPTANCE

NAVSUPWSSEA02 - PRODUCTION LOT TESTING (NOV 1992)

Production Lot Testing in accordance with the Specification incorporated in Section C of the contract is required. The Contractor shall deliver (2) unit(s) to NAVAL RESEARCH LAB CD5524, ATTN: JOE MOLNAR, WASHINGTON, DC for production lot testing no later than 45 days after contract delivery order award. The Contracting Officer shall notify, in writing, of the approval, conditional approval, or disapproval of the samples report within <60> days of receipt of same. The rights and obligations of, and remedies available to the Contractor and the Government are those detailed in FAR Clause 52.246-2 Inspection of Supplies-Fixed Price incorporated by reference in this contract with respect to approval or disapproval of the Production Lot Testing. Shipment of the Production Lot shall be accomplished as soon as possible after notification of approval of samples or test reports. Samples that are destroyed in testing will not be returned to the Contractor. Samples that are not destroyed through testing will be returned at contractor's expense via commercial collect Bill of Lading.*

(*Production lot test samples that are not destroyed in testing and that satisfy contract requirements may be delivered as part of the total contract quantity however cannot be shipped until PLT approval of units is received).

SECTION F – DELIVERIES

1. Place of Delivery: The place of delivery for all items to be acquired hereunder will be specified in individual delivery orders issued under the resultant Indefinite-Delivery Indefinite-Quantity contract.

2. Desired/Required Delivery:

DLA desires delivery of a quantity range up to 30 units to be delivered within 90 days after receipt of a delivery order.

If the offeror is unable to meet the desired delivery schedule stated above, it may, without prejudicing evaluation of its offer, propose a delivery schedule below. However the offeror’s proposed delivery schedule must not extend the delivery beyond the time for delivery in the Government’s required delivery schedule as follows:

DLA requires delivery of a quantity range up to 30 units to be delivered within 120 days after receipt of a delivery order.

Contractor’s proposed delivery schedule: _______________________________________________

1. ACCELERATED DELIVERIES: Accelerated deliveries in advance of the specified delivery schedule are authorized. Any accelerated delivery will be at no additional expense to the Government, unless specifically authorized by the Procuring or Administrative Contracting Officer.

2. PARTIAL SHIPMENTS: Shipments of item quantities less than each line item quantity specified in the delivery order schedule are authorized. Multiple shipments to one destination are authorized. Any partial shipment will be at no additional expense to the Government, unless specifically authorized by the Procuring or Administrative Contracting Officer.

PAGE 52A OF 53

SECTION L - CONTINUED

NAVSUPWSSLA01 - SUBMISSION OF PROPOSALS

This is a two-step solicitation. The first step is a request for technical proposals and bid sample testing, upon acceptance of the submitted technical proposals and bid samples, the second step is a request for price proposals.

Step One -

Request for Technical Proposals:

Offerors shall submit a technical proposal, excluding price, in accordance with the Purchase Description for Sound Level Meter (SCAT 4737) provided as Attachment 3 to this solicitation. Offeror’s technical proposals shall be sufficiently detailed, specific, and complete as to enable Government personnel to make a thorough evaluation of the proposal and a sound determination that the offeror will have a reasonable likelihood of meeting the requirements and objectives of the Government. Offerors are not required, at this time, to submit a signed copy of the solicitation.

This Request for Technical Proposals is not binding on the Government and does not in any way commit the Government to pay for any costs incurred in the preparation and submission of the requested technical proposal.

Each offeror shall submit its technical proposal by the date specified on page 1 of 57 of the solicitation to:

Amy Puchalsky Contracting Specialist DLA Maritime at Mechanicsburg 5450 Carlisle Pike, P.O. Box 2020, Bldg 410 Mechanicsburg, PA 17055-0788 Code ZIBB1

Or via email attachment to:

Amy.Puchalsky@dla.mil

Requirements and Criteria for Technical Proposals:

Format

To maximize efficiency and minimize the proposal evaluation process, each offeror shall submit its technical proposal in accordance with the format provided below. Each offeror shall submit only one technical proposal in response to this solicitation, subject to the following requirements and limitations:

• Title Page: "Unpriced Technical Proposal" The title page of the technical proposal shall include: (1) the solicitation number (SPRMM118RHB78); (2) the company name and CAGE Code of the offeror; (3) the offeror shall identify those portions of its technical proposal that contain copyrighted or proprietary or similar proposal data; (4) date of submittal.

• A table of contents.

PAGE 52B OF 53

• Contents of technical proposal shall be in accordance with the specified purchase description, and, at a minimum, provide a narrative describing line-by-line how the offeror’s equipment meets the Government’s requirements.

• Product catalog pages, drawings, pictures, etc., may be provided as supporting documentation.

Oral or Written Discussions The Government intends to evaluate proposals and make acceptable/unacceptable determinations without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror’s initial technical proposal should contain the offeror’s best terms from a technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary.

Notice of Unacceptable Technical Proposals When a technical proposal is rated unacceptable either initially, or after clarification/discussions, the DLA Contracting Officer will notify the offeror of the basis of the determination and that a revision of the proposal will not be considered.

Bid Sample Test (BST) BST units (quantity to be determined, HISTORICALLY 2 each) may be required for test purposes.

Contractors will be notified by the PCO whether BST units are required or if BST has been waived by the Naval Research Lab (NRL). BST units shall be provided to NRL within 30 days after notification of acceptance of the submitted technical proposal. Correction to an offeror’s BST units that may be required must be made within (# of days to be specified upon discovery of deficiency). Failure to correct deficiency within the time period specified may result in disqualification from further consideration.

Step Two –

Request for Price Proposals:

I. General

After receiving a notification of acceptable technical proposal and, if necessary, Bid Sample Test, offerors are required to submit a proposal as follows (electronic files acceptable):

Price Proposal. Submit the completed and signed solicitation document to include the completed Section B Pricing Spreadsheet found on page 2B of the solicitation. Offerors must respond to all requirements of the solicitation document. Offerors are cautioned not to alter or disassemble the solicitation.

PAGE 52C OF 53

SECTION M – EVALUATION FACTORS FOR AWARD

NAVSUPWSSMA02 – EVALUATION FOR AWARD (Lowest Price Technically Acceptable)

This is a two-step solicitation. The first step is a request for technical proposals/bid samples and, upon acceptance of the submitted technical proposal/bid samples, the second step is a request for price proposals.

The Government intends to make an award to the eligible, responsible, lowest priced technically acceptable offeror. A technically acceptable offer is one that complies with the requirements of the solicitation and does not take exception, nor object, to any of the terms of the solicitation. Offers that are not technically acceptable will not be considered for award. The offeror’s proposal shall be in the form prescribed by, and shall contain a response to each of the areas identified in the Section L Solicitation Provision entitled "Submission of Proposals."

Evaluation Criteria

(1) Technical Proposal. The Naval Research Laboratory will perform the evaluation of technical proposals. Acceptability of each technical proposal will be based upon compliance with the requirements of the preceding notes concerning content of the technical proposal, and, at a minimum, information satisfying the elements in each paragraph of the Purchase Description, clearly demonstrating that the offeror understands the scope and nature of the RFP and Purchase Description requirements.

Evaluation of technical proposals will be conducted on an acceptable/unacceptable basis.

(2) Price. Price will be evaluated using proposed step ladder pricing. Based on historical purchase quantities and expected future demand, the RFP will specify 4 stepladder quantity price points for each item with five yearly ordering periods. For evaluation purposes: one delivery order for a quantity at the midpoint of each quantity interval for each year will be considered.

See associated Pricing Evaluation Matrix (Attachment #2) for the price evaluation methodology.

21 Sept. 2018

NRL 5524

PURCHASE DESCRIPTION

SOUND LEVEL METER 130 DB

SCAT: 4737

Solicitation No: SPRMM118RHB78

1.0 GENERAL This procurement requires a Sound Level Meter to measure decibel noise levels.

2.0 CLASSIFICATION The equipment shall meet the Class 2 performance requirements of MIL-PRF-28800 for Navy shipboard, submarine, and shore applications.

3.0 OPERATIONAL REQUIREMENTS The specifications provided below are the minimum requirements and accuracies that will meet the Government's need. The meter shall at least meet these requirements and accuracies and may provide better performance.

3.1 Sound Level Range 40 to 130 dB minimum

3.2 Sound level accuracy +/-1.5 dB

3.3 Frequency range 31.5 Hz to 8 kHz

3.4 Weighting A and C

3.5 Output >0.65 Vrms behind 600 Ω with meter at full scale; will drive oscilloscope or low impedance headphones

3.6 Display Full scale sound level range set by level range control, 10 dB portion of scale for sound level comparisons on 2 ranges, and low end of sound level range set by level range control or auto range capability.

4.0 GENERAL REQUIREMENTS

4.1 Power Source MIL-PRF-28800 nominal power source requirements are invoked.

The equipment shall be battery operated to maintain portability. Operating time on battery power shall be at least 50 hours.

4.2 Battery Restrictions Per MIL-PRF-28800F, Lithium and Mercury batteries are prohibited without prior authorization. If equipment qualifies for one or both of the exceptions stated below, then the offeror shall submit the required information at the time of submission of proposals. If equipment does not qualify for an exception, then a request for approval for the use of Lithium and Mercury batteries shall be submitted with production lot delivery, after contract award. Approval shall apply only to the specific model proposed.

Exception 1: Per NAVSEA S9310-AQ-SAF-010, the use of non-rechargeable lithium coin cell batteries meeting the following criteria is approved for all uses and

ATTACHMENT 2

does not require individual testing and review by the Naval Ordnance Safety and Security Activity (NOSSA).

- Unmodified, commercially available off-the-shelf (COTS) item;

- Used in single-cell configuration;

- Maximum nominal output of 3 Volts;

- Maximum rated capacity of 1 Ah.

The coin cell manufacturer, part number, nominal voltage, and rated capacity shall be provided at the time of submission of proposals.

Exception 2: Per NAVSEA S9310-AQ-SAF-010, the use of COTS electronics and equipment powered by lithium ion rechargeable (secondary) batteries meeting the following criteria is approved for all uses and does not require individual testing and review by NOSSA.

- Unmodified, COTS battery;

- Underwriters Laboratories (UL) listed;

- Used in the device as recommended by the manufacturer. Modifications to the devices may only be made in accordance with the manufacturer’s recommendations; e.g., addition of memory;

- Recharged only by devices expressly designed for recharge of the specific battery in use;

- No more than four cells in series (less than or equal to 18-Volt output);

- Rated for no more than 100 Watt-hours, as listed in the manufacturer’s specification or calculated by multiplying the capacity in Ah by the maximum working (nominal performance) voltage.

The lithium ion rechargeable cell manufacturer, part number, configuration (number of cells in series), nominal voltage and rated capacity shall be provided at the time of submission of proposals.

4.3 Environmental

4.3.1 Operating temperature: 0°C to +50°C

4.3.2 Storage temperature: -40°C to +60°C, with batteries removed.

4.3.3 Operating Humidity: 5% to 95% RH.

4.4 Weight 0.48 kg (13 oz.) excluding accessories

4.5 Dimensions 27.9 cm H x 9.2 cm W x 5.3 cm D (11” x 3.63” x 2.09”) nominal

4.6 Accessories The equipment shall be delivered with a carrying case as described in section 4.7.

4.7 Enclosure An enclosure provides protection for the contained system components during storage, handling, and use. If the equipment is provided within an integrated transit case capable of housing all provided accessories, a secondary transit case is not specified. If the instrument enclosure does not provide accommodations for the provided accessories, then a transit case shall be provided to house the instrument, hard-copy operating instructions, power cord/adapter, and all provided accessories

4.8 Technical Manual Equipment categorized as “Repairable” .The maintenance philosophy for this unit shall be up to level 2 only (per MIL-PRF-28800F) and shall require maintenance fault isolation to the module level of the unit. The technical manual shall provide necessary guidance to perform level 2 maintenance. A Use and Installation manual (Operator’s Manual, level 1) shall be provided separately.

Information required for performance verification shall include:

• Instructions to verify equipment performance,

• List the equipment required for verification tests,

• Step-by-step instructions for test connections,

• Acceptable result criteria,

• Calibration information,

• Self-test routines.

Maintenance information shall include:

• Parts lists to the component level,

• Schematics and component layout drawings,

• Block and schematic diagrams.

• List of required test equipment and connection diagrams, and

• Sequential instructions for disassembly, repair, replacement, and reassembly shall be provided.

• Board level maintenance and troubleshooting information,

• Step-by-step instructions for troubleshooting and fault isolation,

• Expected signal levels,

• Test data sheets will be included, and as required,

• The instructions will define localizing a defective circuit card.

Parts lists shall include:

• Parts lists shall be shown on illustrations or a separate listing that includes an index or reference to other illustrations.

• Part number, cage code, and generic description.

The technical manual shall be provided in both printed and electronic formats. The printed format shall be otherwise normally provided. The electronic format shall be in Portable Document Format (PDF) - ISO 32000-1:2008. Two separate PDFs are required when applicable, one shall contain the Use and Installation manual and one shall contain the Maintenance and Service manual.

The statement of copyright release:

“REPRODUCTION AND DISTRIBUTION OF THIS TECHNICAL MANUAL IS

AUTHORIZED FOR U.S. GOVERNMENT PURPOSES.”

shall be printed in the first two pages of each technical manual and on the surface of the CD/DVD supplied.

4.9 Training Materials The equipment will be provided with basic operation and maintenance training, provided on non-volatile electronic medium at a minimum (CD, or DVD), and shall be accessible using freeware such as Adobe Reader® or similar. Flash drives (volatile memory medium) shall not be included with the equipment.

4.10 Calibration The calibration interval shall be 12 months minimum. The equipment shall be within all accuracy requirements specified herein, with an 85% or greater confidence factor following its full calibration interval.

4.10.1 Source Codes: Any electronic or software codes necessary to communicate with, modify internal operating parameters, or impose calibration correction factors on any proposed instrument model shall be provided to the Government at no additional cost.

4.10.2 Documentation: An acceptable calibration certificate showing traceability to NIST shall be provided. A calibration label shall be affixed to the equipment.

4.11 Additional Requirements

4.11.1 Human Readable Identification Labeling:

4.11.1.1 Equipment: Per MIL-PRF-28800F, a human readable label shall be provided for all production lot units conforming with MIL-STD-130N and permanently affixed on the equipment in an easily readable location. Required fields on the label are; CAGE, part number, and serial number. Size of the label shall conform to the size of the equipment.

4.11.1.2 Transit Case: Per MIL-PRF-28800F a human readable metal plate shall be provided for all production lot units conforming with MIL-STD-130N and permanently affixed to the front of the transit case. Required fields on the label are;

CAGE, part number, and serial number. Size of the label shall conform to the size of the case. Pressure sensitive adhesive transfer tape is required to hold the plate to the hard transit case such as 3MTM 9472LE. Soft transit cases also require labeling with permanent placement such as a metal plate affixed with rivets, screws or adhesives.

4.11.2 Shipping container: For production lot units the package or carton containing the equipment for shipment shall be marked per MIL-STD-129P.

4.11.3 Other Additional Requirements: Shall be specified in the CDRL of the solicitation.

SPRMM1-18-R-HB78 Pricing Evaluation Matrix Attachment #3

CLIN QTY

OFFEROR PROPOSES THE FOLLOWING FOR CLIN 0001:

0001 (1-10)

(11-20) QTY BASE YR1 BASE YR 2 BASE YR 3 OPT YR 1 OPT YR 2

(21-30) (1-10) $100 $101 $102 $103 $104

31+ (11-20) $99 $100 $101 $102 $103 (21-30) $98 $99 $100 $101 $102 (31+) $97 $98 $99 $100 $101

THE OFFER FOR CLIN 0001 WOULD BE EVALUATED AS FOLLOWS:

QTY TOTAL

(1-10) $100 x 5 x 1 = $500

(11-20) $99 x 15 x 1 = $1,485 (21-30) $98 x 25 x 1 = $2,450

31+ $97 x 35 x 1 = $3,395

QTY

(1-10) $101 x 5 x 1 = $505

(11-20) $100 x 15 x 1 = $1,500 (21-30) $99 x 25 x 1 = $2,475 (31+) $98 x 35 x 1 = $3,430

QTY

(1-10) $101 x 5 x 1 = $505

(11-20) $100 x 15 x 1 = $1,500 (21-30) $99 x 25 x 1 = $2,475 (31+) $98 x 35 x 1 = $3,430

QTY

(1-10) $103 x 5 x 1 = $515

(11-20) $102 x 15 x 1 = $1,530 (21-30) $101 x 25 x 1 = $2,525

31+ $100 x 35 x 1 = $3,500

QTY

(1-10) $104 x 5 x 1 = $520

(11-20) $103 x 15 x 1 = $1,545 (21-30) $102 x 25 x 1 = $2,550

31+ $101 x 35 x 1 = $3,535

EVALUATED TOTAL = $39,870

OPT YR 1

OPT YR 2

OPT YR 3

OPT YR 4

EXAMPLE:

BASE YR 1

HUMAN READABLE IDENTIFICATION PLATE. Per MIL-PRF 28800F, the equipment human readable identification plate shall be permanently affixed at two places, (1) the equipment, (2) on the transit case (Placement of labels will be discussed at Post Award Meeting). The human readable identification plate shall be marked per example below.

SIZE OF THE LABEL WILL CONFORM TO THE SIZE OF THE EQUIPMENT.

MIL-STD-130N (WITH FREE STYLE TEXT) Construct II instructions can be found in MIL-STD-130

Nomenclature: Cage, Part Number (P/N) & Serial Number (S/N) National Stock Number: Data Identifiers:

Manufacturer Name and/or Cage: 17V; 1P; S Part or Model Number:

Serial Number: 17V is Enterprise Identifier Contract Number: 1P is Part or Model number SCAT/TAMCN: S Serial Number

(IF SPACE IS AN ISSUE, WARRANTY INFO CAN BE ADDED TO THE ABOVE LABEL)

(ADDITIONALLY, METAL PLATES ARE REQUIRED FOR BOTH HARD AND SOFT

TRANSIT CASES)

Pressure Sensitive Adhesive Transfer Tape IS REQUIRED TO HOLD PLATE TO THE HARD TRANSIT CASE (Pelican type cases )such as 3M™ 9472LE . Soft cases also require a permanent placement such as rivets, screws or adhesive.

SHIPMENT PACKAGE MARKING. Package containing the equipment for shipment shall be marked per example below:

MIL-STD-129P (WITH FREE STYLE TEXT)

17JUL17 REV D

Cage: 02059

PN:102770-351

Ser: 6694

NSN 7025011415888

SCAT/TAMCN:

CONT: N00104-98-T-0023

REQ#: M95450-0111-1111

Nomenclature: Magnetic Tape

U/I: EA

QTY: 1

ATTACHMENT 4

ADP38B8.tmp
Eval

File details come from the government source that posted it.