Amendment_0005.pdf

PDF 64 KB Posted

Attached to
Removal and Replace Make Up Air Units for DDJC Federal contract opportunity
Solicitation number
SP3300-16-B-0015
Issued by
Defense Logistics Agency Distribution

About this file

Amendment 0005

View the file

Other files for this federal contract opportunity

Other files attached to Removal and Replace Make Up Air Units for DDJC, newest first.
File Type Posted
Tab_E-17_Public_Notice_of_Award.pdf PDF
Bid_Results_-_SP330016B0015.pdf PDF
16B0015_SF30_AMENDMENT_0005.pdf PDF
Amendment_0004.pdf PDF
Amendment_0003.pdf PDF
Attachment_12_Site_Visit_List.pdf PDF
Amendment_0002.pdf PDF
16B0015AMDP0001_PG_2.pdf PDF
16B0015AMDP0001_PG_2.pdf PDF
Attachment_10_SF25A_Payment_Bond.pdf PDF
Attachment_8_SF24_-_Bid_Bond.pdf PDF
Solicitation.pdf PDF
Attachment_7_Davis_Bacon.pdf PDF
Attachment_11_Standard_Form_1442.pdf PDF
Attachment_2_Site_Map.pdf PDF
Attachment_6_Transmittal_of_Shop_Drawings.pdf PDF
Attachment_5_Submittal_Reg.pdf PDF
Attachment_9_SF25_(Performance_Bond).pdf PDF
Attachment_3_Drawing_and_Photos.pdf PDF
Attachment_4_Schedule_of_Supplies.pdf PDF
Attachment_1_SoW _Gen_Specs _and_Checklists.pdf PDF
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SP3300-16-B-0015

AMD 0005

I. The purpose of this amendment is to answer vendor questions.

II. The following vendor questions are answered.

Question 1: There is currently a new Duro-Last roof being installed on Warehouse 28. Could the DLA please advise who the roofing contractor is?

Answer 1: Subcontractor: Cool Roofing Owner: Jamie Billman (Jamie.Billman@cool-roofing.com)

(209) 456-3967 PM/Marketing - Craig Marker (craig@cool-roofing.com)

(209) 815-2225

Question 2: Does the Honeywell controller at each MAU communicate with the fire alarm control panel (FACP) by giving the FACP dry contact inputs for each alarm or does it send alarms to a Honeywell FACP via a data connection like RS-485?

Answer 2: Existing FACP is wired in a loop with all smoke detectors, air flow switches and filter pressure differential switches of all the MAUs tied in one single loop. Existing FACP is an addressable system. New PIDs will be required for all new smoke detectors, air flow switches and filter pressure differential switches. Contractor can use existing twisted pair connecting these devices to FACP. Each Honeywell thermostat communicates with its MAU control panel separately to control hot water valve and evap cooler. Contractor can use existing wires connecting thermostat and MAU control panel. Contractor must field verify all information.

Govt. shall not be responsible for any discrepancies found later on.

Question 3: I do not see any weight commentary. The notes say to match existing curb but nothing about weight. Also the typical drawing of MAU unit on drawing number 03 does not show the evaporative cooling section. Which enhances the weight concerns.

Answer 3: All existing units have evap cooling section. All new units shall have evap cooling section.

Question 4: The new request is for four inch wall construction. Was that the construction of the original units?

Answer 4: Contractor can field verify.

Question 5: Did the existing units have evaporative cooling?

Answer 5: Yes

Question 6: Is there a weight limit on these units.

Answer 6: All existing units are 2000 Kg other than MAU 4B which is 1500 Kg

SP3300-16-B-0015

AMD 0005

III. Question 23 of Amendment 0004 is hereby corrected to read as follows.

Question 23: Can we request post pone of bid date? Need some more time please.

Answer: The Bid Close date is scheduled for September 6th, 2016. Due to the end of the fiscal year, the bid close date cannot be extended at this time.

IV. No further questions will be answered for this solicitation.

V. All other terms and conditions remain unchanged.