CONTRACT DATA REQUIREMENTS LIST

Form Approval OMB No. 0704-0188 Public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.: 9000

B. EXHIBIT: A

C. CATEGORY:

TDP _X__ TM ____ OTHER ___

D. SYSTEM/ITEM: PISTON ASSY, VARIABLE RECOIL MECHANISM, NSN: 1025-00-802-2463

E. CONTRACT/PR NO.: TBD

F. CONTRACTOR: TBD

1. DATA ITEM NO.: A001

2. TITLE OF DATA ITEM: TEST PROCEDURE – HEAVY PHOSPHATE COATING

3. SUBTITLE: PRE-PRODUCTION PROCEDURE

4. AUTHORITY: DI-NDTI-80603A

5. CONTRACT REFERENCE: Section C.5, C.6, and paragraph 3.1 of MIL-DTL-16232G

6. REQUIRING OFFICE: RDAR-MEE-W(R)

7. DD250 REQ: Not Required

8. APP CODE: A

9. DIST. STATEMENT: D

10. FREQUENCY: ONE/R

11. AS OF DATE: Date of Contract award

12. DATE OF FIRST SUB: 60DAC

13. DATE OF SUBS: N/A

14. DISTRIBUTION:

A. ADDRESSEE: Jeff Mahlmeister, Contracting Officer, jeffrey.mahlmeister@dla.mil and Jacob Silcox, Contract Specialist, Jacob.silcox@dla.mil

B. COPIES: 2

DRAFT:

FINAL: 2

15. TOTAL: 2

16. REMARKS:

BLOCK 8 CONT. - PRIOR TO PRODUCTION, APPROVAL THRU THE CONTRACTING OFFICER IS REQUIRED W/IN 60 DAYS AFTER CONTRACT AWARD. CONTRACTING OFFICER WILL ROUTE INTERNALLY TO THE APPROVING OFFICE (RDAR-MEE-W(R)). CONTRACTING OFFICER SHALL PROVIDE PROCEDURE REVIEW RESPONSE BACK TO CONTRACTOR. COATED PANELS PER PARA 3.2.2 SHALL INCLUDE THREE WITH PHOSPHATE ONLY, THREE WITH PHOSPHATE AND PRIMER, AND THREE WITH PHOSPHATE, PRIMER AND TOP COAT.

The contract number must be cited on all phosphate coating procedures submitted for review and approval. Procedures shall include product name and manufacturer of all chemicals/materials to be used. All processes, equipment, controls along with testing and test frequencies used for phosphating including application of supplemental finishes shall be described in detail.