SOW_Temp Chillers 2021.pdf
PDF 164 KB Posted
- Solicitation number
- W911SD-21-R-0062
About this file
This scope of work document outlines requirements for six temporary trailer-mounted chillers to be installed at various buildings on the West Point military base from May to October 2021. Contractors must supply chillers ranging from 100 to 400 tons, along with necessary pumps, piping, electrical work, installation, and maintenance. Specific requirements are listed for each of the six chiller locations, including building information, equipment specifications, and completion deadlines. The related sources sought notice seeks information from small businesses interested in providing the six chillers on a set-aside contract. Respondents are asked to provide company and certification details, past experience, commercially available pricing for the chillers, and recommendations to improve the acquisition approach. The requirement is for the Army Materiel Command for temporary chillers at West Point from May 2021 through October 2021.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DPW, CONSTRUCTION, ESTIMATING & CONTRACT SERVICES BRANCH
4th Floor Bldg. 667A
West Point N.Y. 10996
Subject: Scope of Work Contract name: Temporary Chillers - Summer 2021
IJO: CH 21150 1J
Project Location: Bldgs. 602, 735, 745C, 745D, 751 and 753.
Date: 8 Feb 2020
Scope:
Contractor to provide all labor, material, equipment, and supervision in accordance with all applicable codes and specifications to the following locations at USMA West Point, NY 10996:
1) Supply, install, and test operate one 200 ton trailer mounted air cooled chiller with pumps and 500 KVA transformer at Bldg. 745D, Mac Long Barracks.
2) Supply, install, and test operate one 200 ton trailer mounted air cooled chiller with pumps at Bldg. 602, Grant Barracks.
3) Supply, install, and test operate one 400 ton trailer mounted air cooled chiller with pumps at Bldg. 745C, Eisenhower Barracks.
4) Supply, install, and test operate one 100-150 ton trailer mounted air cooled chiller with pumps at Bldg. 751, Pershing Barracks.
5) Supply, install, and test operate one 400 ton trailer mounted air cooled chiller with pumps at Bldg. 735, Scott Barracks.
6) Supply, install, and test operate two 200 ton trailer mounted air cooled chiller with pumps and 750 KVA transformer at Bldg. 753, Bartlett Hall parking tunnel.
All chillers shall be installed and fully operational from May 15th 2021 to October 15, 2021.
Description of Work:
Contractor shall install, inspect, and test the installation and operation of the trailer mounted chillers no later than May 15th for start of full operational service. On October 15th, that contractor disconnect and remove the temporary chillers and all associated material and equipment.
1) Supply and install one 200 ton chiller with pumps at Bldg. 745D, Mac Long Barracks and have all associated work needed for installation completed and the chiller ready and in operation by May 15th. The existing building power and disconnect is 230/460 VAC. Supply transformer to supply power to the chiller unit. The contractor will be responsible to tap existing 13-8 line and run cables from existing manhole and open conduit path to chiller location and connect to the supplied 500 KVA transformer. Install approximately 200’ ft. of 6” in. rubber hose with connection ends to attach chiller to building 745 piping. Supply and install all pipe fittings as necessary for a complete installation. Supply and install all temporary electrical cable and appurtenances needed to connect chiller to the supplied transformer. The proposed site location and attachment locations (electrical disconnect, piping, etc.) to existing building systems will be shown at pre-bid site visit. The contractor shall have a qualified HVAC subcontractor at the pre-bid site visit to review this location and determine the exact details (specific location, attachment details, piping / cable length etc.). The contractor shall have a qualified high voltage electrical company do the transformer cabling, connections, and supply a fiberglass pad for the transformer. All taps and cable connections to the transformer will be done by other personnel.
The government PM will be notified when new cabling is ready to be connected and PM will then notify Electric shop for terminations.
2) Supply and install one 100-150 ton chiller with pumps at Bldg. 751, Pershing Barracks and have all associated work needed for installation completed and the chiller ready and in operation by May 15th. The existing building power and disconnect is 230/460 VAC. Supply chiller to match existing power and or if required supply and install transformer to use with temporary chiller and house power. Install 6” in. rubber hose with connection ends to attach chiller to building 753 piping. Supply and install all pipe fittings as necessary for a complete installation.
Supply and install all temporary electrical cable and appurtenances needed to connect chiller to the supplied transformer. The proposed site location and attachment locations (electrical disconnect, piping, etc.) to existing building systems will be shown at pre-bid site visit. The contractor shall have a qualified HVAC subcontractor at the pre-bid site visit to review this location and determine the exact details (specific location, attachment details, piping/cable length etc.). The contractor shall have a qualified high voltage electrical company do the transformer cabling, connections, and supply a fiberglass pad for the transformer. All taps and cable connections to the transformer will be done by other personnel. The government PM will be notified when new cabling is ready to be connected and PM will then notify Electric shop for terminations.
3) Supply and install one 200 ton chiller with pumps at Bldg. 602, Grant Barracks and have all associated work needed for installation completed and the chiller ready and in operation by May 15th. The existing building power and disconnect is 230/460 VAC. Supply chiller to match existing power and or if required supply and install transformer to use with temporary chiller and house power. Install 6” in. rubber hose with connection ends to attach chiller to building piping.
Supply and install all pipe fittings as necessary for a complete installation. Supply and install all temporary electrical cable and appurtenances needed to connect chiller to the supplied transformer. The proposed site location and attachment locations (electrical disconnect, piping, etc.) to existing building systems will be shown at pre-bid site visit. The contractor shall have a qualified HVAC subcontractor at the pre-bid site visit to review this location and determine the exact details (specific location, attachment details, piping/cable length etc.). The contractor shall have a qualified high voltage electrical company do the transformer cabling, connections, and supply a fiberglass pad for the transformer. All taps and cable connections to the transformer will be done by other personnel. The government PM will be notified when new cabling is ready to be connected and PM will then notify Electric shop for terminations.
4) Supply and install one 400 ton chiller with pumps at Bldg. 735, Scott Barracks and have all associated work needed for installation completed and the chiller ready and in operation by May
15th. The existing building power and disconnect is 230/460 VAC. Supply chiller to match existing power and or if required supply and install transformer to use with temporary chiller and house power. Install 6” in. rubber hose with connection ends to attach chiller to building piping.
Supply and install all pipe fittings as necessary for a complete installation. Supply and install all temporary electrical cable and appurtenances needed to connect chiller to the supplied transformer. The proposed site location and attachment locations (electrical disconnect, piping, etc.) to existing building systems will be shown at pre-bid site visit. The contractor shall have a qualified HVAC subcontractor at the pre-bid site visit to review this location and determine the exact details (specific location, attachment details, piping/cable length etc.). The contractor shall have a qualified high voltage electrical company do the transformer cabling, connections, and supply a fiberglass pad for the transformer. All taps and cable connections to the transformer will be done by other personnel. The government PM will be notified when new cabling is ready to be connected and PM will then notify Electric shop for terminations.
5) Supply and install one 400 ton chiller with pumps at Bldg. 745C, Eisenhower Barracks and have all associated work needed for installation completed and the chiller ready and in operation by May 15th. The existing building power and disconnect is 230/460 VAC. Supply chiller to match existing power and or if required supply and install transformer to use with temporary chiller and house power. Install 6” in. rubber hose with connection ends to attach chiller to building piping. Supply and install all pipe fittings as necessary for a complete installation.
Supply and install all temporary electrical cable and appurtenances needed to connect chiller to the supplied transformer. The proposed site location and attachment locations (electrical disconnect, piping, etc.) to existing building systems will be shown at pre-bid site visit. The contractor shall have a qualified HVAC subcontractor at the pre-bid site visit to review this location and determine the exact details (specific location, attachment details, piping/cable length etc.). The contractor shall have a qualified high voltage electrical company do the transformer cabling, connections, and supply a fiberglass pad for the transformer. All taps and cable connections to the transformer will be done by other personnel. The government PM will be notified when new cabling is ready to be connected and PM will then notify Electric shop for terminations.
6) Supply and install two 200 ton chiller with pumps at Bldg. 753, Bartlett Hall/parking tunnel and have all associated work needed for installation completed and the chiller ready and in operation by May 15th. The existing building power and disconnect is 230/460 VAC. Supply transformer to supply power to the chiller unit. The contractor will be responsible to tap existing 13-8 line and run cables from existing manhole and open conduit path to chiller location and connect to the supplied 750 KVA transformer. Install approximately 200’ ft. of 6” in. rubber hose with connection ends to attach chiller to building 745 piping. Supply and install all pipe fittings as necessary for a complete installation. Supply and install all temporary electrical cable and appurtenances needed to connect chiller to the supplied transformer. The proposed site location and attachment locations (electrical disconnect, piping, etc.) to existing building systems will be shown at pre-bid site visit. The contractor shall have a qualified HVAC subcontractor at the pre-bid site visit to review this location and determine the exact details (specific location, attachment details, piping / cable length etc.). The contractor shall have a qualified high voltage electrical company do the transformer cabling, connections, and supply a fiberglass pad for the transformer. All taps and cable connections to the transformer will be done by other personnel.
The government PM will be notified when new cabling is ready to be connected and PM will then notify Electric shop for terminations.
7) Supply all labor and materials required to disconnect existing building piping for temporary chiller hook-up. Supply all labor and materials required to reconnect all piping after temporary chillers are removed. All existing system components, electrical connections, structures, roadways, etc. shall be returned to their original existing conditions upon completion of this work for acceptable closing.
Specific Requirements:
a) All work shall performed in accordance with applicable federal, state, local, and USMA requirements laws and regulations.
b) Supply material needed to support temporary chillers at site locations. Plywood, boards, chalks, etc. shall be installed under and chalked around tires and front trailer supports to protect the surface underneath chiller trailer.
c) Remove building louvers as necessary to run piping and electrical cables into building.
Install temporary enclosures around temporary piping to cover the opening where louvers were removed.
d) Use hard rubber piping to connect chiller to building connections.
e) Supply all supervision, labor, equipment, and materials needed for installation and removal of temporary chillers.
f) Supply and install the automatic “red” high capacity air bleeder for normal operations on each chiller unit. Supply the following brand: Bell & Gossett - High Capacity Air Vent, Model 107A.
g) In addition to the work described above, the contractor shall also provide on-call maintenance and repair service for their supplied equipment during the periods of operation as described above. Contractor shall respond within two hours of placed call. After normal work hours, the contractor shall respond within four hours of placed call. The COR will initiate these on-call maintenance and repair services. There will be no additional payment for repair parts or materials needed as these are considered to be included in the cost of provided operational chiller units.
Submittals:
The contractor shall provide the following submittals as a minimum for review and approval.
The government shall have 14 calendar days to review each deliverable:
1) Contractor bid/proposal:
Work plan for the execution of the design, procurement, installation, and testing of the work.
This plan shall describe how the will be executed and how it will be accomplished so as to not interfere with the ongoing operations of the affected buildings and facilities.
Coordination / Schedule:
Contractor shall attend a site visit/existing conditions survey as scheduled by the COR. The contractor shall:
1) Coordinate the date and time of the work with COR within 5 days of Notice to Proceed.
2) Complete material, equipment, delivery and installation by May 15th.
Quality Control:
The contractor shall develop a Quality Control Plan to ensure that the requirements of the contract are provided as specified. This plan shall be submitted for review and approval prior to executing any design or construction work. The plan shall contain the minimum of the following:
1) An inspection program covering all of the services to be performed under this contract.
2) A description of the process to be used for verifying compliance with the contract requirements including non-destructive examinations of welds.
3) The methodology to be used for identifying deficiencies in the quality of services performed before the level of performance has an adverse impact on the execution of the project.
4) A description of the daily quality control reports to be generated during the performance of the work including photographs of the work.
5) Qualifications of the QA/QC representative.
Health, Safety and Environmental Protection:
The contractor shall develop and submit for review and approval their Health and Safety Plan along with their Environmental Protection Plan for this work. These plans shall cover the being performed including fall protection. These plans shall comply with all federal, state, local, and USMA requirements, laws, and regulations.
Reports / Records:
Within 10 days of completion of construction, the contractor shall submit all records of the work including but not limited to quality inspection reports (including photographs), test reports, and manufacturer’s documentation.