1/21/20

MINIMUM SPECIFICATION FOR

UV LASER WIRE MARKING MACHINE

1. Scope

This specification defines the minimum requirements for a new UV Laser Wire Marking Machine for the Electronics Fabrication Division. This specification includes details for the purchase and training for a new wire marking machine with the accessories as defined in this specification.

2. Application

The UV Laser Marking Machine along with its accessories will be used to mark wire/cable for cable assemblies.

3. Process/Performance Requirements The wire marking machine shall be an automated UV laser marking machine capable of being interfaced with Schleuniger automatic cut and strip system. The marking machine shall be capable of automated marking in conjunction with wire processing on Schleuniger PS9550. The marking system shall meet the following requirements as a minimum:

3.1 Enclosure: The UV laser marking machine shall include the appropriate enclosure and or shielding to protect operators from moving part hazards and UV laser exposure.

3.2 Wire size: Marking machine shall be capable of marking Wire sizes are 0.13 – 13.0 mm² (26 – 6 AWG) and cable diameter are between 0.75 – 10 mm (.030 – 0.394”) as a minimum.

3.3 Wire Products: The marking machine shall be capable of marking any UV laser markable wire/cable including but not limited to Kapton, Tefzel and Teflon insulated wires and cables. It must be capable of marking white SAE J-1128 wire (8, 10, 12, 14 and 18 AWG) to meet Mil Spec MIL-W-5088, SAE AS50881 and SAE ARP5607.

3.3 Marking: The marking machine shall be able capable of marking in a variety of font styles and sizes depending on wire/cable size. Marking shall be adjustable to read horizontally from left to right or vertically from top to bottom using a variety of fonts. Fonts shall include but not be limited to Sans Serif, Ariel, Univers and Tahoma.

3.4 Speed – The marking machine shall capable of marking up to 100 feet per minute depending on font size.

3.5 Print/Images – The marking machine shall be capable of printing alpha numeric characters and bar codes.

3.6 Control The marking machine shall have a self-contained internal operating system such that an external PC is not required. It shall operate on Windows based software Windows Vista (or newer). It shall include the necessary software for flexible setup for production marking on wire/cable.

3.7 Accessories The vendor shall provide the following accessories as a minimum:

- Interface – The marking machine shall include all interfaces, cables, encoders and etc that are necessary to provide it as a fully functional system integrated with the Schleuniger PS9550 automatic cut and strip system

- Wire Guides & Straighteners – Provide the necessary wire guides and straighteners to allow the marking machine to function with the automated cut & strip machine.

- Equipment Stand/Rack with drawers and locking casters

3.8 Machine Size: The marking machine shall not require a foot print greater than 3’ by 3’. It is acceptable to provide the equipment in a disassembled condition but the government will not assemble the equipment. This will be considered part of the contractor’s installation.

3.9 Utilities

The wire marking machine shall operate on 120 VAC, single phase, 60 cycle power. The necessary power required and the amperes shall be stated in the proposal. The marking machine shall rely on regular shop air if it has a compressed air requirement. Shop air is approximately

90-100 PSI.

4. Safety

The marking machine shall meet all requirements set forth in OSHA General Industry Standards 29 CFR 1910, dated 1 July 1996. In addition it shall meet or exceed the National Fire Protection Association (NFPA) requirements of NFPA 79-1994, "Electrical Standards for Industrial Machinery." All energy control sources shall have the capability of being locked out and tagged out. The contractor's manuals shall detail the lockout/tagout procedures which are required to bring the marking machine to a zero mechanical state for maintenance or service procedures. Procedures to return from the zero mechanical state to full operational capability shall also be provided.

5. Documentation

The contractor shall provide two sets of commercial manuals with the marking machine.

This documentation shall be provided at the same time as the machine delivery.

6. Training

Training shall begin within 10 working days of installation, set-up, and successful acceptance testing of the marking machine. The contractor shall provide training for a maximum of 3 shop personnel and 2 Engineering personnel in the proper set-up, operation, and calibration of the equipment. The contractor shall also provide instruction on the proper preventative maintenance and troubleshooting techniques for the UV laser marking machine. Instruction shall be performed at the Depot during normal Depot working hours (Monday thru Friday 7:30 AM to 4:00 PM) excluding Federal Holidays. The start-up and instruction shall be structured to be completed within two days (sixteen hours) and have sufficient time for a question and answer session. Training will take place after installation and acceptance testing but prior to final acceptance by the Contracting Officer (KO) or her Representative (COR). The contractor shall supply all training materials necessary to complete the training requirement.

7. Delivery

a. Delivery of the marking machine shall be within 90 days of contract award.

Installation shall be performed by the contractor not later than 15 days after delivery of the equipment and shall be completed within 5 days of start date. Acceptance testing shall be performed not later than 15 days after installation.

b. Training shall be completed not later than 10 days after Acceptance testing.

c. Contractor shall coordinate delivery with the Contracting Officer, to include a pre-delivery notification at least 10 days prior to shipment of equipment.

8. Installation

Installation responsibilities shall be shared between the Government and the contractor. The Government shall unload the equipment from the truck, move it to the shop area, rough level the equipment, and connect the utilities (electricity and compressed air). The contractor shall then complete any incidental installation processes in order to place the laser marking system into service and ready for demonstration/acceptance testing. All installation procedures shall be coordinated with the Contracting Officer (KO) or the Contracting Officer's Representative (COR). All installation shall be performed by English speaking U.S. citizens. All work shall be performed during normal working hours: Monday through Friday from 7:30 am to 4:00 pm Eastern Standard Time, excluding Federal Holidays, unless special arrangements are made with the KO or COR.

9. Acceptance Testing

Operational Acceptance Testing for the marking machine shall be performed following installation of the machine at Tobyhanna Army Depot and prior to training. Acceptance Testing will consist of the Contractor's technical representative demonstrating the ability to perform to the standard specified in the Requirements section of this specification. The material to be used for the Acceptance Testing shall be provided by the Government. In the event that the machine fails the acceptance test or fails to comply with any other aspect of this specification, the Contractor shall correct any deficiencies within 15 working days of the acceptance test, at which time the machine will be retested for compliance. It shall be at the discretion of the Contracting Officer as to whether all, part, or none of the acceptance test procedure shall be performed again.

For the purpose of re-testing required due to the failure of the system to pass the initial testing, it shall be the responsibility of the Contractor to provide the material required for any re-testing, inclusive of any shipping costs, and such material shall be per the specification provided by the

Government.

10. Warranty

The equipment furnished under this specification shall be warranted for parts and labor for a period of 1 year from the date of final acceptance. IN THE CASE OF ANY COMPONENTS OR

SUBSYSTEMS WHICH COME WITH A WARRANTY FROM THE MANUFACTURE

THAT IS LONGER THAN A YEAR, THAT WARRANTY WILL BE PROVIDED TO THE

GOVERNMENT WITH THE OTHER REUQIRED DOCUMENTATION. THE EXISTANCE

OF WARRANTIES FOR COMPONENTS OR SUBSYSTEMS WHICH HAVE A DURATION

OF LONGER THAN ONE YEAR IN NO WAY NEGATES OR DIMINISHES THE

RESPONSIBILITY OF THE CONTRACTOR FOR PROVIDING WARRANTY OF THOSE

COMPONENTS OR SUBSYSTEMS FOR A PERIOD OF ONE YEAR AFTER THE DATE OF

FINAL ACCEPTANCE. There shall be single contractor accountability to prevent confusion of responsibility if a problem or breakdown occurs.

DEPOT ACCESS:

A background check and approval from TYAD Security Branch is required for all contractor and subcontractor personnel prior to on-site access at TYAD. All persons seeking entrance to TYAD shall submit to and comply with all security standards and requirements in force at the time such persons are seeking entry. All contractors, regardless of resident status or citizenship, will be subject to vehicle search and intense in-processing by TYAD security personnel prior to being granted access to TYAD. This security screening process may be time consuming and access may be delayed or denied. The contractor shall ensure ELTY Form 648-C is completed for all contractor and subcontractor personnel requiring depot access to include warranty services. The TYAD point of contact (POC) will provide ELTY Form 648-C, Request Access to Tobyhanna Army Depot, to the contractor/vendor at least ten days prior to the expected visit date for completion. The contractor/vendor shall return the completed ELTY Form 648-C to the TYAD POC in a timely manner so the same may be submitted to Security for processing no later than seven days prior to the visit. All of the required fields on the form shall be complete and accurate by the contractor/vendor for timely processing. This requirement is inclusive of on-site supervisory or managerial personnel and sub-contractor personnel that the Contractor anticipates will be performing work or visiting on-site. This security screening does not relieve the contractor of any responsibilities to conduct thorough pre-employment background checks and drug screening. Contractor workers will not be granted access to the work site until security screening is completed and access is approved. Any contractor personnel on-site who fail screening will not be permitted further access to TYAD. See “Access and General Protection/Security Policy and Procedures” below.

Please submit the completed ELTY Forms 648-C form(s) to the COR or POC.

SECURITY REQUIREMENTS

ANTITERRORISM (AT) / OPERATIONS SECURITY (OPSEC) REQUIREMENTS

All security training certificates shall be provided to the Contracting Officer’s Representative (COR)/Point of Contact (POC) and the Contract Specialist/Purchasing Agent.

Antiterrorism (AT) Level I Training. All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities, and controlled access areas shall complete AT Level I awareness training prior to contract report date. This training is required for any additional or new contractor employees, who start after that period. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR/POC within 10 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: https://jkodirect.jten.mil for CAC holders. Non-CAC holders may go to http://jko.jten.mil/courses/atl1/launch.html for their training. Upon request, the contractor will be provided one copy of the AT level I training slides for use with employees who may not have computer access. TYAD will not be responsible for printing copies of slides for training purposes. TYAD reserves the right to provide instructor led training and will so advise the contractor within one week of the start of performance or at the time of annual training, if that will be the training approach to be utilized. Completion of contractor employee training will be documented on ELTY form 583, TYAD On-Post Training Record, or contractor equivalent. As applicable, contractor employees must complete annual AT awareness training as it pertains the length of the contract.

iWATCH Army Training. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH Army Program. This will consist of utilizing the tools and media products on the informational iWATCH Army website to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR/POC.

The iWATCH training is available at the following website: https://myarmyonesource.com select Family Programs and Services, in the drop down boxes select: Go To, iWATCH Army – “See Something, Say Something”. Additional guidance and support can be provided by the TYAD Antiterrorism Officer (ATO) at the contractor’s request. The contractor shall notify the COR/POC within 10 calendar days of the completed training for any new employees or subcontractor personnel to assure the ELTY form 583 or contractor equivalent is properly documented. TYAD reserves the right to provide instructor led training and will so advise the contractor within one week of the start of performance or at the time of annual training, if that will be the training approach to be utilized. Completion of contractor employee training will be documented on ELTY form 583, TYAD On-Post Training Record or contractor equivalent.

Operations Security (OPSEC) Training. Per AR 530-1, Operations Security, contractor employees must complete Level I OPSEC training prior to the contract report date and for any additional or new contractor employees, who start after that period. All contractor employees must also complete annual OPSEC awareness training available at the following website:

http://cdsetrain.dtic.mil/opsec/index.htm The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR/POC within 10 calendar days after completion of training by all employees and subcontractor personnel. The contractor will be provided a copy of the OPSEC training slides for use with employees who may not have computer access. TYAD will not be responsible for printing copies of slides for training purposes. TYAD reserves the right to provide instructor led training and will so advise the contractor within one week of the start of performance or at the time of annual training, if that will be the training approach to be utilized. Completion of contractor employee training will be documented on ELTY form 583, TYAD On-Post Training Record or contractor equivalent.

Access and General Protection/Security Policy and Procedures. Contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by TYAD Security Branch. Contractor workforce must comply with all personal identity verification requirements as directed by DoD, HQDA, and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection

Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190- 13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by the government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

DEPOT ACCESS:

A background check and approval from TYAD Security Operations Branch is required for all contractor and subcontractor personnel prior to on-site access at TYAD. All persons seeking entrance to TYAD shall submit to and comply with all security standards and requirements in force at the time such persons are seeking entry. All contractors, regardless of resident status or citizenship, will be subject to vehicle search and intense in-processing by TYAD security personnel prior to being granted access to TYAD.

This security screening process may be time consuming and access may be delayed or denied. The contractor shall ensure ELTY Form 648-C is completed for all contractor and subcontractor personnel requiring depot access to include warranty services. The TYAD point of contact (POC) will provide ELTY Form 648-C, Request Access to Tobyhanna Army Depot, to the contractor/vendor at least ten days prior to the expected visit date for completion. The contractor/vendor shall return the completed ELTY Form 648-C to the TYAD POC in a timely manner so the same may be submitted to Security for processing no later than seven days prior to the visit. All of the required fields on the form shall be complete and accurate by the contractor/vendor for timely processing. This requirement is inclusive of on-site supervisory or managerial personnel and sub-contractor personnel that the Contractor anticipates will be performing work or visiting on-site. This security screening does not relieve the contractor of any responsibilities to conduct thorough pre-employment background checks and drug screening. Contractor workers will not be granted access to the work site until security screening is completed and access is approved. Any contractor personnel on-site who fail screening will not be permitted further access to TYAD. See “Access and General Protection/Security Policy and Procedures” below.

Please submit the completed ELTY Forms 648-C form(s) to the COR or POC.

SECURITY REQUIREMENTS

ANTITERRORISM (AT) / OPERATIONS SECURITY (OPSEC) REQUIREMENTS

All security training certificates shall be provided to the Contracting Officer’s Representative (COR)/Point of Contact (POC) and the Contract Specialist/Purchasing Agent.

Antiterrorism (AT) Level I Training. All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities, and controlled access areas shall complete AT Level I awareness training prior to contract report date. This training is required for any additional or new contractor employees, who start after that period. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR/POC within 10 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: https://jkodirect.jten.mil for CAC holders. Non-CAC holders may go to http://jko.jten.mil/courses/atl1/launch.html for their training. Upon request, the contractor will be provided one copy of the AT level I training slides for use with employees who may not have computer access. TYAD will not be responsible for printing copies of slides for training purposes. TYAD reserves the right to provide instructor led training and will so advise the contractor within one week of the start of performance or at the time of annual training, if that will be the training approach to be utilized.

Completion of contractor employee training will be documented on ELTY form 583, TYAD On-Post Training Record, or contractor equivalent. As applicable, contractor employees must complete annual AT awareness training as it pertains the length of the contract.

iWATCH Army Training. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH Army Program. This will consist of utilizing the tools and media products on the informational iWATCH Army website to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. The iWATCH training is available at the following website: https://myarmyonesource.com select Family Programs and Services, in the drop down boxes select: Go To, iWATCH Army –“See Something, Say Something”. Additional guidance and support can be provided by the TYAD Antiterrorism Officer (ATO) at the contractor’s request. The contractor shall notify the COR/POC within 10 calendar days of the completed training for any new employees or subcontractor personnel to assure the ELTY form 583 or contractor equivalent is properly documented.

TYAD reserves the right to provide instructor led training and will so advise the contractor within one week of the start of performance or at the time of annual training, if that will be the training approach to be utilized. Completion of contractor employee training will be documented on ELTY form 583, TYAD On- Post Training Record or contractor equivalent.

Operations Security (OPSEC) Training. Per AR 530-1, Operations Security, contractor employees must complete Level I OPSEC training prior to the contract report date and for any additional or new contractor employees, who start after that period. All contractor employees must also complete annual OPSEC awareness training. The training is available at the following website: http://cdsetrain.dtic.mil/opsec/index.htm.

The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR/POC within 10 calendar days after completion of training by all employees and subcontractor personnel. The contractor will be provided a copy of the OPSEC training slides for use with employees who may not have computer access. TYAD will not be responsible for printing copies of slides for training purposes. TYAD reserves the right to provide instructor led training and will so advise the contractor within one week of the start of performance or at the time of annual training, if that will be the training approach to be utilized. Completion of contractor employee training will be documented on ELTY form 583, TYAD On-Post Training Record or contractor equivalent.

Access and General Protection/Security Policy and Procedures. Contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by TYAD Security Branch. Contractor workforce must comply with all personal identity verification requirements as directed by DoD, HQDA, and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by the government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

File details come from the government source that posted it. Updated .