This statement of work and related federal contract opportunity outline requirements for a construction project to repair airfield pavements at Hancock Field Air National Guard Base in Syracuse, New York. The statement of work requires milling and overlaying approximately 101,000 square yards of asphalt pavement, crack sealing, airfield restripping, and concrete pavement repair. Work must be completed within 180 days in accordance with technical specifications. The pre-solicitation notice seeks bids for project HAAW152023, with bids due by 30 September 2020. The project value is between $1-5 million. This procurement is set aside for qualified HUBZone small businesses under NAICS code 237310.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

HAAW152023

Repair & Maintain Airfield Pavements

174th Attack Wing

Hancock Field ANG Base 6001 East Molloy Road

Syracuse, New York 13211

16 April 2020

Table of contents

1. SCOPE OF WORK

2. AREA OF WORK

3. DESCRIPTION OF WORK

4. PERIOD OF PERFORMANCE

5. MATERIALS

6. MATERIAL SUBMITTALS

7. GENERAL CONDITIONS

8. GOVERNMENT WORKING HOURS

9. DIFFERING SITE CONDITIONS

10. UTILITIES

11. DISPOSAL OF MATERIALS AND CLEANUP

12. MATERIAL & EQUIPMENT ACCOUNTABILITY

13. SECURITY

14. ESCORTS

1. SCOPE OF WORK:

The contractor shall provide all personnel, equipment, tools, materials, supervision, transportation, and other items and services necessary to complete the work as described in this Statement of Work, the B-3 Submittal Project Specifications Volumes 1 & 2, and B-3 Submittal Project Drawing Set. Work location is the 174th Attack Wing (174 ATKW), 6001 East Molloy Road, Syracuse, New York 13211 on Hancock Field Air National Guard Base, Syracuse, New York 13211.

2. AREA OF WORK:

Contractor shall work only in the areas designated by Contracting Officer Representative (COR).

3. DESCRIPTION OF WORK:

The work includes: the mill and overlay of the asphalt pavements associated with existing aprons; spall repair and resealing of joints and cracks within the existing concrete aprons; remarking the lead-in taxiways and apron areas; along with miscellaneous drainage, grading, and incidental related work. All work performed under this SOW shall be conducted in accordance with all applicable state and federal laws and regulations, ANG policies and regulations, the B-3 Submittal Project Specifications and B-3 Submittal Project Drawing Set for HAAW152023 Repair & Maintain Airfield Pavements, and this SOW as outlined below.

4. PERIOD OF PERFORMANCE:

Work must be completed in 180 days to support the duties of 174 ATKW personnel and safety of the Mission.

5. MATERIALS:

See B-3 Submittal Project Specifications and B-3 Submittal Project Drawing Set for HAAW152023 Repair & Maintain Airfield Pavements

6. MATERIAL SUBMITTALS:

& Maintain Airfield Pavements.

7. GENERAL CONDITIONS:

8. DIFFERING SITE CONDITIONS:

9. GOVERNMENT WORKING HOURS:

10. UTILITIES:

11. DISPOSAL OF MATERIALS AND CLEANUP:

12. MATERIAL & EQUIPMENT ACCOUNTABILITY:

13. SECURITY:

Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within Government controlled installation, facility, or area. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

For Contractors that do not require CAC, but require access to a DoD Facility and/or Installation.

Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 31-101 and AFI 10-245), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

AT Level I Training. This standard language is for contractor employees with an area of performance within a Government controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access to Government Installations, Facilities and Controlled Access areas shall complete AT Level I awareness training within 10 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Certificates of completion for each affected contractor employee and subcontractor employee will be maintained by the COR or Antiterrorism Representative. AT level I Awareness Training is available through ADLS by completing the Force Protection CBT.

174th ATKW Security Forces shall monitor the incoming and outgoing of work personnel during the duration of the project. All deliveries shall be coordinated with the COR to arrange for their entrance onto 174th ATKW property. Additionally, See B-3 Submittal Project Specifications and B-3 Submittal Project Drawing Set for HAAW152023 Repair & Maintain Airfield Pavements.

14. ESCORTS:

14.1. A security briefing will be conducted prior to the start of the contract.

14.2. All Contractor personnel shall have a minimum of one (1) Form of Photo Identification with them at all times.

14.3. See B-3 Submittal Project Specifications and B-3 Submittal Project Drawing Set for HAAW152023 Repair & Maintain Airfield Pavements.

File details come from the government source that posted it. Updated .