This Statement of Work (SOW) details Schneider Electric's maintenance and technical support services for NASA's National Center for Critical Information Processing and Storage (NCCIPS) facility. The contract covers support for Schneider Electric Power Logic Supervisory Control and Data (SCADA) and Power Monitoring Expert systems, with a total of six required deliverables including ESP Plan Ultra, PSO Support, Onsite Maintenance Visits, Training Subscription, and In-office Support. The maintenance contract is effective from 06/08/2025 through 06/07/2026, with all deliverables subject to review and approval by SAIC and NASA.

Key contract requirements include establishing a Non-Disclosure Agreement (NDA), ensuring all documents are labeled "Sensitive But Unclassified", and mandatory United States citizenship for personnel accessing the NASA Stennis Space Center and NCCIPS data center. The subcontractor must comply with local, state, and federal standards, as well as generally accepted engineering principles and NCCIPS/NASA standards. The SOW specifies that the subcontractor will provide a delivery schedule for each deliverable, which will be reviewed and approved by SAIC.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUBCONTRACTOR

STATEMENT OF WORK (SOW)

FOR

Schneider Electric Maintenance and Technical Support

Date: May 15, 2025

1. Technical Scope

1.1 Overview

This Statement of Work (SOW) describes the scope and deliverables for Schneider to provide maintenance and technical support for our Schneider Electric Power Logic Supervisory Control and Data (SCADA) system and our Power Monitoring Expert system for the National Aeronautics and Space Administration (NASA) National Center for Critical Information Processing and Storage (NCCIPS) facility.

The scope of work includes onsite maintenance visits, remote technical support and training. These systems are critical to monitoring and data reporting of the electrical infrastructure throughout the NCCIPS campus.

This project shall be accomplished through the services of an SAIC subcontractor to complete the deliverables with specified scope described in Section 1.2.

1.2 Engineering Deliverables

This section describes the deliverables required. The subcontractor’s response shall include proposed pricing for the required deliverables and their proposed delivery dates. The response must have detailed explanation of cost with breakdown of estimated man hours and cost associated with labor, including providing the basis of these estimates. The following are the required deliverables:

Deliverables Quantity

ESP Plan Ultra 1 TOTAL

PSO Support 1 TOTAL

Onsite Maintenance Visits 6 Total

Deliverables Quantity

Training Subscription 1 Total

In office support 1 Total

The format of the response expected to this SOW is provided in Appendix A.

1.3 Non-Disclosure Requirements

This project requires the establishment and implementation of a Non-Disclosure Agreement (NDA) policy. All key subcontractor personnel shall be required to sign NDA forms and abide by all NDA requirements.

This project requires all electronic and hardcopy documents used and developed by the subcontracted electrical engineer to be securely maintained. All drawings and other documents developed by the subcontracted electrical engineer must be labeled as “Sensitive But Unclassified.”

At the end of this contract, electronic copies of all drawings and documents delivered to or developed by the subcontracted electrical engineer are to be submitted to SAIC.

1.4 Assumptions

The following assumptions apply to this SOW:

• All deliverables sahll be reviewed by SAIC subject matter experts.

• All deliverables require SAIC and NASA approval.

1.5 Applicable Standards

The subcontractor shall comply with all local, state and federal standards and adhere to generally accepted engineering standards and principles, and NCCIPS/NASA standards.

2. Period of Performance

The subcontractor shall provide a schedule of the proposed delivery date for each deliverable.

This schedule will be reviewed and approved by SAIC.

The period of performance of this SOW is from the award of the engineering contract through completion of all work as described.

This maintenance contract shall be effective 06/08/2025 through 06/07/2026.

3. Security

United States citizenship is required to gain access into the NASA Stennis Space Center and into the

NCCIPS data center. Proof of citizenship will be required to be presented for on-site work that requires entry into Zone A.

Appendix D – Acronyms and Abbreviations

ACRONYM/ ABBREVIATION DEFINITION

NASA National Aeronautics and Space Administration

NDA Non-Disclosure Agreement

NCCIPS National Center for Critical Information Processing and Storage

SCADA Supervisory Control and Data Acquistion

SOW Statement Of Work

SSC Stennis Space Center

UPS Uninterruptible Power Supply