This Scope of Work document issued by the United States Coast Guard Base Los Angeles Long Beach outlines tree removal services for Building 40 located at 1001 South Seaside Avenue, San Pedro, California. The project, dated May 20, 2026, requires contractors to cut down one large tree, haul all wood off-site, grind the stump at least 8 inches below grade, remove visible roots, and clear all tree debris from the site. Contractors must notify the Contracting Officer's Representative (COR) Paul L. Nelson five business days in advance of the intended start date and five business days prior to final inspection readiness. All on-site work must be performed between 7:00 AM and 4:00 PM, Monday through Friday, excluding federal holidays, unless otherwise approved. Site investigation is required per FAR 52.236-3, and contractors must arrange site access through the COR via email.
This is designated as a lowest-price, technically acceptable solicitation. Bidders must possess a DUNS number and be registered with the System for Award Management (SAM.gov) prior to award. All contractor personnel require clearance through the Coast Guard security office five business days before commencing work, with updated personnel lists provided as changes occur. Contractors must have valid photo identification and comply with OSHA Safety and Health Standards (29 CFR Part 1926), California Construction Safety Orders (Title 8, Division 1, Chapter 4, Subchapter 4), and Army Corps of Engineers EM385-1-1, with the most restrictive standard applying. All products must meet Buy American and Buy America Act requirements under DFARS 225 and FAR 25.103. Bids must include a detailed cost breakdown separating labor and materials, and contractors assume responsibility for disposal of all refuse and waste materials in compliance with federal, state, and local regulations.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF HOMELAND SECURITY
UNITED STATES COAST GUARD
BASE LOS ANGELES LONG BEACH
1001 South Seaside Ave.
SAN PEDRO, CALIFORNIA 90731
Scope of Work
FOR
Remove Tree at building 40 Dated: 05/20/2026
Base Los Angeles Long Beach Initial Date
TBD
Contracting Officer (KO)
Paul Nelson Paul.L.Nelson@uscg.mil
Contracting Officers Representative (COR)
LT Brandon McKee
BASE FACILITY ENGINEER
mailto:Paul.L.Nelson@uscg.mil
GENERAL REQUIREMENTS
PART 1 GENERAL
1.01 SCOPE OF WORK: Provide all labor, materials, and equipment necessary to remove a large tree at building 40. This is lowest-price, technically acceptable solicitation. The work includes, but is not limited to, the following:
A. Cut down one large tree and haul all wood off-site.
B. Grind stump at least 8 inches below grade and remove any visible roots.
C. Clean site making sure to pick up all tree debris.
1.02 LOCATION: Project site is located next to Building 40 at US Coast Guard Base Los Angeles Long
Beach, 1001 South Seaside Avenue, San Pedro, CA 90731. Contracting Officer’s Representative
(COR) for this project is Paul Nelson Paul.L.Nelson@uscg.mil.
1.03 SITE INVESTIGATION: Investigate the site per FAR 52.236-3 to ascertain the general and local conditions which can affect the work or its cost. Contact: Paul L Nelson via email to arrange site access. Vendors must have DUNS and be registered at System for Award Management
(SAM.gov) prior to be awarded a government Purchase Order.
1.04 CONTRACTOR SECURITY REQUIREMENTS: For this Coast Guard facility, the Contractor shall provide a list of all on-site personnel on the provided access request form, including sub-contractors and suppliers, to the Contracting Officers Representative (COR) 5 days prior to commencing work for clearance (clearance can take up to 3 business days). The contractor shall update this list when changes occur. Contractor personnel not listed may be denied access to the Coast Guard facility.
Contractor personnel will be restricted to designated working areas. Any personnel violating this policy may lose access to the Coast Guard facility. Contractor personnel shall have photo identification at all times while working on Coast Guard facilities.
Contractor and delivery personnel may be required to present personal photo identification to gain access to a Coast Guard installation. If identification does not indicate United States citizenship, Coast Guard Security will require proof of the legal right to work in the United States. Contractor and delivery personnel also may be subjected to an immigration status and outstanding criminal warrants check.
Contractors shall provide the COR with 48 hours of advance notice of every delivery to the site (e.g., concrete, lumber, parts, etc.) and provide the company name, delivery person, and phone number of the firm(s) making deliveries. All vehicle access to government property requires vehicle registration and proof of liability insurance. Otherwise access to the Coast Guard facility may be denied.
1.05 CONTINUITY OF FACILITIES OPERATION: Schedule work to minimize interference with the facilities normal operations. Notify the COR 3 business days in advance of any shutdowns.
Contractor is required to coordinate Lock Out/Tag Out Processes and Procedures with the
COR. Perform all on-site work between the hours of 7:00 AM and 4:00 PM, Monday through
Friday (Federal Holidays excluded), unless otherwise approved by the COR or the Facility Engineer
(FE).
mailto:Paul.L.Nelson@uscg.mil
1.06 NOTIFICATION OF START AND COMPLETION OF WORK: The Contractor shall notify the
COR in writing (email) five (5) business days in advance of the date they intend to commence work, and five (5) business days prior to the date that work will be ready for final inspection. All notifications must be approved by the COR, in writing, prior to commencing or completing work.
1.07 RECYCLING AND DISPOSAL OF REFUSE: Refuse, excess, or waste materials resulting from construction operations shall become the property of the Contractor and shall be recycled and/or disposed of off Government property. All disposals shall be done in accordance with federal, state, and local laws and regulations.
1.08 SAFETY: During the execution of this contract, the Contractor shall conform to the rules and regulations as set forth by OSHA Safety and Health Standards, 29 CFR Part 1926 - Safety and Health
Regulations for Construction and California Code of Regulations, Title 8, Div. 1, Ch 4, Subchapter 4
Construction Safety Orders, and Army Corps of Engineers EM385-1-1. When the standards differ, the more restrictive standard shall apply. The contractor shall provide barriers, temporary fencing, ventilation, trench covers, etc. wherever work could cause injury to workers, visitors, Coast Guard personnel, or dependents. Return work site to original condition after completion of work by cleaning and removal of all construction material. An Accident Prevention/Safety Plan shall be submitted by the contractor prior to any commencement of work.
1.09 SUPPLIES AND SERVICES: All products must meet the requirements of the Buy American and
Buy America Acts as amended in DFARS 225 and the FAR 25.103.
1.10 TEMPORARY FACILITIES:
A. STORAGE: The location for exterior stock piling or lay down area of materials will be available on base with location to be determined by COR and Facility Engineer depending on size. The
Contractor shall be responsible for protecting materials stockpiled against weather, damage, theft, and other risks of loss. The Coast Guard assumes no responsibility for material or equipment left in the storage area.
B. SANITARY FACILITIES: Toilet facilities are available for use located in Buildings 33.
C. WATER AND ELECTRICITY: Water and 120V electricity are available at no cost to the
Contractor. Cost of these utility connections and disconnections shall be the responsibility of the
Contractor. Personnel using extension cords to bring power from another location for construction, maintenance, remodeling, etc., shall employ portable ground fault circuit interrupters (GFCIs), even if connecting to building wiring. Use of portable generators and compressors is authorized at contractor expense to operate portable equipment.
1.11 All bids submitted shall include break down of cost for labor and materials.