SOW Refrigerant Plant Inspect_Repair.pdf
PDF 731 KB Posted
- Solicitation number
- 52000QR260028760
About this file
This is a Statement of Work (SOW) for refrigeration plant inspection, repair, and replacement services on the USCGC Vigilant (WMEC-617), a U.S. Coast Guard vessel located at Cape Canaveral, Florida.
The Contractor must troubleshoot, flush, repair/replace, and test two refrigeration plants (NR1 and NR2) manufactured by Bailey Refrigeration Co., Inc./Carrier Type 90YR20 Salt Water Cooled systems. Government-furnished property includes two reciprocating compressors (NSN: 4310-01-571-6959, estimated cost $4,870 each), two condensers (NSN: 4130-01-576-5680, estimated cost $4,964 each), one chill box evaporator (NSN: 4130-01-576-4489, estimated cost $1,036), and two freeze box evaporators (NSN: 4130-01-576-5706, estimated cost $1,550 each). The systems contain severe contamination including thick metallic sludge and debris clogging oil separators and filter drier housings.
Required work includes securing electrical power, capturing and discarding refrigerant/oil using approved reclamation systems, removing vital components, performing deep mechanical flushing with specialized high-volume recirculating pumps and approved refrigeration cleaning solutions, replacing compressors and evaporators with Government-furnished equipment, inspecting and replacing thermal expansion valves and raw water cooling flex hoses, replacing accumulator bladders, conducting comprehensive system inspections and piping repairs, performing final nitrogen flush with insulation restoration, conducting comprehensive electrical and control cabinet restoration and testing, and performing operational tests including pressure testing, leak checks, vacuum decay testing, system filling with new oil and R134A refrigerant, and final verification of operating pressures and temperatures. The Contractor must be an authorized Carrier or Bailey contractor with personnel certified in AC&R handling of R134A refrigerant. Three potential periods of performance are offered: Primary (19 October – 30 November), Secondary (26 October – 7 December), or Tertiary (2 November – 14 December), with the Government retaining sole authority to designate which period will be executed. All work must be completed within the single designated period.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FAR Matrix September.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK: Refrigeration Plants, Inspect and Repair/Replace
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to troubleshoot, flush, repair/replace, and test the NR1 and NR2 refrigeration plants (Make: Bailey Refrigeration Co, Inc. / Carrier Type 90YR20 Salt Water Cooled) onboard USCGC Vigilant (WMEC-617).
1.2 Government-furnished property.
MTI ITEM
DESCRIPTION
NSN/PN QTY ESTIMATED
COST
($/UNIT)
Y Compressor, Reciprocating
NSN: 4310-01-571-6959
PN: 06DR8200DA365A
2 ea. 4,870.00
N Condenser NSN: 4130-01-576-5680
PN: MHX-602B-4
2 ea. 4,964.00
N Evaporator, Chill Box NSN: 4130-01-576-4489
PN: KLP103VE
1 ea. 1,036.00
N Evaporator, Freeze Box NSN: 4130-01-576-5706
PN: KLP104VE
2 ea. 1,550
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 618-WMEC 516-004, Rev B, Diag of SS Refrigeration Sys. & S.W.
Cooling Piping
Coast Guard Drawing 618-WMEC 516-006, Rev A, Mods Incidental to the Carrier Reefer Plant Install
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary Machine Systems
OTHER REFERENCES
NSTM 516 Refrigeration Systems can be provided upon request due to size of file.
3. REQUIREMENTS
3.1 General.
3.1.1 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.2 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:
Refrigeration piping and valves
Insulation
Electrical control cabinets and wiring
Compressor oil and refrigerant (R134A)
Salt Water piping and valves
3.1.3 Facility & Personnel Qualifications. The Contractor is preferred to be an authorized Carrier or Bailey contractor. All personnel handling refrigerant must be AC&R certified specifically for handling R134A refrigerant and complexity of repairs.
3.2 Refrigeration plant repairs. The Contractor must perform the following repairs to the NR1 and NR2 refrigeration systems using Coast Guard Drawings 618-WMEC 516-004 and 618-WMEC 516-006 as guidance.
3.2.1 Refrigeration plant, secure. Secure and tag-out electrical power to the NR1 and NR2 refrigeration plants.
3.2.2 Capture and Discard. The Contractor must capture and remove all refrigerant/oil from all components in the refrigeration system using an approved vacuum pump and reclamation system.
3.2.3 Component Removal. The Contractor must remove all vital components prior to mechanical flushing, including compressors, condensers, chill box evaporators, freeze box evaporators, receivers, accumulators, TXVs, oil separators/filter, filter driers, and back-pressure regulating valves for both the NR1 and NR2 refrigeration systems
3.2.4 Deep system flushing. Completely disconnect and mechanically flush both NR1 and NR2 refrigeration systems to remediate catastrophic internal failures. The contractor must make sure that no connection dead heads so that debris/contamination does not build up in the system. This will be a complete flush of all piping and components remaining in the system.
NOTE:
SYSTEMS CONTAIN SEVERE CONTAMINATION, INCLUDING THICK
METALLIC SLUDGE AND DEBRIS COMPLETELY CLOGGING THE
OIL SEPARATORS AND FILTER DRIER HOUSINGS.
3.2.4.1 Utilize a specialized high-volume recirculating flushing pump (such as a Goodway flushing system) and an approved refrigeration cleaning solution (such as CF20 or equivalent).
3.2.5 Component replacement. The contractor must submit a CFR for each sub paragraph to 3.2.5.
3.2.5.1 The Contractor must replace compressors, condensers, chill box evaporators, and freeze box evaporators for both the NR1 and NR2 refrigeration systems utilizing the Government-furnished property listed in Section 1.2. Prior to disposal or turn-in, thoroughly inspect the removed NR1 and NR2 compressor to document the extent of internal damage.
3.2.5.2 Inspect and remove the Thermal Expansion Valves (TXVs) for the chill box and freeze box, which have been compromised by debris. Contractor to provide replacement of TXVs if necessary.
3.2.5.3 Remove and replace the Raw Water (R/W) cooling flex hoses.
3.2.5.4 Accumulators. The Contractor must remove and replace the accumulator bladder.
3.2.6 System inspection and piping repair. Conduct a comprehensive inspection of the remaining refrigeration plant infrastructure. Submit a CFR per sub paragraph.
3.2.6.1 Inspect receivers, accumulators, oil separators, filter-driers, refrigeration piping, strainers, and associated regulating valves. Clean, pressure test, disassemble, or replace components as required based on inspection findings. Contractor to provide necessary replacement parts not listed in Section 1.2 if not available in military stock system.
3.2.6.2 Inspect all refrigeration system crossover and isolation valves. Replace valves showing signs of significant degradation or missing components (e.g., stem locking hardware) to ensure NR1 and NR2 circuits can be positively isolated from one another.
3.2.7 Final flush prior to operation. The Contractor must flush the system with dry nitrogen once all components and piping connections are renewed.
3.2.7.1 Insulation. The Contractor must restore insulation to removed interferences and apply to all condensing piping.
3.2.8 Electrical and control cabinet restoration. Conduct a comprehensive repair and restoration of both NR1 and NR2 refrigeration control cabinets.
3.2.8.1 Restore the #1 and #2 control cabinets to their intended configuration while installing new GFE compressors.
3.2.8.2 Overhaul electrical components. Based on discrepancy reports, replace necessary internal cabinet components. Contractor to provide required switches, fuses, relays, and hardware if not available in military stock system.
3.2.8.3 Test all safety, pressure controls, oil pressure controls, relays, wiring, and protective devices for proper operation in both cabinets.
3.3 Operational test, post repairs. Clear all tags. After completion of work and in the presence of the Coast Guard Inspector, the Contractor must thoroughly test and demonstrate the equipment to be in satisfactory operating condition with assistance from ship’s force. Submit a CFR.
3.3.1 Pressure test both refrigeration systems with dry nitrogen, perform a leak check, evacuate, and perform a vacuum decay test (pulling system to 500 microns).
3.3.2 Fill both systems with new compressor oil and R134A refrigerant.
3.3.3 Individually operationally test both NR1 and NR2 through a complete box temperature pull down.
3.3.4 Record and verify operating pressures, temperatures, oil pressure, superheat, subcooling, and box temperatures during final testing. Ensure there is no fluctuation in oil pressures.
4. PERIOD OF PERFORMANCE.
The Government has established three potential Periods of Performance (POPs) for this requirement:
Primary: 19 October – 30 November Secondary: 26 October – 7 December Tertiary: 2 November – 14 December
The Government reserves the exclusive and unilateral right to determine and designate which POP will be utilized based on operational requirements. All required services shall be completed during the single period of performance established by the Government.
Prior to award, offerors must explicitly state and confirm their availability to perform the required services during any of the three specified periods (Primary POP, Secondary POP, or Tertiary POP). The authority to select and direct which period of performance is executed rests solely with the Government.
5. LOCATION.
CGC VIGILANT
9235 Grouper Road, Cape Canaveral, FL 32920
File details come from the government source that posted it. Updated .