SUMMARY OF WORK AND SPECIAL CONDITIONS

01010-1

C:\Users\denisethomas\AppData\Local\Temp\acrord32_sbx\A9bo4udw_18q3rnq_fkk.tmp\SPECS.doc

SECTION 01010

PART 1 GENERAL

1.01 SUMMARY

Description of Work: Contract shall include all tools, procurement, construction, delivery and installation of a new rolled carpet flooring in the Reserve Conference room which shall terminate at the existing tile flooring near the sink. Work shall include demolition and disposal of existing carpet tile flooring and include extension and professional finish of existing floor receptacles (approximately 16 – 8” x 6” receptacles). Also included shall be all base boards and threshold coverings at all carpet terminations such that the final product is finished professionally and complete. Total flooring area is approximately 600 square feet with approximately 100 linear feet of wall for baseboard. Exact dimensions to be field verified by contractor. Carpeting shall be high wear and stain resistant and shall be in the style of Spiced Tea as made by Mohawk Flooring (or approved COR equal). Installment shall include all carpet backing / cushioning as recommended by manufacturer. Included Contractor shall submit example of flooring and baseboards for approval prior to procurement. Baseboards shall be oak and match flooring in color. Work shall include all fasteners and underlayment as recommended by vendor. As a note, existing carpeting was carpet tiles placed on a floating floor. Contractor may be required to add modifications to existing flooring in order to professionally lay new carpeting. Final work shall be professional and without any defects. Work shall also include all provisions needed for existing floor receptacles. Extensions shall be provided, if needed, and final product shall have a smooth transition to the existing receptacles with a professional finish and ease of use of receptacles.

A. Location: Work under this contract is located in Reserve, Catron County, New Mexico.

1.02 REFERENCES

A. Referenced Specifications/Standards with Abbreviations and/or Acronyms: Wherever the following acronyms are used in these specifications or on the drawings, they are to be construed the same as the respective expressions represented. Copies of the referenced specifications/standards referred to herein may be procured by the Contractor from the following:

B. Construction which is not governed by a local building code or the Contract Specifications will be governed by the more stringent provisions of the latest published edition, or Statute adopted edition, of the following applicable codes:

ANSI American National Standards Institute 1430 Broadway New York, NY 10018

APA American Plywood Association P. O. Box 11700 Tacoma, WA 98411

ASTM American Society of Testing and Materials 1916 Race Street Philadelphia, PA 19103

01010-2

C:\Users\denisethomas\AppData\Local\Temp\acrord32_sbx\A9bo4udw_18q3rnq_fkk.tmp\SPECS.doc

AWI Architectural Woodwork Institute 2310 S. Water Reed Dr.

Arlington, VA 22206

AWPA American Wood Preservers’ Association P. O. Box 849 Stevensville, MO 21666

CPSC Consumer Products Safety Commission Superintendent of Documents Forest Printing Office Washington, DC 20402

FM Factory Mutual System Factory Mutual Engineering and Research Corporation P. O. Box 888 Norwood, MA 02062

FS Federal Specifications/Standards Superintendent of Documents Forest Printing Office Washington, DC 20402

NBS National Bureau of Standards Gaithersburg, MD 20899

NPCA National Paint and Coatings Association 1500 Rhode Island Avenue, N.W.

Washington, DC 20005

NWMA National Woodwork Manufacturing Association, Inc.

205 W. Touhy Ave.

Park Ridge, IL 60068

OSHA Occupational Safety and Health Administrations’ Standards U. S. Department of Labor Denver Area Office 333 West Colfax Ave.

Denver, CO 80204

PS Product Standard (U.S. Department of Commerce) Superintendent of Documents Forest Printing Office Washington, DC 20402

TCA Tile Council of America, Inc.

P. O. Box 326 Princeton, NJ 08542

WCLIB West Coast Lumber Inspection Bureau P. O. Box 23145 Portland, OR 97225

WWPA Western Wood Products Association 1500 Yeon Building Portland, OR 97204

01010-3

C:\Users\denisethomas\AppData\Local\Temp\acrord32_sbx\A9bo4udw_18q3rnq_fkk.tmp\SPECS.doc

1. NOTE: Federal specifications and catalogues may be obtained at Business Service Centers of Regional Offices of the General Services Administration, Washington, DC; Boston, MA; New York, NY; Philadelphia, PA; Atlanta, GA;

Chicago, IL: Kansas City, MO; Ft. Worth, TX; Denver, CO; San Francisco, CA;

and Auburn, WA.

B. Referenced Codes with Abbreviations and/or Acronyms: Wherever the following acronyms are used in these specifications or on the drawings, they are to be construed the same as the respective expressions represented. Copies of the referenced codes referred to herein may be procured by the Contractor from the following:

UBC Uniform Building Code International Conference of Building Officials 5360 S. Workman Mill Rd.

Whittier, CA 90601

UL Underwriters’ Laboratories, Inc.

333 Pfingston Rd.

Northbrook, IL 60062

1.03 QUALITY ASSURANCE

A. Code and Standards: The work shall comply with codes and standards applicable to each type of work and as listed in the individual sections of these specifications. This Contract incorporates materials, applications, and tests by reference, with the same force and effect as if they were given in full text.

B. Conflict: Where a conflict occurs between reference documents and project specifications, the project specifications shall govern.

C. Measurements: Where approved manufacturers’ diagrams and shop drawings give specific measurements or rough-in dimensions for equipment, these dimensions shall take precedence over dimensions indicated on the drawings.

1.04 DELIVERY, STORAGE, AND HANDLING

A. Delivery: The Contractor shall protect products, incorporated into the work, from damage while in transit to the site. Products must be delivered in original unopened containers with manufacturers’ name and brand designation and contents legibly indicated. The containers shall bear the referenced specification number, type and class as applicable.

B. Storage: The Contractor shall provide temporary storage facilities for products complying with manufacturers’ recommendations that will protect them from damage until installation of the project and final acceptance. The storage area shall permit access for inspection and handling.

1.05 Handling: The Contractor shall load and unload products in such manner that protects them from damage until installation on the project.

1.06 PROJECT/SITE CONDITIONS

A. Access to the Work: Contractor shall coordinate with COR for all access to the site.

1.07 SEQUENCING AND SCHEDULING

A. Requirements: The Contractor shall be responsible for operations necessary to complete the work, including coordination with other crafts relative to the contractor’s requirements.

01010-4

C:\Users\denisethomas\AppData\Local\Temp\acrord32_sbx\A9bo4udw_18q3rnq_fkk.tmp\SPECS.doc

Work shall be scheduled in such a manner as to avoid delays in overall construction and permit proper installation of work.

1.08 MISCELLANEOUS REQUIREMENTS

A. The organization of these specifications into Divisions, Sections and Articles, and the arrangement of the drawings, shall not control the Contractor in dividing the work among subcontractors or in establishing the extent of work to be performed by any trade.

B. Do not scale any drawings. Rely on printed dimensions.

C. Field verification of scale dimensions is required since actual locations, distances, and levels will be governed by actual field conditions.

1.09 UTILITY CONNECTIONS

A. Electrical Service: Existing electrical service to the building. Contractor shall be responsible for all necessary connections.

B. Water Service: Contractor shall be responsible for extending existing supply to all necessary points of use.

1.10 CONSTRUCTION SCHEDULE AND PROGRESS CHARTS:

A. Within 10 days after receipt of Notice to Proceed, the Contractor shall prepare and submit to the COR for approval a practicable progress schedule. The schedule shall show the order in which the Contractor proposes to carry on the work, the date of which he will start the several major activities (including procurement of materials, plants, and equipment), and the contemplated dates for completing same. The schedule shall be in the form of a progress chart of suitable scale to indicate graphically the percentages of work scheduled for completion at any time. As the Work progresses, the Contractor shall enter on the chart the actual progress at the end of each partial payment period or at such intervals as directed by the COR. The Contractor shall also revise the schedule to reflect any adjustments in contract time approved by the COR. Three copies of the updated schedule shall be delivered at such intervals as directed by the COR.

B. If, in the opinion of the COR, the work accomplished falls behind that schedule, the

Contractor shall take such action as necessary to improve his progress. In addition, the COR may require the Contractor to submit a revised schedule demonstrating his program and proposed plan to make up lag in scheduled progress and to insure completion of work within the contract time. If the COR finds the proposed plan not acceptable, he may require the Contractor to submit a new plan. If a satisfactory plan is not agree upon, the COR may require the Contractor to increase the work force, the construction plan and equipment, or the number of work shifts, without additional cost to the Forest.

C. Failure of the Contractor to comply with these requirements shall be considered grounds for determination by the COR that the Contractor is failing to prosecute the work with such diligence as will insure its completion within the time specified.

1.11 FOUNDATON INFORMATION

A. Bidders should visit the site and acquaint themselves with all existing conditions. Prior to bidding, bidders may make their own subsurface investigations to satisfy themselves as to site and subsurface conditions, but all such investigations shall be performed only under time schedules and arrangements approved in advance by the COR.

01010-5

C:\Users\denisethomas\AppData\Local\Temp\acrord32_sbx\A9bo4udw_18q3rnq_fkk.tmp\SPECS.doc

B. Adjust all work performance that does not meet technical or design requirements, but make no deviations from Contract Documents without specific and written approval of the

COR.

1.12 TESTS

A. In the event of suspicion of inadequate work, the COR may call for testing. In the event of a failed test, Contractor shall pay for all testing, repairs and re-testing if deemed necessary by the COR.

1.13 CUTTING AND PATCHING: In addition to the requirements of the General Conditions, Contractor shall perform all cutting and patching required to remove and replace work not conforming to the requirements of the Contract Documents, to uncover ill-timed work for inspection, to replace defective work, to make parts fit properly, etc., and shall:

A. Perform all cutting and patching in strict accordance with pertinent requirements of these

Specifications and, in the event no such requirements are determined, in conformance with the COR’s written direction.

B. Prior to cutting which affects structural safety, submit written request to the COR for permission to proceed with cutting.

C. Prior to cutting and patching performed pursuant to the COR’s instructions, submit cost estimate to the COR. Secure the COR’s approval of cost estimates and type of cost reimbursement before proceeding with cutting and patching.

D. Submit written notice to the COR designating time the work will be uncovered, to provide for the COR’s observation.

E. Perform all other cutting and patching needed to comply with the Contract Documents at no additional cost to the Forest. (The Forest will reimburse the contractor for cutting and patching performed pursuant to the COR’s written request after claim for such reimbursement is submitted by the Contractor.)

1.14 RECORD DRAWINGS: In accordance with the requirements of the General Conditions, the COR will provide the contractor with a set of reproducible drawings to the original bidding documents, as required and at contractor’s expense, as follows:

A. If the Contractor elects to vary from the Contract Documents, and secures prior approval of the COR, for any phase of the work other than those listed below, he shall record in a neat readable manner all such variances on the reproducible drawings furnished.

B. The following requirements apply to all Record Drawings.

1. They shall be maintained at the Contractor’s expense.

2. All such drawings shall be done carefully and neatly by a competent draftsman and inform approved by the COR.

3. Additional drawings shall be provided as necessary for clarification.

4. They shall be kept up-to-date during the entire course of the work and shall be available on request for examination by the COR and, when necessary, to establish clearances for other parts of the work.

5. The Record Drawings shall be returned to the COR on completion of the work and are subject to the approval of the COR.

1.15 TEMPORARY CONSTRUCTION AND SERVICES: The Contractor shall provide the following specific items of temporary construction and services:

01010-6

C:\Users\denisethomas\AppData\Local\Temp\acrord32_sbx\A9bo4udw_18q3rnq_fkk.tmp\SPECS.doc

A. Temporary Water:

1. Water required in the performance of the Contract shall be available at the site and paid for by the Forest. Contractor shall practice prudent use of water.

2. Contractor shall furnish and install all mains, laterals, branch lines and service pipings and fittings to supply temporary water in sufficient quantity as required to locations of the building and shall bear costs of making the service connections at approved locations. Temporary connections and piping shall be removed and all openings closed at the end of the work.

B. Temporary Electric Service:

1. Electricity required in the performance of the Contract shall be available at the site and paid for by the Forest. Contractor shall practice prudent use of electricity.

C. Contractor may use existing toilet facilities. Contractor shall maintain facilities in a clean and neat condition.

D. Temporary Closures: Contractor shall erect temporary closures over openings when weather conditions render such action necessary for proper installation of any portion of the work. The Contractor shall also install temporary partitions as shown or required to separate work under construction from areas occupied by the Forest.

E. Protection of Work in Place: Work in place that is subject to injury because of operations carried on adjacent thereto shall be covered, boarded up or substantially enclosed with adequate protection. Permanent openings used as thoroughfares for the introduction of work and materials to the structure shall have heads, jambs and sills well blocked and boarded. All forms of protection shall be constructed in such manner that on completion the entire work will be delivered to Forest in unblemished condition.

F. Temporary Fire Protection: Contractor shall provide and maintain fire extinguishers, fire hoses and other equipment necessary for fire protection during construction. Such equipment shall be used for fire protection only.

G. Signs: No signs will be permitted on the Project except the project sign, identifying captions over offices, certain directional and warning signs required for safety and protection. Contractor shall take all necessary steps to prevent installation of any unauthorized signs, and, should any appear, cause them to be removed immediately, and repair and repaint any damage caused thereby without additional cost to the Forest.

H. Temporary Buildings: All temporary buildings shall be maintained in a neat orderly appearance for the duration of the Work.

I. Removal of Temporary Construction: Temporary office facilities, toilets, storage sheds, and other construction of a temporary nature shall be removed from the site as soon as the progress of the Work will permit; and the portions of the site occupied by the same shall be properly restored.

1.16 CLEANING UP: In addition to other provisions of the Specifications, the following shall be required:

A. Besides the “removal of waste materials,” the following special cleaning shall be required just prior to acceptance.

1. Remove stains, wash and polish glass inside and outside. This work shall be done by persons skilled and equipped for such work.

2. Remove foreign matter, marks, stains, foreign paint, fingerprints, soil and dirt from (and have in a polished condition where applicable) the following:

a. Painted, decorated and stained Work.

b. All hardware, fixtures and incorporated equipment.

01010-7

C:\Users\denisethomas\AppData\Local\Temp\acrord32_sbx\A9bo4udw_18q3rnq_fkk.tmp\SPECS.doc

c. All finished surfaces and metal surfaces, whether interior or exterior.

d. All doors and windows.

B. Use only the cleaning materials and equipment, which are compatible with the surface being cleaned, as recommended by the manufacturer of the material or as approved by the COR.In addition to the clean-up provisions of the Specifications, the Contractor shall take appropriate steps to prevent airborne dust due to the Work of the Contract. Water shall be applied wherever practical to settle and hold dust to a minimum, particularly during excavation and moving of materials.

1.17 EXAMINATION OF SITE

A. Bidders are requested to visit the site, compare the drawings and specifications with any work in place, and inform themselves of all conditions, including other work, if any, being performed. Failure to visit sites will in no way relieve the successful bidder from necessity of furnishing any materials or performing any work that may be required to complete work in accordance with drawings and specifications, without additional cost to the Forest.

B. Information respecting the site of the work given in drawings or specification is believed to be reasonably correct, but the Forest does not warrant either the completeness of accuracy of such information, and it is the responsibility of the contractor to verify all such information independently and to make such other examination of the conditions to be encountered during construction.

C. The Contractor acknowledges that he has investigated and satisfied himself as to the conditions affecting the work, including, but not restricted to, those bearing upon transportation, disposal, handling and storage of materials, availability of labor, water, electric power, roads and uncertainties and conditions of the ground, the character of equipment and facilities needed preliminary to and during prosecution of the work. The Contractor further acknowledges that he has satisfied himself to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the sites. Any failure by the Contractor to acquaint himself with the available information will not relieve him from responsibility for estimating properly the difficulty or cost of successfully performing the work. The Forest assumes no responsibility for any conclusions or interpretations made by the Contractor on the basis of the information made available by the COR.

PART 2 PRODUCTS

2.01 GENERAL

A. (See specific section for applicable requirements).

PART 3 EXECUTION

3.01 PREPARATION

A. Any monuments or benchmarks disturbed or removed during construction shall be reset by the Contractor at the Contractor’s expense.

3.02 PROTECTION

01010-8

C:\Users\denisethomas\AppData\Local\Temp\acrord32_sbx\A9bo4udw_18q3rnq_fkk.tmp\SPECS.doc

A. Damage: Repair of damage to new construction and equipment or existing utilities resulting from construction procedures, shall not be initiated prior to notification of the

COR.

B. Right-of-Way: Existing utility lines shall have the right-of-way over all other lines, and all lines encountered by the Contractor shall be carefully maintained in proper alignment.

Should the Contractor find that the grades of new utility lines intersect existing utility lines, he shall stop the laying of the new lines until new grades are established.

C. Repairs: The Contractor shall repair damages to any new or existing active utility above or below ground, whether indicated on the drawings or not, and immediately report such damage to the COR. All costs of repair for damages due to the Contractor’s negligence will be paid by the Contractor.

END OF SECTION

01010-9

C:\Users\denisethomas\AppData\Local\Temp\acrord32_sbx\A9bo4udw_18q3rnq_fkk.tmp\SPECS.doc

SECTION 02040

DEMOLITION

PART 1 GENERAL

1.01 DESCRIPTION

A. Remove existing work, materials and items as indicated on the drawings, as required by job site conditions, as scheduled, and as specified herein, to accomplish new work and alteration in the existing buildings. Cut pockets, openings, chases, depressions, etc, to install or allow for installation of materials.

B. Patch all existing surfaces that are disturbed, damaged or otherwise made defective in appearance or function by the execution of required work under this contract. Repair and resurface all disturbed areas using compatible materials to match adjacent surfaces in hardness and texture.

1.02 QUALITY ASSURANCE

A. Contractor shall coordinate construction procedures and schedule with Forest’s representative, and shall comply with all applicable requirements found in the Construction Documents.

PART 2 PRODUCTS

2.01 DISPOSITION OF MATERIALS

A. Remove all materials or debris resulting from demolition operation from the site promptly.

No accumulation of debris will be permitted.

B. Do not burn wood and inflammable debris resulting from demolition operations on the site.

PART 3 EXECUTION

3.01 PREPARATION

A. Plan all work in advance, informing COR of procedure and schedule.

3.02 INSTALLATION

A. Protect existing buildings and adjacent surfaces, features, and property. Restore to original condition all work damaged or otherwise made defective in appearance or function by the execution of required work under this contract. Interference with Forest’s use of existing buildings and facilities shall be kept to a minimum and all work resulting in such interference shall be performed at a time approved beforehand by the Engineer/Architect.

B. Remove all work carefully and only to the extent required for the final work. Remove all loose or damaged materials, caused by demolition, noted or specified to be removed.

C. Conduct all operations with a minimum of noise.

D. Erect dustproof partitions where demolition work is in progress and as directed. Such partitions shall remain in place until their removal is directed.

01010-10

C:\Users\denisethomas\AppData\Local\Temp\acrord32_sbx\A9bo4udw_18q3rnq_fkk.tmp\SPECS.doc

E. Where openings are to be cut in existing structures; cut such openings with care. Where materials, equipment, frames, etc., are to be removed, remove such items with care to minimize damage to adjacent materials. Structural shoring and/or bracing may be necessary for safety reasons and to prevent structural collapse.

F. Sawcutting is permitted. The use of pneumatic or electric hammers for demolition and cutting purposes will require prior approval of the COR.

G. After the demolition work in any area is completed, clean the area before any new construction is started.

H. Any abandoned utilities to be terminated at floor, walls, ceilings, and other locations shall be capped securely within floor, wall, or ceiling, tested by Contractor and approved by COR before being covered. After approval, areas shall be patched and finished to match adjacent surfaces. Utility connections include, but are not limited to, water, electric, phone, computer, drains, vents, and other utilities. Coordinate with plumbing drawings and equipment supplier.

I. Walls and structural elements to be removed may consist of concrete masonry units, plaster, concrete, metal, wood, or other materials. All repairs shall be made with materials to match adjacent.

J. Drawings are schematic only, Field-verify for estimating and construction purposes.

3.03 PROTECTION

A. Take reasonable and adequate precautions to protect the Forest’s property from damage during demolition work, moving of debris, and damage by the elements. Restore any damage to Forest property due to the aforesaid work or replace in a manner satisfactory to the Engineer/Architect.

B. Provide and maintain suitable barricades, shelters, lights, and danger signals during the progress of the work. They shall meet the requirements of the applicable building codes, safety codes & regulations. Assume the responsibility of barriers to completion of contract and remove same.

01010-11

C:\Users\denisethomas\AppData\Local\Temp\acrord32_sbx\A9bo4udw_18q3rnq_fkk.tmp\SPECS.doc

SECTION 06400

ARCHITECTURAL WOODWORK

PART 1 GENERAL

1.01 DESCRIPTION

A. Work includes: Provide and install Architectural Woodwork as needed for proper installation of flooring and baseboards.

1.02 QUALITY ASSURANCE

A. Use adequate numbers of skilled workers who are thoroughly trained and experienced in the necessary crafts and who are completely familiar with the specified requirements and the methods needed for proper performance of the work of this Section.

B. Codes and standards:

1. In addition to complying with pertinent codes and regulations of governmental agencies having jurisdiction, comply with minimum requirements of the Architectural Woodwork Institute for the grade specified.

2. WIC certification and stamp will not be required.

1.03 SUBMITTALS

A. Comply with pertinent provisions of Section 01340.

B. Product data: Within 7 calendar days after the Contractor has received the Forest's Notice to Proceed, submit:

1. Materials list of items proposed to be provided under this Section;

2. Shop drawings if needed

1.04 PRODUCT HANDLING

A. Comply with pertinent provisions of Section 01640.

PART 2 PRODUCTS

2.01 FLOORING / BASEBOARDS

A. Finish hardware shall be factory installed, and shall be selected contractor and approved by the COR from standard styles and finishes of the approved manufacturer.

2.04 OTHER MATERIALS

A. Provide other materials, not specifically described but required for a complete and proper installation, as selected by the Contractor subject to the approval of the COR.

PART 3 EXECUTION

3.01 SURFACE CONDITIONS

A. Examine the areas and conditions under which work of this Section will be performed.

Correct conditions detrimental to timely and proper completion of the Work. Do not proceed until unsatisfactory conditions are corrected.

3.02 FIELD MEASUREMENTS

A. Take necessary measurements in the field to assure proper dimensions for the work of this Section.

3.03 INSTALLATION

01010-12

C:\Users\denisethomas\AppData\Local\Temp\acrord32_sbx\A9bo4udw_18q3rnq_fkk.tmp\SPECS.doc

A. Install the work of this Section in strict accordance with the approved Shop Drawings and the referenced standards, anchoring all items firmly into position and to secure a plumb and level installation. No visible gaps shall exist between cabinetwork and adjacent surfaces of the room. .

01010-13

C:\Users\denisethomas\AppData\Local\Temp\acrord32_sbx\A9bo4udw_18q3rnq_fkk.tmp\SPECS.doc

SECTION 09680

CARPETING

PART 1 GENERAL

1.01 DESCRIPTION

A. Work included: Provide carpeting and carpet accessories where shown on the Drawings, as specified herein, and as needed for a complete and proper installation.

B. Related work:

1. Documents affecting work of this Section include, but are not necessarily limited to, General Conditions, Supplementary Conditions, and Sections in Division 1 of these Specifications.

1.02 QUALITY ASSURANCE

A. Use adequate numbers of skilled workmen who are thoroughly trained and experienced in the necessary crafts and who are completely familiar with the specified requirements and the methods needed for proper performance of the work of this Section.

1.03 SUBMITTALS

A. Product data: Within 30 calendar days after the Contractor has received the CO's Notice to Proceed, submit:

1. Materials list of items proposed to be provided under this Section;

2. Manufacturer's specifications and other data needed to prove compliance with the specified requirements;

3. Shop Drawings showing location of seams and locations and types of carpet metal and accessories;

4. Samples of the full range of colors and patterns of carpet and of exposed accessories available from the proposed manufacturers in the specified qualities.

5. Manufacturer's recommended installation procedures which, when approved by the COR, will become the basis for accepting or rejecting actual installation procedures used on the Work.

C. After the COR has selected the color and pattern, submit three Samples of each specified color and pattern from the stock proposed to be installed. Secure the COR’s approval of these Samples prior to installation.

1.04 PRODUCT HANDLING

A. Comply with pertinent provisions of Section 01640.

PART 2 PRODUCTS

2.01 CARPET

A. Provide "Spiced Tea" design, by Mohawk, or provide equal products of other manufacturers’ when approved by the COR.

B. Provide carpeting with at least the following minimum attributes:

1. 10 year limited wear warranty;

2. Fiber: 100% solution dyed nylon;

3. Stitch gauge: 1/10;

4. Yarn weight: 28-oz.;

5. Pile height: 3/16-inch, 5/32-inch, 1/8-inch;

6. Stitches per inch: 10;

01010-14

C:\Users\denisethomas\AppData\Local\Temp\acrord32_sbx\A9bo4udw_18q3rnq_fkk.tmp\SPECS.doc

7. Primary backing: Polypropylene;

8. Secondary backing: ActionBac R

9. Total weight/square yard: 62 oz.;

10. Width: 12 ft.;

11. Flammability: Pill test (CPSC FF1-70, ASTM D-2859), passed.

2.02 OTHER MATERIALS

A. Adhesives:

1. Provide carpet adhesive recommended for the purpose by the manufacturer of the proposed carpet, or equal approved by COR.

2. Provide seam adhesive recommended for the purpose by the manufacturer of the proposed carpet, or equal approved by COR.

B. At intersection of carpet and other flooring, provide threshold cover or other cover which will prevent tearing of edge of carpet.

C. Provide other materials, not specifically described but required for a complete and proper installation, as selected by the Contractor subject to the approval of the COR.

PART 3 EXECUTION

3.01 SURFACE CONDITIONS

A. Examine the areas and conditions under which work of this Section will be performed.

Correct conditions detrimental to timely and proper completion of the Work. Do not proceed until unsatisfactory conditions are corrected.

3.02 SURFACE PREPARATION

A. Immediately prior to installation of the work of this Section, thoroughly clean substrata and remove oil, grease, paint, varnish, hardeners, and other items, which would adversely affect the bond of adhesive.

B. Make substrata level and free from irregularities. Assure one constant floor height after carpet is installed, filling low spots and grinding high spots as required.

3.03 INSTALLATION

A. General:

1. Place on floor, using pads or foam as recommended by manufacturer if required.

2. Scribe the carpet accurately to vertical surfaces.

3. Align the lines of carpet, as woven, using no fill stripes less than 6" wide, laying all carpet in the same direction unless specifically directed otherwise by the Engineer/Architect.

B. Seams:

1. Lay such as to make minimum seams.

2. Locate seams to the maximum extent practicable out of the way of traffic.

3. Fabricate seams by the compression methods, using a butt joint, and properly bead and seal.

4. Do not stretch seams.

C. In addition to the cleaning requirements stated elsewhere, thoroughly clean carpet and adjacent surfaces prior to final acceptance of the carpeted areas by the COR.

01010-15

C:\Users\denisethomas\AppData\Local\Temp\acrord32_sbx\A9bo4udw_18q3rnq_fkk.tmp\SPECS.doc

3.04 PROTECTION

A. Provide a heavy non-staining paper or plastic walkway as required over carpeting in direction of traffic, maintaining intact until carpeted space is accepted by the COR.

3.05 SURPLUS MATERIAL

A. Allow the COR to inspect and select from scrap carpet remaining after the installation.

Bundle, wrap in burlap, and deliver to the Owner the carpet scraps selected by him.