STATEMENT OF WORK
NATIONAL OCEAN SERVICE
NATIONAL GEODETIC SURVEY
TESTING & TRAINING CENTER
1.0 CONTRACT PROJECT:
1.1 Project Title: NGS TTC IMB Road and Parking Lot Maintenance
2.0 PROJECT CONTACT PERSONS:
2.1 On-Site Project Contact (PC)
Charles Geoghegan NOAA/NOS/National Geodetic Survey 15351 Office Drive Woodford, VA 22580 Phone: (540) 373-1243 Email: charles.geoghegan@noaa.gov
2.1 Contracting Officer Technical Representative (COR)
Sonita Tiwari NOAA/NOS/National Geodetic Survey Phone: 240-676-3859 Email: sonata.tiwari@noaa.gov
3.0 SCOPE OF SERVICES:
The scope of work consists of providing all plant, labor, equipment supplies, material, transportation, handling, and storage, and performing all operations necessary to complete the application of seal coat of asphalt cement for roads and parking surfaces located at the National Geodetic Survey’s Training Center & Laboratory facility located at 15351 Office Drive, Woodford, VA 22580. There is approximately 29000 combined square feet of road and parking surface area requiring slurry seal application associated with Office Drive and associated parking areas. The associated tasks include:
4.0 MATERIALS:
Materials should meet standard Industry specification for Asphalt Based Pavement Sealers. See attached ASTM International Standard Specification for Asphalt Emulstion Pavement Sealer (Mineral Colloid or Chemically Stabilized Type), Designation: D8099/D8099M-17.
5.0 CONSTRUCTION METHODS:
5.1 SURFACE PREPARATION
Purpose: The surface to receive asphalt sealcoat must be free of all foreign material and dry immediately prior to sealcoat application.
Contractor Shall:
Clean surface by air blowing or mechanical sweeping, or other as approved by on-site property contact.
Pretreatment and scrap any oil / grease spots to insure prior adhesion of seal coating.
Cleaning of such areas can be scraping, burning and/or chemical cleaning. (Where chemical cleaning is to be the method of cleaning MSDA sheets on all chemicals must be submitted to the owner prior to use.)
Remove any vegetation in cracks and treat the areas with a non-oil base soil sterilant prior to treating the crack as outlined in this document.
Cracks in excess of ¼ inch, but less than 1 inch in width must be properly sealed, in a fashion consistent to the manufacture’s recommendations of the sealcoat product, prior to seal coat application. Crack filler shall be hot or cold applied product designed to be compatible with the seal coating and meet current MDOT standards.
5.2 APPLICATION:
Purpose: The sealer must be applied to sound pavements. It is not a method of resurfacing deteriorated pavement. The sealer is specifically formulated to shield against the drying action of the sun, resist damage from oil and gasoline leakage and prevent water penetration. The sealer can extend the life of the pavement IF applied to sound pavement on an as needed schedule. For optimal protection Rate (undiluted material) 2 coats at 30 gallons per 100 square feet (15 gallons each coat)
First application of the seal coat must be dry prior to the second application of seal coat.
Sealer should not be applied unless pavement temperature is at least 50 ºF (10 ºC) and the air temperature is 50 ºF (10 ºC) and rising.
Sealer should not be applied during rainy or wet weather, or when rain is anticipated within eight hours after application is completed.
Sealer should not be applied to hot surfaces under the summer sun (over 90 ºF, ambient) without first cooling the surface with clean water. Water should dampen the surface without leaving puddles.
Seal coat shall be applied uniformly, free of lumps and other inconsistencies, leaving no ridge or uncoated areas.
Application method shall be by an approved method as recommended by the manufacture of the product being applied.
5.3 PAVEMENT MARKING/STRIPING:
All sealed areas shall be marked/striped to as is prior to seal coating or current ADA and codes as apply.
6.0 GENERAL REQUIREMENTS:
The Contractor shall be responsible for verifying site conditions, making quantity take offs, obtaining accurate measurement of existing conditions, and performing any act or operation which may be necessary to properly bid the work and complete the same as depicted and specified. Failure to verify the existing site conditions shall not relieve the Contractor of the responsibility to complete the work as required.
Permits: Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the Contractor.
Installation: It shall be the responsibility of the Contractor to complete work in accordance with the manufacturer’s recommendations and Industry Standards. Additional procedures and materials may be required than is indicated herein. If any item specified herein conflicts with applicable codes and recommendations, the Contractor shall bring it to the attention of the Contracting Officer for immediate resolution.
Submittals: Sufficient detail to review the proposal will be required at the time of offer. However, manufacturer's descriptive literature/shop drawings for all materials shall be submitted to the CO and EPM for review after contract award. The descriptive literature/catalogue cuts shall be annotated/highlighted with sufficient clarity so as to identify each specific product proposed for this project and show its conformance with contract requirements. Submittals are required for all building materials including: Shop drawings/product data/ samples, highlighting specific part numbers proposed, along with all selected options.
Quality Control: The work performed under this contract shall be subject to continuous audit by the COR. Quality control is the exclusive responsibility of the Contractor.
Protection of Work and Property/Safety Requirements:
(a) The Contractor shall protect the work, the site, and all existing property and structures within the limit of construction activities or that may be affected thereby until acceptance of the work.
Any damage to property shall be repaired at the Contractor’s expense, to pre-damaged condition to the satisfaction of the COR.
(b) Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities for protection and security.
7.0 Temporary Facilities:
(a) Temporary utilities (water and electricity) may be furnished to the Contractor by the Government, if available and, if requested. Contractor shall maintain and protect all such utilities during the course of construction and shall repair or replace any items damaged through his own negligence.
(b) Should the Contractor require any power or utility shutdown during construction, he shall receive approval for such shutdown from the OSPC three working days prior to this need.
(c) Access to restrooms located at the facility may be furnished to the Contractor by the Government, if available and if requested.
8.0 Cleanup:
The construction site shall be kept clean and free of debris at all times. Upon completion of project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the CO/COR.
9.0 Warranty:
Submit data concerning the standard one year warranty for workmanship, including the warranty period (dates), and warranty contacts with names, addresses and telephone numbers.
(a) Extended Equipment/Product Warranties: Obtain and furnish to the Contracting Officer all written warranties for equipment/products that have extended warranties (warranty periods exceeding the standard one-year warranty) furnished under the contract. The warranty period shall begin on the same date as project acceptance and shall continue for the full/product warranty period. The warranties shall be fully executed and delivered to the Contracting Officer prior to final acceptance of the facility.
10.0 Final Payment/Contract Closeout:
The following submittals are REQUIRED PRIOR TO FINAL PAYMENT. (1) General and Subcontractors one (1) year warranty on work.
11.0 PROJECT SCHEDULE:
The project is must be completed within 45 days of notice being given to proceed.
12.0 IT SECURITY REQUIREMENTS:
The Assessment and Authorization (A&A) requirements of Clause 48 CFR 1352.239-72 do not apply, and a Security Accreditation Package is not required.
The Contractor shall not access, store, process or transmit any government-privileged information. The Contractor shall not have access to any non-public government information, government systems and/or government networks.
Figure 1. Roads at the NGS Training Center & Laboratory Facility. Office Drive represented by light blue poly-line.
Figure 2. Parking Areas A, B and C represented by yellow polygons.
Figure 3. Existing parking space striping and markings.
A
B C
Handicap Accessible Parking
Access Aisle