This Statement of Work (SOW) details the design and installation of a propane-fueled heating system for a 40'W x 60'L pre-engineered metal fire building located at the Rachel Carlson National Wildlife Refuge in Wells, Maine. The project requires a comprehensive heating solution including forced air propane heaters or infrared tube heaters, exterior propane tank installation, proper ventilation, programmable thermostat control, and combustion air management, with specific requirements to accommodate high air-exchange areas and ensure efficient winter heating.

The contract anticipates a firm-fixed price award in August 2025, with a 45-calendar day completion timeline from the Notice to Proceed. The contractor must perform heat load calculations, coordinate with a licensed propane supplier, obtain all necessary local and state permits, comply with Maine Fuel Board codes and NFPA 58 regulations, and provide complete system testing, commissioning, and owner training. Required submittals include manufacturer technical data, installation instructions, and warranty information, to be emailed to the Fire Program Manager and Project Engineer/Contracting Officer's Representative.

View the file

Other files

File Type Posted
Notice_to_Offerors.pdf PDF
Sol_140FGA25Q0041.pdf PDF
DOL_Wage_Determination.pdf PDF
Price_Schedule.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Fish and Wildlife Service – RCNWR 1 of 3 SOW – Fire Building Heating System

STATEMENT OF WORK

Fire Building Heating System

PART 1 - PROJECT OVERVIEW

A. NOTICES

1. Project Information

Project Title: Heating System for Fire Building

Location: U.S. Fish & Wildlife Service Rachel Carlson National Wildlife Refuge 429 Post Road Wells, ME 04090

Contracting Officer (CO): TBD

Project Engineer / Contracting Brian Waz, 413-253-8605 Officer’s Representative (COR):

FWS Facilities Manager: Spencer Goodrich, 978-518-9739, spencer_goodrich@fws.gov

FWS Fire Program Manager: Christopher McCandless, 207-849-6793, christopher_mccandless@fws.gov

2. Project Overview

Design and install a complete reliable and efficient propane-fueled heating system for a newly constructed 40’W x 60’L pre-engineered metal building (PEMB). The structure includes three (3) 12'x12' garage doors, two

(2) man doors, and five (5) windows (Refer to Appendix 1: Photographs). The heating system will be designed to ensure consistent, safe, and efficient indoor heating throughout the winter months in coastal Maine. The system shall accommodate high air-exchange areas due to large garage doors.

B. PROJECT DETAILS

1. Contract Work:

This Contract is to design and install propane-fueled heating system. The following system requirements are required but not limited too based on the design.

Heating Type: Forced air propane heater(s) or infrared tube heaters (based on usage and ceiling height).

Fuel Supply: Exterior propane tank(s) with regulators sized for demand.

Ventilation: Proper flue gas exhaust and fresh air intake as required.

Thermostatical Control: Programmable thermostat for zone control.

Combustion Air: Ducted or louvered openings for safe operation.

Freeze Protection: Heat to prevent water carrying equipment from freezing.

The work shall comply with all industry standard best practices, regulations, and materials.

U.S. Fish and Wildlife Service – RCNWR 2 of 3

2. Heating System Design:

Perform heat load calculations based on building size, insulation (closed-cell spray foam), window/door count, and use case.

Determine appropriate heater sizing and quantity.

Develop layout for heaters, ductwork (if applicable), gas piping, and venting.

3. Propane System Installation:

Coordinate with licensed propane supplier to install:

o External propane storage tank(s) sized for building usage (minimum 500-gallon recommended).

o If concrete pad is required for propane tank, the government will supply.

o Trenching and installation of underground or protected above-ground gas lines to building.

o Pressure regulation and shut-off valves per NFPA 58 and Maine Fuel Board regulations.

Include tie-in to building heating system and required leak/pressure testing.

4. Code Compliance and Permitting:

Obtain and comply with all local and state permits, including mechanical, propane fuel system, and electrical (if applicable).

All work must comply with:

o Maine Fuel Board codes o NFPA 58 (Liquefied Petroleum Gas Code) o Manufacturer’s installation instructions o Federal, state, and local regulations.

o Local coastal building codes (if any), including wind and corrosion resistance.

5. Testing, Commissioning, and Training:

Start up and commission all heating equipment.

Verify complete and safe propane operation, combustion air, and exhaust systems.

Train owner/operator on thermostat settings, safety shut-offs, and propane system maintenance.

6. Project Submittals:

The following information is required from the Contractor, but not limited to:

Manufacturer’s Technical Data and Specifications Manufacturer’s Installation Instructions Warranty information

Submittals shall be emailed to the following:

Contracting Officer (CO): TBD

FWS Fire Program Manager: Christopher McCandless, 207-849-6793, christopher_mccandless@fws.gov

Project Engineer / Contracting Officer’s Representative (COR): Brian Waz, brian_waz@fws.gov, (413)-253-8605

7. Anticipated Award Period / Contract Type:

The Government anticipates a firm-fixed priced award of this contract in August 2025.

U.S. Fish and Wildlife Service – RCNWR 3 of 3

8. Completion Date:

The project shall be completed and commissioned no later than 45 calendar days from the Notice to Proceed issued by the Contracting Officer.

APPENDIX 1:

Photographs

40’W x 60’L Fire Building

Photo #1: View of front of the building.

Photo #2: Side/back view of building.

Photo #3: Interior view of left wall.

Photo #4: Interior view of right wall.

SOW - RCNWR - Fire Building Heating System.pdf
APPENDIX 1

File details come from the government source that posted it. Updated .