This document outlines requirements for a bulk ramp materials contract for Cape Hatteras National Seashore. The National Park Service Outer Banks Group requires clam shell material to repair and maintain vehicle access ways at two locations - 1375 cubic yards for the Cape Point Campground Parking Lot in Buxton, and 100 cubic yards for the Ocracoke Maintenance Yard. The clam shells must be crushed and rolled with no more than 25% whole shells, and may contain up to 10% of other shell types but no oyster shells. Delivery vehicles must contact the NPS point of contact for exact delivery locations, and are responsible for site conditions. Receipts documenting material details are required from each delivery, and the contractor must retain records. The related federal contract opportunity is solicitation number 140P5323Q0052 for FY23 bulk ramp materials for the Department of the Interior National Park Service Southeast Region.

View the file

Other files

File Type Posted
Sol_140P5323Q0052.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ramp Maintenance Materials Page 1

CAPE HATTERAS NATIONAL SEASHORE

Outer Banks Group

Statement of Work

FY 23 Provide Bulk Ramp Materials

1.0 INTRODUCTION

The National Park Service (NPS) Outer Banks Group (OBG) has a requirement for construction materials to several sites on Cape Hatteras National Seashore.

2.0 CONSTRUCTION SITE LOCATIONS

The site locations include:

1) Buxton - Parking area between Cape Point CG and South beach Road (back of Cape

Point Campground) See Figure 2.

a. 35 o 14’06.73” N, 75 o 32’37.52” W

2) Ocracoke Burrow Pit Parking lot and Bitterswash parking

a. 35 o 07’03.67” N, 75 o 59’01.86” W

3.0 BACKGROUND AND EXISTING CONDITIONS

The NPS maintains vehicle access ways to the National Seashore using a variety of materials for the surface. A mixture of clay and shells per the instructions of the North Carolina Coastal Area

Management Agency (CAMA) is used for repairs and maintenance to the access ways. NC

Highway 12 runs from Bodie Island south to Ocracoke Island. The NPS has sand ramps at various locations along Highway 12.

The following pictures show aerial photos of the project sites:

Ramp Maintenance Materials Page 2

Figure 2. Cape Point Campground Parking Lot, Buxton, NC

Figure 3. Ocracoke Bitter Swash Parking Lot and Burrow Pit Parking Lot

Ramp Maintenance Materials Page 3

4.0 STATEMENT OF WORK

The contractor will provide all technical support, materials, tools, equipment, and manpower required to provide the NPS with the following:

Ramp Maintenance Materials Page 4

Base BID: Provide the following at the locations listed. The Contractor must meet the requirements and deliverables. Take special note of the additional requirements below – receipts showing weights/volumes must be provided to the NPS and a copy kept for the Contractor’s records.

Buxton - Cape Point Campground Parking Lot:

• 1375 cubic yards of clam shell material

Ocracoke Maintenance Yard:

• 100 cubic yards of clam shell material

Material Requirements:

i. Soil group classification

2) The clam shells must meet the following specifications:

a. The clam shells must be crushed and rolled to reduce edges. Whole shells should not account for more than 25% of the delivered material.

b. Scallops, cockle shells, whelks, and cone shells can be included but should not be more than 10% of the total shell volume.

c. Oyster shells may not be substituted.

The NPS reserves the right to take samples of any or all deliveries to be tested for consistency and material distribution. The NPS reserves the right to withhold payment for any delivery that does not meet expectations as agreed upon between the NPS and contractor providing the material. If the material is deemed inadequate the NPS may reject the delivery and the contractor must provide additional material until the full amount of acceptable material is received. The contractor may obtain additional samples and test above the required number at his own expense to verify overall consistency of the deliveries.

ADDITIONAL REQUIREMENTS:

1) The vendor will be required to call the NPS point of contact (POC) for exact location on the day of delivery.

2) The Contractor must abide by the conditions listed in the Deliverables section of this scope of work.

3) The Contractor is responsible for all drivers and vehicles used for deliveries. These sites are considered off road and may require backing, turning, dumping, etc. on or near unpaved areas. The Contractor is responsible for verifying existing conditions prior to and at time of delivery.

4) The Contractor is required for scheduling deliveries to meet ferry routes to and from

Ocracoke Island. Contractor vehicles are authorized to utilize the priority lane for ferry routes between Hatteras Island and Ocracoke Island.

Ramp Maintenance Materials Page 5

5) Each vehicle/truck providing a delivery must also provide a receipt showing the materials being delivered to include volume, weight, dimensions, etc.

6) The Contractor must keep his own record/receipts of delivery in order to request payment. Accumulated totals of each type of material must be provided to the POC prior to submitting an invoice for payment.