This document is a Statement of Work (SOW) for the cyclic maintenance on gravel roads and storage areas at Vicksburg National Military Park. The objective is to resurface approximately 34,200 square feet of existing gravel roads and parking/storage areas at the park's maintenance complex. The scope of work includes scarifying the road/parking lot surfaces, filling in potholes and ruts, re-graveling with a 4-inch thick crushed limestone base, and compacting the surfaces. All materials must meet federal DOT standards. The contractor will be responsible for providing all materials, equipment, and labor, as well as temporary road signs and markers. Work is to be performed Monday through Friday during normal operating hours, and the contractor must follow all applicable safety and environmental regulations. The related federal contract opportunity is Solicitation Number 140P5224Q0037 for "Re-Surface Gravel Road" maintenance at the park.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid_Schedule.xlsx | XLSX spreadsheet | |
| Solicitation_140P5224Q0037.pdf | ||
| Past_Performance_Questionnaire.doc | DOC document | |
| Sol_140P5224Q0037.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Vicksburg National Military Park
STATEMENT OF WORK:
Cyclic Maintenance on Gravel Roads and Storage Areas
DATED:
May 2024
NATIONAL PARK SERVICE
Cyclic Maintenance on Gravel Roads and Storage Areas SOW
SOUTHEAST REGION
Introduction:
Vicksburg National Military Park (VICK) is comprised of several discontinuous units related to the US Civil War, including:
· The Campaign for Vicksburg: For 18 months Union and Confederate Forces engaged each other all through the region as they positioned for control of Vicksburg.
· The Siege of Vicksburg: For 47 days, the Union General US Grant held the Confederate Army and city of Vicksburg under a hard and brutal siege.
The multiple sites are managed under one administration and are located in and around a 40-mile radius surrounding Vicksburg, Mississippi. Sites related to the Campaign for Vicksburg include the Port Gibson Unit (Shaifer House), Raymond Unit (Battle of Raymond), and Champion Hill (Crossroads and Coker House). The Siege of Vicksburg sites include the main battlefield and National Cemetery within the City of Vicksburg, Pemberton's Headquarters, Louisiana Circle, Navy Circle, and the USS Cairo.
At the main battlefield unit at 3201 Clay Street, the park facilities maintenance complex is sited at a bottom of a hill along a drainage. The complex contains several buildings and gravel access roads.
Objective:
Vicksburg National Military Park plans to resurface existing gravel roads and parking/storage areas in and around the Maintenance Complex. A total of one (1) roads and two (2) parking/storage areas will be re-graveled as part of this project. These include the Maintenance Access Road (approximately 24,200 sf), Operations Building parking/storage (approximately 8,000 sf), and Upper Storage parking/storage (2,000 sf). Contractor will measure and verify the approximately 34,200 square feet of gravel roads and parking/storage areas to be resurfaced. See Figure 1 for map of areas.
· Resurfacing will include:
· Scarify road/parking lot surface to remove all grass and vegetation
· Fill in existing potholes and ruts with compacted crushed lime base prior to the addition of the final layer
· Regravel with “DOT base” of crushed limestone base rock, grade with crown for drainage. See Scope for depth of gravel to be used for each road/parking lot.
· Compact all gravel road/parking lot surfaces to approved psi (pounds per square inch).
· All new lime base and gravel will match the existing color of existing gravel drives and parking/storage areas.
· Gravel must meet Federal DOT standards for “DOT base” material and not be more than 1.5 inches in diameter.
· Gravel mix shall include an appropriate amount of “fines” to compact and lock larger aggregate together to create a smooth driving surface.
Scope:
1. Contractor will provide all material, equipment, parts and labor required to perform all of the work of this contract.
2. Contractor will provide all road signs and markers per DOT standards, to allow safe passage of visitors and employees.
3. Gravel access road will remain same dimensions (width).
4. All equipment, material and waste removed or generated by work of this contract shall be properly disposed of offsite by the contractor.
5. All areas shall receive the following: top dressing will be four inches thick at the crown and no less than two inches at the road/storage area edge after compaction.
6. Operations Building parking/storage (approximately 8,000 sf) includes an area under roof cover that requires gravelling. Contractor may need to use smaller equipment in area under roof cover to get adequate compaction.
7. Contractor shall verify the quantity of materials needed to complete the task identified in this statement of work (SOW).
8. Contractor will provide a work site and environment that is safe for employees, for visitors to the Park, and NPS staff. The work area will be cordoned off (if necessary) and secure.
9. Contractor shall leave the worksite clean and free of construction debris.
10. All work will be performed Monday through Friday from 7:00 am until 3:00 pm. No work will be performed on weekends or federal holidays without prior approval.
11. All construction access will be via the main park entrance at 3201 Clay Street.
12. Contractor and employee parking and equipment storage areas will be designated by the Park. No company signs shall be installed on government property. Smoking and eating will be performed in areas designated by the Park. Employees shall wear appropriate clothing at all times.
13. Contractors will notify NPS staff of scheduled site visits to ensure access to secure areas.
14. The Davis-Bacon Act applies for this contract.
Submittals:
Contractor will submit cut sheets to the COR for material approval prior to use for the following items:
1. Product Submittals (Cut Sheets):
a. Road surface material
b. Road Sign Verbage during construction
Period of Performance:
Three Months after Notice to Proceed Safety:
All work performed on government property will be accomplished in accordance with OSHA, EPA, Federal, State and local regulations and requirements. Prior to starting work on government property, the contractor will submit to Cane River Creole National Historical Park (CARI) for approval a copy of their company safety plan pertaining to this particular contract. Although not all inclusive, the safety plan must address at a minimum the following areas:
1) Confined space operations (if required)
2) Heavy equipment operations (if required)
3) Public/visitor safety (barriers/signage, etc…)
4) Traffic safety plan (if required)
5) Trenching/sloping of soil
6) Personal protective equipment to be used
7) Hazardous materials (HAZMAT) to be used
a. Copies of Safety Data Sheets must be provided to CHPI
b. Storage of HAZMAT
8) Emergency response protocols
9) Personnel training requirements
10) OSHA DART rate
a. OSHA 300A Summary for last three years
Contractor shall use “green” products whenever possible and all HAZMAT must be pre-approved for use by the COR. The contractor will be responsible for the safety and security of the site to ensure unauthorized personnel (park visitors & employees) do not enter the construction area.
Security & Work Hours:
Contractor shall only perform this work during normal operating hours, Monday through Friday (7:00am – 3:00pm), unless approval is given by Park.
Location map of Maintenance Complex road (red) and parking/storage areas (yellow).