SOW_for_Long_Lake_Bunkhouse_Siding_Project.pdf

PDF 171 KB Posted

Attached to
ND-LONG LAKE NWR-BUNKHOUSE SIDING REPLACEMENT
Solicitation number
140F0122Q0002
Issued by

View the file

Other files

File Type Posted
Sol_140F0122Q0002_Amd_0002.pdf PDF
Map_Bunkhouse_0002.pdf PDF
Sol_140F0122Q0002_Amd_0001.pdf PDF
B03_-_DOL_Wage_Determination.pdf PDF
Sol_140F0122Q0002.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

NAICS: 238170 Siding Contractors

Long Lake NWR Bunkhouse Siding Replacement Burleigh County, ND

1. General:

1.1 Describes the project in general terms. (Who: Long Lake National Wildlife Refuge, 12000 353rd ST SE, Moffit, ND 58560), What (Type of Service (NAICS) and Title), and Where Bunkhouse located at headquarters complex.

1.2 Purpose/End Application: Briefly state the purpose of the project or Why the project is being pursued and desired outcome. If applicable, note how this requirement relates to other projects or requirements in process. The project is to remove and dispose of old and rotten wood siding, install construction wrap, and install seamless steel siding on the Bunkhouse.

1.3 Contractor Qualifications: State licensed contractor with experience in removing old siding and installing new seamless steel siding.

1.4 Other: NA

2. Place of Performance and Period of Performance (Where and When) the project is being completed.

2.1 Work will be completed at 12000 353rd St SE, Moffit, ND 58560.

2.2 Annotate the Performance start and end date. Work should be completed outside of the winter months, generally November through March

2.3 Normal duty hours Monday thru Friday 7:30 a.m. - 4:00 p.m. In the event of emergencies, Contractor shall provide contact information.

2.4 Non-duty hours include week nights, weekends, and Government holidays (New Year’s Day, Martin Luther King JR.s’s Birthday, Memorial Day, Independence Day, Labor Day, Columbus Day, Veteran’s Day, Thanksgiving Day, Christmas Day).

3. Scope

3.1 Contractor shall remove and properly dispose of the old wood siding, taking care to collect loose nails. Contractor shall inform Station Manager of any underlying damage discovered after removal of old siding. Contractor shall install construction wrap around building according to industry standards. Contractor shall install seamless steel siding and trim around the entire exterior walls of the Bunkhouse according to industry standards. Contractor shall clean the site of all construction materials.

4. Deliverables and/or Delivery Schedule: (for extended list a bid schedule and/or use of line item detail on the PR is recommended) NA

5. Data Management Plan (DMP) for Science Data Agency Reference. NA

6. Government-Furnished Equipment (GFE) / Government-Furnished Information

(GFI) NA

7. Evaluation and Acceptance

7.1 The contractor will be evaluated as detailed herein. Government acceptance is contingent upon: adherence to all applicable building codes, completion in an appropriate amount of time, quality of work, completion of work within the scope of the project and site cleanup.

8. Quality Control/Quality Assurance:

8.1 For commercial supplies reference clauses for inspection and acceptance. Where appropriate, QC will be maintained according to industry standards and made available to the agency with the contractor’s proposal.

8.2 Identify and detail measures for assessing quality control and acceptance; each requirement is unique and a table format is visually friendly and may be desirable.

Acceptance will be evaluated against compliance with all applicable building code and industry standards.

Materials shall be free from inperfections.

Installation shall be clean looking and uniform.

9. Technical Coordinator:

9.1 Identify the primary individual responsible for the final product or service.

Jared Newton, Station Manager, 701-329-0857, 12000 353rd ST SE, Moffit, ND 58560

9.2 Identify the secondary or co-individual responsible with same pertinent information.

Todd King, Maintenance Worker, 701-387-4786, 12000 353rd ST SE, Moffit, ND 58560

STATEMENT OF WORK
1. General:
2. Place of Performance and Period of Performance (Where and When) the project is being completed.
2.1 Work will be completed at 12000 353rd St SE, Moffit, ND 58560.
2.2 Annotate the Performance start and end date. Work should be completed outside of the winter months, generally November through March
2.3 Normal duty hours Monday thru Friday 7:30 a.m. - 4:00 p.m. In the event of emergencies, Contractor shall provide contact information.
2.4 Non-duty hours include week nights, weekends, and Government holidays (New Year’s Day, Martin Luther King JR.s’s Birthday, Memorial Day, Independence Day, Labor Day, Columbus Day, Veteran’s Day, Thanksgiving Day, Christmas Day).
3. Scope
4. Deliverables and/or Delivery Schedule: (for extended list a bid schedule and/or use of line item detail on the PR is recommended) NA