Specs W9128F21Q0084 Concrete Paving Cold Brook.pdf
PDF 732 KB Posted
- Attached to
- Cold Brook Concrete Paving Federal contract opportunity
- Solicitation number
- W9128F21Q0084
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W9128F21Q0084_Amd0001.pdf | ||
| Am0001 Advertise Drawing Set.pdf | ||
| 01 11 00 Summary of Work.pdf | ||
| W9128F21Q0084 - Solicitation.pdf | ||
| CB Concrete Paving Advertisement Set_July 2021 - final.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATIONS
(Purchase Order - For Construction Contract)
Solicitation Number W9128F21Q0084
Concrete Paving EM/Rec Access Cold Brook Dam, SD
August 2021
US Army Corps of Engineers Omaha District
This page was intentionally left blank for duplex printing.
CONCRETE PAVING EM/REC ACCESS
COLD BROOK DAM, SD
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 10 00-3 BIDDING SCHEDULE
00 73 00 SUPPLEMENTARY CONDITIONS (SPECIAL CONTRACT
REQUIREMENTS)FOR PURCHASE ORDERS
DIVISION 01 - GENERAL REQUIREMENTS
01 33 00 SUBMITTAL PROCEDURES
01 41 26.01 24 (SOUTH DAKOTA) NPDES PERMIT REQUIREMENTS FOR STORM WATER
DISCHARGES FROM CONSTRUCTION SITES
01 57 20.00 10 ENVIRONMENTAL PROTECTION
01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 05 19 GEOTEXTILE
31 11 00 CLEARING AND GRUBBING
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 10 00.01 (SOUTH DAKOTA) PAVEMENTS FOR SMALL PROJECTS
DIVISION 33 - UTILITIES
33 40 00 STORM DRAINAGE UTILITIES
-- End of Project Table of Contents --
00 10 00 Page 3
BASE AREA
BIDDING SCHEDULE
ITEM
NO. DESCRIPTION QUANTITY UNIT AMOUNT
BASIC ITEMS
Entire work, complete to supply and install
Concrete Pavement, Dowels, Traffic Control, Joint Saw Cutting Grading, Tubular Delineators Expansion Joint.
JOB
Entire work, to supply and install Geotextile, Type B Rip Rap, Epoxy Rebar, and Concrete Slope.
All other work, including, but not limited to tree removal, bank preparation, site restoration/seeding, mobilization, and demobilization. This excludes all other Basic Item entire work.
TOTAL AMOUNT $
Concrete Paving EM/REC Access, Cold Brook Dam, Hot Springs, SD CB06
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 73 01
SUPPLEMENTARY CONDITIONS (SPECIAL CONTRACT REQUIREMENTS)FOR PURCHASE ORDERS
2/19
PART 1 GENERAL
1.1 SCOPE
1.2 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK.
1.3 CONTRACT DRAWING AND SPECIFICATIONS
1.4 CONTRACTOR QUALITY CONTROL (CQC).
1.4.1 Responsibility of the Contractor
1.5 GUARANTEE
1.6 ACCIDENT PREVENTION
1.7 PROTECTION OF EXISTING FACILITIES AND WORKS
1.8 CONTRACT DRAWINGS AND SPECIFICATIONS
1.8.1 NOTIFICATION OF DISCREPANCIES
1.8.2 OMISSIONS
1.9 PAYMENT
1.9.1 PROMPT PAYMENT ACT
1.9.2 PAYMENTS FOR MODIFICATIONS
1.10 AVAILABILITY OF UTILITY SERVICES
1.11 PROFIT
1.12 AS-BUILT DRAWINGS
1.13 PORTABLE TOILETS
1.14 FEDERAL HOLIDAYS AND WORKING HOURS
1.15 ANTITERRORISM (AT)/OPERATIONS SECURITY (OPSEC) PROVISIONS
PART 2 NOT USED
PART 3 NOT USED
-- End of Section Table of Contents --
DOCUMENT 00 73 00 Page 1
SECTION 00 73 01
SUPPLEMENTARY CONDITIONS (SPECIAL CONTRACT REQUIREMENTS)FOR PURCHASE ORDERS
2/19
PART 1 GENERAL
1.1 SCOPE
See Section 01 11 00 Summary of Work.
1.2 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK.
The Contractor shall commence work under this contract within ten (10) calendar days after the date of receipt by him of Notice to Proceed, prosecute said work diligently, and complete the entire work except seeding ready for use not later than 90 calendar days after receipt of Notice to Proceed. The time stated for completion shall include final cleanup of the premises. (FAR 52.211-10)
1.3 CONTRACT DRAWING AND SPECIFICATIONS
The Contractor shall be responsible for making his own copies of specifications, drawings and any amendments, as needed for the duration of the project, from the electronic files provided.
1.4 CONTRACTOR QUALITY CONTROL (CQC).
1.4.1 Responsibility of the Contractor
Except for isolated tests or other items of work specified to be performed by the Government, the quality of all work shall be the responsibility of the Contractor. Sufficient inspections and tests of all items of work, including that of subcontractors, to ensure conformance to applicable specifications and drawings with respect to the quality of materials, workmanship, construction, finish, functional performance, and identification shall be performed on a continuing basis.
1.5 GUARANTEE
The equipment and supplies to be furnished under this contract shall be guaranteed for a period of one (1) year from the date of acceptance thereof, either for beneficial use or final acceptance, whichever is earlier, against defective materials, design, and workmanship. Upon receipt of notice from the Government of failure of any of the guaranteed equipment during the guarantee period, new replacement parts shall be furnished and installed promptly by the Contractor at no additional cost to the Government. The Contractor shall also obtain and deliver to the Contracting Officer any warranties of equipment or supplies which the subcontractors, manufacturers, or suppliers would give normal commercial practice.
1.6 ACCIDENT PREVENTION
In accordance with EM 385-1-1, Safety and Health Requirements Manual, the
DOCUMENT 00 73 00 Page 2
Contractor shall provide for protecting of the lives and health of employees and other persons; preventing of damage to property; and avoiding work interruptions.
1.7 PROTECTION OF EXISTING FACILITIES AND WORKS
The Contractor shall be responsible for the protection of work area from damage and upon completion of the work shall leave existing works in a condition equal to that which existed when the work started.
1.8 CONTRACT DRAWINGS AND SPECIFICATIONS
1.8.1 NOTIFICATION OF DISCREPANCIES
The Contractor shall check all drawings furnished him immediately upon their receipt and shall promptly notify the Contracting Officer of any discrepancies. Dimensions marked on drawings shall be followed in lieu of scale measurements. Enlarged plans and details shall govern where the same work is shown at smaller scales. The Contractor shall compare all drawings and verify the figures before laying out the work and will be responsible for any errors which might have been avoided thereby.
1.8.2 OMISSIONS
Omissions from the drawings or specifications or the misdescription of details of work which are manifestly necessary to carry out the intent of the drawings and specifications, or which are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work but they shall be performed as if fully and correctly set forth and described in the drawings and specifications.
1.9 PAYMENT
1.9.1 PROMPT PAYMENT ACT
Pay requests authorized in CONTRACT CLAUSES clause: "Payments Under Fixed Price Construction Contracts", will be paid pursuant to the clause, "Prompt Payment for Construction Contracts". Pay requests will be submitted on ENG Form 93 and 93a, "Payment Estimate Contract Performance" and "Continuation". All information and substantiation required by the identified contract clauses will be submitted with the ENG Form 93, and the required certification will be included on the last page of the ENG Form 93a, signed by an authorized contractor official and dated when signed.
The designated billing office is the Office of the Area Engineer.
1.9.2 PAYMENTS FOR MODIFICATIONS
Payments may be made for cost bearing change orders within the scope of the contract only to the extent funds are authorized in the order on a two part modification. Contractor pricing proposed must be submitted at the earliest possible time after the change order is issued, or at a specific time as directed by the Contracting Officer. At the discretion of the Contracting Officer, any and all payments may be withheld on the modification until the Contractor has submitted a qualifying price proposal, in as much detail as required by the Contracting Officer, and the final price has been agreed.
DOCUMENT 00 73 00 Page 3
1.10 AVAILABILITY OF UTILITY SERVICES
Use of public and private utilities will be as found available. The Contractor shall make his own arrangements for use of public and private utilities.
1.11 PROFIT
a. Weighted guidelines method of determining profit shall be used on any equitable adjustment change order or modification issued under this contract. The profit factors shall be as follows:
Factor Rate Weight Value Degree of Risk 20 See Item Relative difficulty of work 15 b. below Size of Job 15 Period of performance 15 Contractor's investment 5 Assistance by Government 5 Subcontracting 25
b. Based on the circumstances of each procurement action, each of the above factors shall be weighted from .03 to .12 as indicated below. The value shall be obtained by multiplying the rate by the weight. The value column when totaled indicates the fair and reasonable profit percentage under the circumstances of the particular procurement.
(1) Degree of Risk. Where the work involves no risk or the degree of risk is very small, the weighting should be .03; as the degree of risk increases, the weighting should be increased up to a maximum of .12. Lump sum items will have, generally, a higher weighted value than the unit price items for which quantities are provided. Other things to consider: the portion of the work to be done by subcontractors, nature of work, where work is to be performed, reasonableness of negotiated costs, amount of labor included in costs, and whether the negotiation is before or after performance of work.
(2) Relative Difficulty of Work. If the work is most difficult and complex, the weighting should be .12 and should be proportionately reduced to .03 on the simplest of jobs. This factor is tied in to some extent with the degree of risk. Some things to consider: the nature of the work, by whom it is to be done, where, and what is the time schedule.
(3) Size of Job. All work not in excess of $100,000 shall be weighted at .12. Work estimated between $100,000 and $5,000,000 shall be proportionately weighted from .12 to .05.
(4) Periods of Performance. Jobs in excess of 24 months are to be weighted at .12. Jobs of lesser duration are to be proportionately weighted to a minimum of .03 for jobs not to exceed 30 days. No weight where additional time not required.
(5) Contractor's Investment. To be weighted from .03 to .12 on the basis of below average, average, and above average. Things to consider: amount of subcontracting, mobilization payment item, Government furnished property, equipment and facilities, and expediting assistance.
(6) Assistance by Government. To be weighted from .12 to .03 on
DOCUMENT 00 73 00 Page 4 the basis of average to above average. Things to consider: use of Government-owned property, equipment and facilities, and expediting assistance.
(7) Subcontracting. To be weighted inversely proportional to the amount of subcontracting. Where 80 percent or more of the work is to be subcontracted, the weighting is to be .03 and such weighting proportionately increased to .12 where all the work is performed by the Contractor's own forces.
1.12 AS-BUILT DRAWINGS
The Contractor shall provide a marked-up half size drawing to show actual work performed to include necessary sketches, modification drawings, shop drawings and notes. Red ink is to be used for additions and deviations from the contract. Green ink is to be used to indicate work deleted from the contract. The drawings shall be maintained by the contractor as the work progresses and available for review by the government representatives. The as-built drawings shall be submitted for approval at the completion of the project. The completed set shall be available at time of final inspection.
1.13 PORTABLE TOILETS
Toilet facilities will not be available for Contractor's use. The Contractor shall provide and maintain portable toilets for use by the Contractor's staff . Toilet(s) shall be placed at the location directed by the Contracting Officer. To prevent overturning by high winds, all portable toilets shall be anchored down.
1.14 FEDERAL HOLIDAYS AND WORKING HOURS
Work hours: The Contractor can work Monday through Friday 0700 to 1700.
Working outside these work hours will need written permission from the COR.
The Contractor will not be allowed to work on Federal holidays or observance days.
The following Federal legal holidays are observed by this installation:
New Year's Day 1 January Martin Luther King's Birthday Third Monday in January President's Day Third Monday in February Memorial Day Last Monday in May Juneteenth 19 June Independence Day 4 July Labor Day First Monday in September Columbus Day Second Monday in October Veterans Day 11 November Thanksgiving Day Fourth Thursday in November Christmas Day 25 December
If a wage determination applies the number of holidays specified on it, it has priority over this requirement.
1.15 ANTITERRORISM (AT)/OPERATIONS SECURITY (OPSEC) PROVISIONS
1. Not Used
2. Access and General Protection/Security Policy and Procedures
DOCUMENT 00 73 00 Page 5
All Contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The Contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in Contractor security matters or processes.
3. thru 14 Not Used.
15. Pre-Screen Candidates using E-Verify Program The Contractor must pre-screen Candidates using the E-verify Program (http://www.dhs.gov/E-Verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.
PART 2 NOT USED
PART 3 NOT USED
-- End of Section --
DOCUMENT 00 73 00 Page 6
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
08/18, OMH 02/2019
PART 1 GENERAL
1.1 SUMMARY
1.1.1 Submittal Information
1.2 SUBMITTALS
1.2.1 Action Codes
1.2.1.1 Contractor Action Codes
1.2.1.2 Government Reviewer Designations
1.3 SUBMITTAL CLASSIFICATION
1.3.1 Government Approved (G)
1.3.2 For Information Only
1.4 PREPARATION
1.4.1 Transmittal Form
1.4.2 Source Drawings for Shop Drawings
1.4.2.1 Source Drawings
1.4.2.2 Terms and Conditions
1.4.3 Electronic File Format
1.5 QUANTITY OF SUBMITTALS
1.5.1 Number of SD-04 Samples
1.6 INFORMATION ONLY SUBMITTALS
1.7 PROJECT SUBMITTAL REGISTER
1.7.1 Submittal Management
1.7.2 Preconstruction Use of Submittal Register
1.7.3 Contractor Use of Submittal Register
1.7.4 Approving Authority Use of Submittal Register
1.7.5 Action Codes
1.7.6 Delivery of Copies
1.8 VARIATIONS
1.8.1 Considering Variations
1.8.2 Proposing Variations
1.8.3 Warranting that Variations are Compatible
1.8.4 Review Schedule Extension
1.9 SCHEDULING
1.10 GOVERNMENT APPROVING AUTHORITY
1.11 DISAPPROVED SUBMITTALS
1.12 APPROVED SUBMITTALS
1.13 APPROVED SAMPLES
1.14 WITHHOLDING OF PAYMENT
PART 2 PRODUCTS
PART 3 EXECUTION
ATTACHMENTS:
SECTION 01 33 00 Page 1
ENG Form 4025-R
Project Submittal Register
SECTION 01 33 00 Page 2
SECTION 01 33 00
SUBMITTAL PROCEDURES
08/18, OMH 02/2019
PART 1 GENERAL
1.1 SUMMARY
1.1.1 Submittal Information
The Contractor is responsible for total management of their work including, but not limited to, approval, scheduling, control, certification of all submittals and compliance with all applicable Buy-American and Trade Agreement clauses. The submittal management system provided in these specifications is intended to be a complete system for the Contractor to use to control the quality of materials, equipment and workmanship provided by manufacturers, fabricators, suppliers and subcontractors. Review each submittal for contract compliance. Compliance with all applicable Buy American and Trade Agreement Clauses is to be included in this review. The Contractor must provide the country of origin on ENG Form 4025 for each item submitted. The Submittal Register (ENG Form 4288) will be utilized to log and monitor all submittal activities.
The Contracting Officer may request submittals, in addition to those specified, when deemed necessary to adequately describe the work covered in the respective sections. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having any designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with this section.
SD-01 Preconstruction Submittals
Submittal Register; G-PO]
SECTION 01 33 00 Page 3
1.2.1 Action Codes
1.2.1.1 Contractor Action Codes
DESIGN BID BUILD SUBMITTALS
Submittal Classifications shown in UFGS Sections
Submittal Classification
Corresponding SpecsIntact
Submittal Register Code which is populated in the SI Submittal Register.
Software
Limitations: (The software shows one character delineation in the
SpecsIntact Submittal Register)
RMS – The following Submittal
Classifications are populated in RMS when the SpecsIntact
Submittal Data File is pulled into RMS)
G Submittal requires Government Approval
G GA
BLANK Submittal is For Information Only
(FIO)
BLANK FIO
1.2.1.2 Government Reviewer Designations
Following the Submittal Classification designation "G", the following reviewer designations may be included:
RO - Resident Office AO - Area Office DO - District Office
Additional information will be provided at the pre-design and/or pre-construction conference.
Corps of Engineers, Omaha District Office for "DO" reviewer designations, submittals will be coordinated through:
Michael Hebert U.S. Army Corps of Engineers Omaha District Attn: CENWO-CDS-T 1616 Capitol Ave Omaha, NE 68102-4901 E-mail: CENWO.ConstructionSubmittal@usace.army.mil
SECTION 01 33 00 Page 4
1.3 SUBMITTAL CLASSIFICATION
1.3.1 Government Approved (G)
Government approval is required for extensions of design, critical materials, variations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Government.
Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, submittals are considered to be "shop drawings."
1.3.2 For Information Only
Submittals not requiring Government approval will be for information only. Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are not considered to be "shop drawings."
1.4 PREPARATION
1.4.1 Transmittal Form
Use the ENG Form 4025-R transmittal form for submitting both Government-approved and information-only submittals. Submit in accordance with the instructions on the reverse side of the form. These forms will be furnished to the Contractor. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. If there are multiple Item numbers listed on a particular ENG Form 4025-R submittal, combine all submitted items for review into a single Adobe file with bookmarks (for ease of review). Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.
1.4.2 Source Drawings for Shop Drawings
1.4.2.1 Source Drawings
The entire set of source drawing files (DWG or DGN) will not be provided to the Contractor. Request the specific Drawing Number for the preparation of shop drawings. Only those drawings requested to prepare shop drawings will be provided. These drawings are provided only after award.
1.4.2.2 Terms and Conditions
Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse is at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor must make no claim, and waives to the fullest extent permitted by law any claim or cause of action of any nature against the Government, its agents, or its subconsultants that may arise out of or in connection with the use of these electronic files. The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities, or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
These electronic source drawing files are not construction documents.
Differences may exist between the source drawing files and the corresponding construction documents. The Government makes no
SECTION 01 33 00 Page 5 representation regarding the accuracy or completeness of the electronic source drawing files, nor does it make representation to the compatibility of these files with the Contractor hardware or software. The Contractor is responsible for determining if any conflict exists. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished source drawing files, the signed and sealed construction documents govern. Use of these source drawing files does not relieve the Contractor of the duty to fully comply with the contract documents, including and without limitation the need to check, confirm and coordinate the work of all contractors for the project.
If the Contractor uses, duplicates or modifies these electronic source drawing files for use in producing construction data related to this contract, remove all previous indication of ownership (seals, logos, signatures, initials and dates).
1.4.3 Electronic File Format
Provide submittals in electronic format, with the exception of material samples required for SD-04 Samples items. Compile the submittal file as a single, complete document, to include the Transmittal Form described within. Name the electronic submittal file specifically according to its contents, and coordinate the file naming convention with the Contracting Officer. Electronic files must be of sufficient quality that all information is legible. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer. All documents must make use of optical character recognition (OCR) routines to make text searchable and selectable, so that the text can be copied. Index and bookmark files exceeding 30 pages to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature.
E-mail electronic submittal documents smaller than 10MB to an e-mail address as directed by the Contracting Officer, unless directed otherwise by COR. Provide electronic documents over 10 MB on an optical disc or through an electronic file sharing system, such as secure ftp site or Government web application located at the following website:
https://safe.arl.army.mil/. Use of the Government web application must be initiated by the Government, unless Contractor has a Government CAC card.
The Government may allow the AMRDEC SAFE Web Application located at the following website: https://safe.amrdec.army.mil/safe/. Both Government web applications restrict the number of days files are available to download.
1.5 QUANTITY OF SUBMITTALS
Submittals are to be transmitted electronically, unless directed otherwise.
1.5.1 Number of SD-04 Samples
a. Submit two samples, or two sets of samples showing the range of variation, of each required item. One approved sample or set of samples will be retained by the approving authority and one will be returned to the Contractor.
b. Submit one sample panel or provide one sample installation where directed. Include components listed in the technical section or as directed.
c. Submit one sample installation, where directed.
d. Submit one sample of nonsolid materials.
SECTION 01 33 00 Page 6
1.6 INFORMATION ONLY SUBMITTALS
Submittals without an action code must be certified by the QC manager and submitted to the Contracting Officer for information-only. Approval of the Contracting Officer is not required on information only submittals. The Contracting Officer will mark "receipt acknowledged" on submittals for information and will return only the transmittal cover sheet to the Contractor. Normally, submittals for information only will not be returned. However, the Government reserves the right to return unsatisfactory submittals and require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work;
and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.
1.7 PROJECT SUBMITTAL REGISTER
A sample Project Submittal Register showing submittals required by the specifications is attached to this section as "Project Submittal Register."
1.7.1 Submittal Management
Prepare and maintain a submittal register, as the work progresses. Do not change data that is output in columns (c), (d), (e), and (f) as delivered by Government; retain data that is output in columns (a), (g), (h), and (i) as approved. As an attachment, provide a submittal register showing items of equipment and materials for which submittals are required by the specifications. This list may not be all-inclusive and additional submittals may be required.
Column (c): Lists specification section in which submittal is required.
Column (d): Lists each submittal description (SD Number. and type, e.g., SD-02 Shop Drawings) required in each specification section.
Column (e): Lists one principal paragraph in each specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting the project requirements.
Thereafter, the Contractor is to track all submittals by maintaining a complete list, including completion of all data columns and all dates on which submittals are received by and returned by the Government.
1.7.2 Preconstruction Use of Submittal Register
Submit the submittal register as an electronic database, using the submittal management program furnished to Contractor, unless directed otherwise by COR. Include the QC plan and the project schedule. Verify that all submittals required for the project are listed and add missing
SECTION 01 33 00 Page 7 submittals. Coordinate and complete the following fields on the register database submitted with the QC plan and the project schedule:
Column (a) Activity Number: Activity number from the project schedule.
Column (g) Contractor Submit Date: Scheduled date for the approving authority to receive submittals.
Column (h) Contractor Approval Date: Date that Contractor needs approval of submittal.
Column (i) Contractor Material: Date that Contractor needs material delivered to Contractor control.
1.7.3 Contractor Use of Submittal Register
Update the following fields in the Government-furnished submittal register program or equivalent fields in the program used by the Contractor with each submittal throughout the contract.
Column (b) Transmittal Number: List of consecutive, Contractor-assigned numbers.
Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.
Column (l) Date submittal transmitted.
Column (q) Date approval was received.
1.7.4 Approving Authority Use of Submittal Register
Update the following fields:
Column (b) Transmittal Number: List of consecutive, Contractor-assigned numbers.
Column (l) Date submittal was received.
Column (m) through (p) Dates of review actions.
Column (q) Date of return to Contractor.
1.7.5 Action Codes
See paragraph Action Codes above.
1.7.6 Delivery of Copies
Submit an updated electronic copy of the submittal register to the Contracting Officer with each invoice request, unless a paper copy is requested by the Contracting Officer. Provide an updated Submittal Register monthly regardless of whether an invoice is submitted.
1.8 VARIATIONS
Variations from contract requirements require Contracting Officer approval pursuant to contract Clause FAR 52.236-21 Specifications and Drawings for
SECTION 01 33 00 Page 8
Construction, and will be considered where advantageous to the Government.
1.8.1 Considering Variations
Discussion of variations with the Contracting Officer before submission will help ensure that functional and quality requirements are met and minimize rejections and resubmittals. When contemplating a variation that results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).
Specifically point out variations from contract requirements in transmittal letters. Failure to point out variations may cause the Government to require rejection and removal of such work at no additional cost to the Government.
1.8.2 Proposing Variations
When proposing variations, deliver a written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government. Include the DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item.
Clearly mark the proposed variation in all documentation.
Check the column "variation" of ENG Form 4025 for submittals that include variations proposed by the Contractor. Set forth in writing the reason for any variations and note such variations on the submittal. The Government reserves the right to rescind inadvertent approval of submittals containing unnoted variations.
1.8.3 Warranting that Variations are Compatible
When delivering a variation for approval, the Contractor warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
1.8.4 Review Schedule Extension
In addition to the normal submittal review period, a period of 14 calendar days will be allowed for the Government to consider submittals with variations.
1.9 SCHEDULING
Schedule and submit concurrently product data and shop drawings covering component items forming a system or items that are interrelated. Submit pertinent certifications at the same time. No delay damages or time extensions will be allowed for time lost in late submittals.
Contracting Officer review will be completed within 20 calendar days after the date of submission.
The Government review period for each construction submittal does not begin until the submittal is delivered via RMS CM. Contract compliance for all submittals are the Contractor's responsibility. Government acceptance or receipt acknowledged does not remove this responsibility for contract compliance on any construction submittal.
SECTION 01 33 00 Page 9
1.10 GOVERNMENT APPROVING AUTHORITY
Upon completion of review of submittals requiring Government approval, stamp and date submittals. An electronic copy of the submittal will be retained by the Contracting Officer and an electronic copy of the submittal will be returned to the Contractor. The Government may process submittals in the RMS CM System.
1.11 DISAPPROVED SUBMITTALS
Make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications, give notice to the Contracting Officer as required under the FAR clause titled CHANGES. The Contractor is responsible for the dimensions and design of connection details and the construction of work. Failure to point out variations may cause the Government to require rejection and removal of such work at the Contractor's expense.
If changes are necessary to submittals, make such revisions and resubmit in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
1.12 APPROVED SUBMITTALS
The Contracting Officer's approval of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing, and other information are satisfactory.
Approval or acceptance by the Government for a submittal does not relieve the Contractor of the responsibility for meeting the contract requirements or for any error that may exist, because under the Quality Control (QC) requirements of this contract, the Contractor is responsible for ensuring information contained with in each submittal accurately conforms with the requirements of the contract documents.
After submittals have been approved or accepted by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
1.13 APPROVED SAMPLES
Approval of a sample is only for the characteristics or use named in such approval and is not be construed to change or modify any contract requirements. Before submitting samples, provide assurance that the materials or equipment will be available in quantities required in the project. No change or substitution will be permitted after a sample has been approved.
Match the approved samples for materials and equipment incorporated in the work. If requested, approved samples, including those that may be damaged in testing, will be returned to the Contractor, at its expense, upon completion of the contract. Unapproved samples will also be returned to the Contractor at its expense, if so requested.
Failure of any materials to pass the specified tests will be sufficient cause for refusal to consider, under this contract, any further samples of
SECTION 01 33 00 Page 10 the same brand or make as that material. The Government reserves the right to disapprove any material or equipment that has previously proved unsatisfactory in service.
Samples of various materials or equipment delivered on the site or in place may be taken by the Contracting Officer for testing. Samples failing to meet contract requirements will automatically void previous approvals.
Replace such materials or equipment to meet contract requirements.
1.14 WITHHOLDING OF PAYMENT
Payment for materials incorporated in the work will not be made if required approvals have not been obtained.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 33 00 Page 11
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 2 PAGES
Concrete Paving EM/REC Access, Cold Brook Dam, Hot Springs, SD
01 33 00 SD-01 Preconstruction Submittals
1.7 G PO]Submittal Register
01 41 26.01 24 SD-01 Preconstruction Submittals 3.2.1Notice of Intent
Authorization Letter 3.2.4Storm Water Pollution Prevention
Plan 3.2.7Notice of Termination
SD-06 Test Reports 3.2.5Reports
01 57 20.00 10 SD-01 Preconstruction Submittals
1.7 G OAEnvironmental Protection Plan
01 57 23 SD-07 Certificates 2.1.3Mill Certificate or Affidavit
31 00 00 SD-01 Preconstruction Submittals
3.5 G POShoring
G PODewatering Work Plan SD-07 Certificates
3.16 G POTesting
31 05 19 SD-03 Product Data
2.1.2Thread 2.2Manufacturing Quality Control
Sampling and Testing SD-04 Samples
3.1Quality Assurance Samples and Tests
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 2 PAGES
Concrete Paving EM/REC Access, Cold Brook Dam, Hot Springs, SD
31 05 19 SD-07 Certificates 2.1.1Geotextile
31 11 00 SD-03 Product Data 2.3.2Nonsaleable Materials
GPO
32 10 00.01 SD-03 Product Data
1.10Plant, Equipment, and Tools
2.1.1.2 G POMixture Proportions
SD-06 Test Reports
2.7 G POInitial Tests
3.1.7 G POContractor Quality Control
3.1.8 G POAcceptability of Work
3.3.2 G POAcceptability of Work
SD-07 Certificates
3.1.8.1 G POTesting Laboratory
SD-08 Manufacturer’s Instructions
3.1.6 G POManufacturer's
Recommendations 33 40 00 SD-04 Samples
2.1Pipe for Culverts and Storm Drains
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
ENG FORM 4025, MAY 2017 PREVIOUS EDITIONS ARE OBSOLETE. Page 1 of 2
U.S. Army Corps of Engineers (USACE)
TRANSMITTAL OF SHOP DRAWINGS, EQUIPMENT DATA, MATERIAL SAMPLES, OR
MANUFACTURER'S CERTIFICATES OF COMPLIANCE
For use of this form, see ER 415-1-10; the proponent agency is CECW-CE.
DATE TRANSMITTAL NO.
SECTION I - REQUEST FOR APPROVAL OF THE FOLLOWING ITEMS (This section will be initiated by the contractor)
TO:
PROJECT TITLE AND LOCATIONSPECIFICATION SEC. NO. (Cover only one section with each transmittal)
FROM: CONTRACT NO. CHECK ONE:
THIS TRANSMITTAL IS FOR: (Check one)
THIS IS A NEW TRANSMITTAL
THIS IS A RESUBMITTAL OF
TRANSMITTAL
FIO GA DA CR DA/CR DA/GA
ITEM
NO.
(See
Note 3)
USACE
ACTION
CODE
(Note 9)
SUBMITTAL
TYPE CODE
(See Note 8)
NO.
OF
COPIES
SPEC.
PARA. NO.
DRAWING
SHEET NO.
CONTRACTOR
REVIEW
CODE
VARIATION
Enter "Y" if requesting a variation
(See Note 6)
DESCRIPTION OF SUBMITTAL ITEM
(Type size, model number/etc.)
a. i.c. d. e. f. g. h.b.
CONTRACT DOCUMENT
REFERENCE
REMARKS
SECTION II - APPROVAL ACTION
I certify that the above submitted items had been reviewed in detail and are correct and in strict conformance with the contract drawings and specifications except as otherwise stated.
NAME OF CONTRACTOR SIGNATURE OF CONTRACTOR
NAME AND TITLE OF APPROVING AUTHORITY SIGNATURE OF APPROVING AUTHORITY DATEENCLOSURES RETURNED (List by item No.)
ENG FORM 4025, MAY 2017 Page 2 of 2
INSTRUCTIONS
1. Section I will be initiated by the Contractor in the required number of copies.
2. Each Transmittal shall be numbered consecutively. The Transmittal Number typically includes two parts separated by a dash (-). The first part is the specification section number. The second part is a sequential number for the submittals under that spec section. If the Transmittal is a resubmittal, then add a decimal point to the end of the original Transmittal Number and begin numbering the resubmittal packages sequentially after the decimal.
3. The "Item No." for each entry on this form will be the same "Item No." as indicated on ENG FORM 4288-R.
4. Submittals requiring expeditious handling will be submitted on a separate ENG Form 4025-R.
5. Items transmitted on each transmittal form will be from the same specification section. Do not combine submittal information from different specification sections in a single transmittal.
6. If the data submitted are intentionally in variance with the contract requirements, indicate a variation in column h, and enter a statement in the Remarks block describing he detailed reason for the variation.
7. ENG Form 4025-R is self-transmitting - a letter of transmittal is not required.
8. When submittal items are transmitted, indicate the "Submittal Type" (SD-01 through SD-11) in column c of Section I.
Submittal types are the following:
SD-01 - Preconstruction SD-02 - Shop Drawings SD-03 - Product Data SD-04 - Samples SD-05 - Design Data SD-06 - Test Reports
SD-07 - Certificates SD-08 - Manufacturer's Instructions SD-09 - Manufacturer's Field Reports SD-10 - O&M Data SD-11 - Closeout
9. For each submittal item, the Contractor will assign Submittal Action Codes in column g of Section I. The U.S. Army Corps of Engineers approving authority will assign Submittal
Action Codes in column i of Section I. The Submittal Action Codes are:
A -- Approved as submitted.
B -- Approved, except as noted on drawings. Resubmission not required.
C -- Approved, except as noted on drawings. Refer to attached comments.
Resubmission required.
D -- Will be returned by separate correspondence.
E -- Disapproved. Refer to attached comments.
10. Approval of items does not relieve the contractor from complying with all the requirements of the contract.
F -- Receipt acknowledged.
X -- Receipt acknowledged, does not comply with contract requirements, as noted.
G -- Other action required (Specify)
K -- Government concurs with intermediate design. (For D-B contracts)
R -- Design submittal is acceptable for release for construction. (For D-B contracts)
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 41 26.01 24
(SOUTH DAKOTA) NPDES PERMIT REQUIREMENTS FOR STORM WATER DISCHARGES FROM
CONSTRUCTION SITES
08/21
PART 1 GENERAL
1.1 REFERENCES (Not Applicable)
1.2 SUBMITTALS
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 GENERAL
3.2 IMPLEMENTATION
3.2.1 Notice of Intent
3.2.2 Authorization Letter
3.2.3 Posting NOI and Authorization Letter
3.2.4 Storm Water Pollution Prevention Plan
3.2.5 Inspections and Reporting
3.2.6 Retention of Records
3.2.7 Notice of Termination
3.2.8 Renotification
SECTION 01 41 26.01 24 Page 1
SECTION 01 41 26.01 24
(SOUTH DAKOTA) NPDES PERMIT REQUIREMENTS
FOR STORM WATER DISCHARGES
FROM CONSTRUCTION SITES
08/21
PART 1 GENERAL
"General Permit For Storm Water Discharges Associated With Construction Activities", Permit No. SDR10#### can be found at the following website:
http://denr.sd.gov/des/sw/StormWaterandConstruction.aspx
NOTE: If the Contractor has less than one acre of ground disturbance including the staging area, then no NPDES permit will be required.
1.1 REFERENCES (Not Applicable)
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having an "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittal
Notice of Intent.
Authorization Letter.
Storm Water Pollution Prevention Plan.
Notice of Termination.
SD-06 Test Reports
Reports.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 GENERAL
The Contractor shall be responsible for implementing the terms and requirements of the attached "General Permit For Storm Water Discharges Associated With Construction Activities", Permit No. SDR10####, for storm water discharges from construction sites. The Contractor shall be considered the "permittee". All submissions to the state shall be by certified mail. Copies of the return receipt for each submission shall be included with the submittal to the Contracting Officer's Representative
(COR).
SECTION 01 41 26.01 24 Page 2
3.2 IMPLEMENTATION
3.2.1 Notice of Intent
The Contractor shall complete and submit a Notice of Intent (NOI) in accordance with Permit No. SDR10####. A copy of the submitted NOI shall be furnished to the COR at least 15 days prior to the commencement of construction activities. The Government shall be considered the "Applicant" and shall sign as such on the form after review. The Contractor will complete Attachment C in the Permit No.SDR10####.
Attachment C is titled Deparment of Environment and Natural Resources Contractor Certification Form. Which will be submitted with the NOI.
NOTE: The Contractor is responsible for any Notice of Violations that occur during the NPDES Permit being in effect. The Contractor will be responsible for paying for any violation fines and/or making any corrections necessary.
The State Of South Dakota has authorized stormwater permit fees. Effective July 1, 2018 new construction Notice of Intents (NOIs) must include the first year's fee, shall be paid the the Contractor at time of the NOI filing. (If the fee is not paid, the owner of the project will be billed, but the Contractor will be responsible for the fee.) The fee as follows:
•<5 acres = $100 •5 to <40 acres = $250 •40 to <80 acres = $500 •80+ acres = $750 NOTE: These fees are per year and must be paid every year of the project by the Contractor.
3.2.2 Authorization Letter
Construction activities regulated under Permit No. SDR10#### shall not begin until an authorization letter from the State granting coverage for the storm water discharges is received by the Contractor. A copy of the authorization letter shall be furnished to the COR at least 2 days prior to the commencement of construction activities.
3.2.3 Posting NOI and Authorization Letter
A copy of the NOI and the authorization letter shall be posted by the Contractor at the construction site in a prominent place for public viewing.
3.2.4 Storm Water Pollution Prevention Plan
The Contractor shall prepare and implement a Storm Water Pollution Prevention Plan (SWPPP) in accordance with Permit No. SDR10####. Any temporary or permanent erosion and sedimentation control measures shown on the drawings shall be incorporated into the Contractor's SWPPP. A copy of the SWPPP shall be submitted to the COR at least 2 days prior to the commencement of construction activities. Copies of all revisions to the SWPPP shall also be submitted.
3.2.5 Inspections and Reporting
The Contractor shall be responsible for all inspections and reporting required under the NPDES Permit No. SDR10####. Copies of all inspection reports shall be furnished to the COR.
SECTION 01 41 26.01 24 Page 3
3.2.6 Retention of Records
The Contractor shall retain a copy of the SWPPP, reports, and records of all data used to complete the NOI in accordance with Permit No. SDR10####.
3.2.7 Notice of Termination
The Contractor shall complete and submit a Notice of Termination (NOT) in accordance with Permit No. SDR10####. The Government shall be considered the "Facility Operator". A copy of the submitted NOT shall be furnished to the COR for signature prior to submission to the State..
3.2.8 Renotification
If the current permit expires prior to completion of construction, the Contractor shall submit a new NOI in accordance with Permit No. SDR10####.
A copy of all submissions to the State shall be furnished to the COR.
SECTION 01 41 26.01 24 Page 4
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 57 20.00 10
ENVIRONMENTAL PROTECTION
08/21
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.2.1 Environmental Pollution and Damage
1.2.2 Environmental Protection
1.2.3 Contractor Generated Hazardous Waste
1.2.4 Land Application for Discharge Water
1.2.5 Pests
1.2.6 Surface Discharge
1.2.7 Waters of the United States
1.2.8 Wetlands
1.3 GENERAL REQUIREMENTS
1.4 SUBCONTRACTORS
1.5 PAYMENT
1.6 SUBMITTALS
1.7 ENVIRONMENTAL PROTECTION PLAN
1.7.1 Compliance
1.7.2 Contents
1.7.3 Appendix
1.8 PROTECTION FEATURES
1.9 PERMITS, NOTICES, REVIEWS, AND/OR APPROVALS
1.9.1 NPDES Permit for South Dakota Construction Activities
1.9.2 US Army Corps of Engineers, 404 Nationwide Permit1
1.10 ENVIRONMENTAL ASSESSMENT OF CONTRACT DEVIATIONS
1.11 NOTIFICATION
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 LAND RESOURCES
3.1.1 Work Area Limits
3.1.2 Landscape
3.1.3 Erosion and Sediment Controls
3.1.4 Contractor Facilities and Work Areas
3.2 WATER RESOURCES
3.2.1 Wetlands
3.3 AIR RESOURCES
3.3.1 Particulates
3.3.2 Odors
3.3.3 Sound Intrusions
3.3.4 Burning
3.4 CHEMICAL MATERIALS MANAGEMENT AND WASTE DISPOSAL
3.4.1 Solid Wastes
SECTION 01 57 20.00 10 Page 1
3.4.2 Chemicals and Chemical Wastes
3.4.3 Contractor Generated Hazardous Wastes/Excess Hazardous Materials
3.4.4 Fuel and Lubricants
3.4.5 Waste Water
3.5 RECYCLING AND WASTE MINIMIZATION
3.6 NON-HAZARDOUS SOLID WASTE DIVERSION REPORT
3.7 HISTORICAL, ARCHAEOLOGICAL, AND CULTURAL RESOURCES
3.8 BIOLOGICAL RESOURCES
3.8.1 Endangered/Threatened Species
3.8.1 Interior Least Terns and/or Piping Plovers
3.8.2 Bald Eagles
3.8.3 Migratory Birds
3.9 PREVIOUSLY USED EQUIPMENT
3.10 MAINTENANCE OF POLLUTION FACILITIES
3.11 TRAINING OF CONTRACTOR PERSONNEL
3.12 POST CONSTRUCTION CLEANUP
SECTION 01 57 20.00 10 Page 2
SECTION 01 57 20.00 10
ENVIRONMENTAL PROTECTION
08/21
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
WETLANDS DELINEATION MANUAL Corps of Engineers Wetlands Delineation Manual
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
33 CFR 328 Definitions of Waters of the United States
40 CFR 261 Identification and Listing of Hazardous Waste
40 CFR 262 Standards Applicable to Generators of Hazardous Waste
40 CFR 279 Standards for the Management of Used Oil
40 CFR 302 Designation, Reportable Quantities, and Notification
40 CFR 355 Emergency Planning and Notification
40 CFR 68 Chemical Accident Prevention Provisions
49 CFR 171 - 178 Hazardous Materials Regulations
1.2 DEFINITIONS
1.2.1 Environmental Pollution and Damage
Environmental pollution and damage is the presence of chemical, physical, or biological elements or agents which adversely affect human health or welfare; unfavorably alter ecological balances of importance to human life;
affect other species of importance to humankind; or degrade the environment aesthetically, culturally and/or historically.
1.2.2…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .