SP3300-15-R-0013
Amendment 0002
1. The purpose of Amendment 0002 is to answer questions pertaining to the solicitation, revise the solicitation and statement of work, add Davis-Bacon Act provisions, and add a drawing. The following changes are made:
a. Provide the Government response to Contractor questions pertaining to the Statement of Work.
Contractor Submitted Question Government Response Question 1:
Will Davis-Bacon wage determination be used for this solicitation?
Response 1:
Davis-Bacon wage determination will be applicable for electrical work.
Question 2:
Will all new VLM’s need to be fully operational and tested prior to the start of the demolition phase of the project?
Response 2:
Yes. CLIN 0002 states the 90 day performance period begins 180 days after the acceptance of the new VLM system.
Question 3:
Can dumpsters be placed along the dock on the side of the building for tear out? If not, where?
Response 3:
No, due to fire department regulations.
Dumpsters can be placed near the North side of the building, and can be accessed by driving down the dock and down the ramp.
Exact placement will be coordinated through the COR at the start of the demolition phase of the contract.
Question 4:
Will propane lift equipment be allowed?
Response 4:
Yes.
Question 5:
Will the site of the new installation (Bay 4) be completely cleared out prior to the start of installation so that new equipment staging can use this location?
Response 5:
The area depicted for the VLM’s permanent location will be available to the contractor for staging.
Question 6:
How long is it going to take DDAG personnel to move the contents from the existing VLM’s to the new VLM’s?
Response 6:
One hundred and eighty days are scheduled following the acceptance of the VLM system.
Question 7:
If this process slows down the demolition phase of the project, will the contract time period be extended so as not to incur any financial penalties?
Response 7:
The contractor will not be financially penalized if the Government requests to delay the equipment demolition phase.
Question 8:
Will the contractor have complete access to the existing VLM’s for demolition from 0600 to 1800 Monday – Friday?
Response 8:
Yes, except holidays.
SP3300-15-R-0013
Amendment 0002
Question 9:
Based on the statements made in paragraph 3.1, is it correct that the government is seeking the manufacturers “current commercially available” model that best fits the specifications for both capacity and velocity?
Response 9:
All equipment (each whole product with its integral software) shall be the manufacturer’s current, commercially designed and available or a commercial product that has been slightly modified to fit the proposed system.
Question 10:
Paragraph 3.2.2.4 states that tray is delivered automatically to the external access delivery point. Was it not stated during the round table discussion, at the site visit, that the word “external” would be removed and replaced by “delivery to the access point”?
Response 10:
Paragraph 3.2.2.4 is revised. “Once the user has completed the actions required in the first tray, the second tray is delivered automatically to the access delivery point while the VLM dynamically returns the first tray to its first available stored position.”
Question 11:
Must we offer a bid on all line items or can we no bid certain items 0003 & 0004?
Response 11:
Contractor’s must bid/price Contract Line Items 0001, 0002, 0003, 0004, 0005. All or none.
Question 12:
Are Drawing and Dimensions available?
Response 12:
Yes, a Drawing was an attachment to the original solicitation. A PDF drawing is also included in this amendment.
Question 13:
Are we (Offerors/Contractors) to install Ethernet cable?
Response 13:
Yes, the offerors are required to install the Ethernet cable (for future networked capability).
b. Replace in its entirety the SF 1449, SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS CONTINUATION SHEET with pages 2 – 40, attached hereto as Attachment 1. (Note: See right margin line-draw for revision locations.)
c. Replace in its entirety the STATEMENT OF WORK with pages 1 – 27, attached hereto as Attachment 2. (Note: See right margin line-draw for revision locations.)
d. Add the Davis-Bacon Act Wage Determination to the list of attachments, attached hereto as Attachment 3.
e. Add the PDF Drawing to the list of attachments, attached hereto as Attachment 4.
2. All other terms and conditions remain unchanged.
END OF AMENDMENT 0002