SOW_SEC_SD_UPH_Bathroom_Renovations.pdf
PDF 254 KB Posted
- Attached to
- Bathrooms Renovation, Sector San Diego- UPH - 05
- Solicitation number
- 37250PR260000047
- Issued by
- San Diego County, San Diego City, California
About this file
This is a Statement of Work (SOW) for bathroom renovation work at USCG Sector San Diego, located at 2170 N. Harbor Drive, San Diego, California. The contractor shall perform complete renovations of two distinct bathrooms (Restrooms C9/C10 and C13/14) in Building C-2, including all personnel, equipment, supplies, transportation, tools, materials, and supervision necessary to complete the work. The scope encompasses demolition of existing flooring, plumbing fixtures (toilets, urinals, sinks, showers, valves, and flushometers), and bathroom fixtures (partitions, shower pans, mirrors, and dispensers), followed by installation of new heavy-duty waterproof vinyl flooring, plumbing fixtures, and bathroom fixtures. All new fixtures, finishes, and furnishings require Coast Guard Unit POC approval prior to purchase and installation. Final work includes reconnection of all fixtures to existing water, sewage, and electrical systems in compliance with local and federal building codes, with comprehensive functionality and leak testing performed with unit POC.
The project involves critical hazardous material considerations that must be carefully managed. Asbestos-containing material (ACM) was confirmed at 2% by PLM analysis in two locations: chrysotile asbestos detected in south walls of bathrooms C13/14 (texture, taping mud, drywall) and C9/10 (ceramic wall tile, grout, thin-set). These concentrations exceed the 1% threshold under 40 CFR Parts 61 and 763 and California OSHA regulations. The SOW explicitly prohibits disturbance or abatement of ACM and requires contractors to utilize existing wall penetrations where necessary to avoid disturbing these materials. Lead was also detected at very low concentration levels. The contract is designated as a Total Small Business Set-Aside under NAICS code 236118 (Residential Remodelers) and includes approximately 240 square feet of new flooring installation and furnishing of all new plumbing and bathroom fixtures for both bathrooms.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW) FOR
SECTOR SAN DIEGO: UPH
BATHROOM RENOVATIONS
1.0 GENERAL
1.1 Scope of Work
The contractor shall provide all personnel, equipment, supplies, transportation, tools, materials, and supervision necessary to perform complete renovations of two
(2) distinct bathrooms at Sector San Diego in Building C-2: Restrooms C9/C10 and
C13/14.
1.2 Place of Performance
USCG Sector San Diego: 2170 N. Harbor Drive, San Diego, California 92101
2.0 SPECIFIC REQUIREMENTS/TASKS
2.1 Itemized List of Work
The table below specifies both the removal/demolition scope and the new installations to be executed within each respective bathroom.
All fixtures, finishes, and furnishings shall be presented to the Coast Guard Unit POC for approval prior to purchase and installation.
Feature / Requirement List of Work
Flooring (Demolition) Remove all existing flooring
Plumbing (Demolition) Remove all existing plumbing fixtures (toilets, urinals, sinks, showers, valves, and flushometers).
Fixtures (Demolition) Remove all existing bathroom fixtures, including partitions, shower pans, mirrors, and soap and paper towel dispensers.
Flooring (New) Install new heavy duty waterproof vinyl flooring
Plumbing (New) Install new sinks, showers, showerheads, valves, and toilets/urinals, utilizing existing penetrations where necessary to avoid disturbing ACM.
Fixtures (New) Install new partitions, shower pans, mirrors, and soap and paper towel dispensers.
Reconnection and testing Ensure that all new fixtures are properly connected to existing water, sewage, and electrical systems, adhering to local and federal building codes. Test for functionality and leaks with unit POC.
2.2 Demolition & Hazardous Material Handling
• CRITICAL ASBESTOS SAFETY NOTE:
Detectable chrysotile asbestos was confirmed at 2% by PLM in two locations:
south walls of bathrooms C13/14 (texture, taping mud, drywall) and C9/10
(6" ceramic wall tile (white), grout, thin-set) and should be assumed to be present in material homogenous to the sampled locations. These results exceed the 1% analytical threshold defining asbestos-containing material under 40 CFR Part 61 (NESHAP), 40 CFR Part 763 (AHERA), and applicable
Cal/OSHA asbestos regulations. See attached Asbestos and Lead Survey
Report Job No. 26-092 for greater detail.
Disturbance or abatement of ACM is strictly prohibited on this project.
Utilize existing wall penetrations where necessary for new fixtures to avoid disturbance of ACM.
• LEAD SAFETY NOTE:
Lead was detected at a very low concentration of <0.00146% by weight for bathroom C9/C10 on the south wall and <0.00154% by weight on the east wall. Lead was detected in bathroom C13/14 on the shower wall at a concentration of <0.00155% by weight (AESS Job No. 26-092). While these concentrations are well below the EPA/HUD threshold for Lead-Based Paint
(LBP) of 0.5% (5,000 ppm), any detectable level of lead triggers Cal/OSHA
Lead in Construction Standard (8 CCR § 1532.1) compliance.
Final Clean-up & Waste Characterization
Maintain clean containment zones daily. Upon completion, perform a final detailed cleanup of all work areas.
• Surface Protection: The contractor shall protect all adjacent surfaces, hallways, pathways, and building furniture during all prep, and construction phases.
• Debris Removal: The contractor is solely responsible for the daily removal, profiling/characterization (including TTLC/TCLP testing for lead-containing tile debris), transport, and legal disposal of all construction debris.
Government dumpsters shall not be used.
• LEAD DEBRIS NOTE: Debris and waste generated from the removal of the lead-containing wall tile must be evaluated for appropriate disposal classification (such as Toxicity Characteristic Leaching Procedure (TCLP) or
Total Threshold Limit Concentration (TTLC) waste characterization) prior to disposal, consistent with California hazardous waste regulations. All waste must be legally disposed of off-site. Government dumpsters shall not be used.
2.3 Unexpected Hazardous Materials Protocol
If, during the performance of work under this contract, the contractor encounters any previously unidentified material that is suspected to be hazardous (including, but not limited to, lead, asbestos, heavy metals, or toxic chemical residue) outside of the areas already documented in the provided survey report (AESS Job No. 26-092), the contractor shall:
1. Immediately halt work in the affected area and secure the immediate vicinity to prevent personnel exposure or disturbance of the suspect material.
2. Implement appropriate local controls to isolate the area.
3. Notify the Unit Point of Contact (POC) and the Contracting Officer (KO) verbally within four (4) hours, followed by written notification within twenty-four (24) hours.
4. Do not resume work in the affected area until the material has been formally tested, characterized, and certified safe, or until proper abatement is completed and the Contracting Officer issues written authorization to proceed.
3.0 CONTRACTOR PERSONNEL
3.1 Qualifications
All plumbing, electrical, tile-setting, and mechanical work must be performed by licensed, qualified professionals in accordance with California state and local codes.
3.2 Base Access
Contractor personnel must comply with all USCG Sector San Diego security requirements and maintain a professional demeanor. All personnel must have a
REAL ID Act compliant form of identification to enter the facility. Vehicles must have valid registration and insurance, and vehicle operators must have a valid driver license.
3.3 Safety Requirements
The contractor shall strictly adhere to all applicable safety standards, including:
• Implementation of proper active mechanical ventilation to safeguard both workers and station personnel.
• Full compliance with federal and state OSHA regulations.
• Mandatory and correct use of task-specific Personal Protective Equipment
(PPE), including but not limited to respiratory protection, safety goggles, gloves, and protective suits.
3.4 Contractor Responsibilities
The contractor shall:
• Provide valid proof of business insurance (general liability, workers' compensation) and all applicable professional and trade licenses to the
Contracting Officer prior to contract award.
• Mobilize all necessary equipment, supplies, and personnel to the work site to safely execute the bathroom remodeling project.
• Ensure all on-site workers are fully certified, trained, and qualified for the specific tasks they are assigned.
• Communicate regularly with the designated Project Manager (PM) regarding project milestones, timeline progression, and any issues or field changes.
4.0 PERIOD OF PERFORMANCE
The period of performance shall be 60 days from the date of the Notice to Proceed
(NTP).
5.0 HOURS OF OPERATION / SCHEDULE
The contractor shall perform all work during normal Sector business hours (0800 to
1700, Monday through Friday, excluding Federal Holidays) unless authorized by the
Contracting Officer. Any disruption to water, power, or gas must be coordinated with the Facility Manager at least 72 hours in advance.
6.0 GOVERNMENT FURNISHED RESOURCES
Contractor will provide all materials to furnish and complete all necessary work required to perform this SOW. The government will provide electricity, parking, and laydown area as available from the unit. Bathroom facilities will not be available for contractor personnel.
7.0 GOVERNMENT ACCEPTANCE PERIOD
Upon completion, the Government and Contractor will conduct a joint walkthrough to inspect, and test installed fixtures, plumbing, and flooring to verify compliance with project specifications and quality standards. The Government will have five (5) business days to inspect the space and issue a “Punch List.” Final acceptance occurs when the KO confirms all punch list items are resolved.
8.0 INVOICING
In conjunction with the subject award, proper invoices will be submitted through the Invoice Processing Platform (IPP) website (www.ipp.gov). IPP is a secure web-based electronic invoicing system provided by the U.S. Department of the Treasury’s
Bureau of the Fiscal Service in partnership with the Federal Reserve Bank of St.
Louis (FRSTL).
IPP is available at no cost to any commercial vendor or independent contractor doing business with a participating government agency.
Actions to Take:
• If you are already enrolled in IPP: If your company is already registered to use IPP, you will not be required to re-register and you do not need to contact IPP.
• If you are NOT already enrolled in IPP: The point of contact you provided in your SAM.gov registration will receive two emails from ipp.noreply@mail.eroc.twai.gov:
1. The first email will have the IPP Logon ID and a link to the IPP application.
2. A second email, sent within 24 hours of the first, contains a temporary password.
Once registered, your company may submit invoices electronically, receive email notifications when requests are paid, view payment history, and access remittance downloads.
• Support & Training: Vendor training materials, including a first-time login tutorial, are available on the IPP website (www.ipp.gov).
• Toll-free number: 866-973-3131 http://www.ipp.gov/ mailto:ipp.noreply@mail.eroc.twai.gov http://www.ipp.gov/
• Email address: IPPCustomerSupport@fiscal.treasury.gov
• Hours of operation: Monday through Friday (excluding bank holidays) from 8:00 am - 6:00 pm ET
9.0 ADDITIONAL NOTES
• Written Scope Changes: Any changes, alterations, additions, or deductions to this Scope of Work must be formally approved in writing by the Contracting
Officer (KO) and the Project Manager (PM) through official contract modification.
• Disruption Minimization: The contractor shall coordinate all utility disruptions, dust-heavy work, or loud operations with the Facility Manager in advance, and make every concerted effort to ensure minimal disruption to the building occupants, active-duty personnel, and daily emergency response operations of USCG Sector San Diego.