This Justification Approval (J A) is for Maintenance Repair and Operation (MRO) Northwest Region and is being posted as required by FAR 6.302-1. The J A is attached to this notice.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MRO NORTHWEST REGION Page 1 of 5

JUSTIFICATION FOR OTHER THAN FULL AND OPEN COMPETITION

SCIENCE APPLICATIONS INTERNATIONAL CORPORATION

NORTHWEST REGION

MAINTENANCE, REPAIR, AND OPERATIONS (MRO) PROGRAIW

1. Defense Logistics Agency (DLA) Troop Support, Construction and Equipment Supply Chain, is the contracting activity.

2. The action being approved is the ability to solicit for DLA requirements on an other than full and open competition basis.

3. The proposed acquisition is for a bridge contract for a period of 121 days to provide for the purchasing of facilities Maintenance, Repair and Operations (MRO) supplies and associated incidental services. The Tailored Logistics Support Prime Vendor (TLS PV) contract provides for MRO materials and other supplies including, but not limited to: Heating, Ventilation and Air Conditioning (HVAC); plumbing supplies (including bath and shower items); electrical products (including generators, wire, connectors, sockets, outlets, lights, etc.); tools of various kinds;

chemical, lubricating, and rubber products and products including same; construction supplies (including but not limited to cement, lumber and plywood, bricks, blocks, steel, aluminum, and other metal products, conduits, prefabricated structures, etc.); perimeter security items such as barriers, barbed wire, concertina wire, and sand bags (also used for erosion prevention);

communication devices (such as walkie-talkies, two-way radios, etc. used by maintenance persom1el); and various other MRO supplies needed by war-fighters stationed in the Northwest Region of the United States. The maximum dollar value, based on current sales data including an additional $5.25 million added for surge requirements, for this proposed contract is $10.5 million for the period of 121 days. The original contract, SPM500-04-D-BP15, was awarded to Science Applications International Corporation (SAIC) on May 19, 2004 to support military customers with MRO requirements in the Northwest Region. The contract was issued with a two (2) year base period and eight (8) one-year options, and also included an implementation period of 90 days. The contract is currently in the eighth and final option year and is due to expire on August 17, 2014. This action will be the first bridge contract for this region with an effective period of August 18, 2014 through December 17, 2014. If a competitively awarded contract is issued ahead of the projected timeframe and the contract guaranteed minimum of $50,000.00 is satisfied, delivery orders will no longer be placed under this (c)(l) bridge contract.

4. The statutory authority pel'lllitting other than full and open competition is 10 U.S.C. 2304(c)(l), as implemented by FAR 6.302-1, Only One Responsible Source and No Other Supplies or Services Will Satisfy Agency Requirements.

5. Contract SPM500-04-D-BP15 is the only contract supp01ting the Northwest Region under the existing MRO Program. This contract is critical to maintaining continuity of support for war-fighters stationed in the Northwest Region. The requisite MRO products and associated incidental services are deemed to be available only from the current contractor, SAIC, in the required tinle-frame. Award to any other source would result in unacceptable delays in fulfilling the Agency's requirements.

MRO NORTHWEST REGION Page 2 of5

The Northwest Region contract is one of fourteen contracts which operate alike under the MRO TLS PV Program. The first three follow-on solicitations (MRO Japan, Korea and Southeast) were to be a template for the North Central Region follow-on solicitation.

Based upon the foregoing reasons, including additional market research conducted and customer feedback, the Agency reconsidered this determination and decided that it is necessary to provide for the incidental service requirements. This revised acquisition strategy was necessary to meet mission requirements and customer needs.

Additional market research was conducted and confomed that the MRO TLS Prime Vendor Program is in line with commercial industry buying practices.

MRO NORTHWEST REGION Page3of5

Following approval of the acquisition strategy change, the MRO Northwest solicitation was synopsized and issued on July 14, 2014 with a closing date of August 18, 2014.

This proposed bridge contract is required to allow for the Source Selection Evaluation Board (SSEB) to evaluate the offers, pricing evaluations, negotiations, reverse auction, final evaluations, preparation of award documents, contract review and approval, as well as to provide contract coverage during the thi1iy (30) day "ramp up" or transition period. Full contract implementation is expected by December 17, 2014.

It is essential that DLA Troop Suppo1i maintain the ability to purchase MRO supplies and associated incidental services, in the period from August 18, 2014 through December 17, 2014.

This proposed bridge contract will ensure continuous contract coverage providing for an uninterrupted supply of vitally needed MRO supplies and incidental services throughout the No1ihwest Region. If this bridge contract is not awarded and coverage lapses, DoD and DLA' s ability to provide much-needed supplies will be significantly impaired in as much as the traditional DLA supply system could not support the volume of individual orders that are processed through the MRO program. SAIC is the only established firm capable of providing continued support for these vital MRO items in the No1ihwest Region while the follow-on competitive acquisition is being completed.

A new contractor would require at least a thirty (30) day

"ramp-up" period to form relationships with local suppliers and manufacturers located in the Northwest Region, identify potential delivery service and transportation requirements, establish adequate purchasing, distribution and quality control systems, hire local customer support representatives, and implement systems that would interface with DLA Troop Support.

6. This requirement will be synopsized in FedBizOpps as required by FAR Subpart 5.2. In addition, this justification will be made available for public inspection after award, in accordance with FAR 6.305.

7. As the Contracting Officer, I hereby dete1mine that the anticipated cost to the Government will be fair and reasonable based on price analysis, including comparison to

MRO NORTHWEST REGION Page 4 of 5 available commercial pricing, General Services Administration (GSA) pricing, and other Government contracts.

8. The requirement for this bridge contract will be synopsized. No other firms will be solicited since the required supplies and services are only available from the incumbent contractor in the required timeframe.

9. Considering the high volume of demands cmTently being experienced and the ability to reduce the logistics response time, the current contract with SAIC is required to support customer requirements until a follow-on initiative is competitively awarded. The current contract with SAIC allows DLA Troop Support to support the No1thwest Region by reducing customer wait time, improving logistics response time, managing suppliers rather than managing supplies, avoiding depot operation costs for managing, storing, shipping, handling, and transporting MRO materials, and improving product availability.

10. SAIC is the only established source to express an interest in this bridge contract.

11. The proposed bridge covers the Northwest Region. The solicitation for the follow-on initiative was solicited on a full and open competition basis on July 14, 2014 and future solicitations are expected to he issued competitively. The award of the follow-on contract is expected by November 17, 2014.

12. As the Contracting Officer, I hereby cettify that this justification is accurate and complete to the best of my knowledge and belief.

Contracting Officer

I hereby certify that the requirements which form the basis of this justification are accurate, that these supplies and incidental services meet the Government's needs in accordance with applicable specifications and that this justification is accurate and com lete to the best of my knowledge and belief.

d3-:S:t c201t.{

DATE

I have reviewed this justification and recommend approval.

CHET EV ANITSKY

MRO Division Chief

I have reviewed this justification and recommend approval.

iVffiO NORTHWEST REGION

7 (.:i '{I I'(

DATE RALPH LUND

Director of Supplier Operations Construction & Equipment

I have reviewed this justification and recommend approval.

DA: E

LA Troop Support Competition Advocate

I have reviewed this justification for legal sufficiency.

S pply Chain Counsel DLA Counsel - Troop Support

I have reviewed and hereby approve this justification.

Executive Director DLA Troop Support Contracting and Acquisition Management