NATIONAL

PARK

SERVICE

Virgin Islands National Park St. John, Virgin Islands

SCOPE OF WORK

CINNAMON BAY LOOP TRAIL AND CAMPGROUND

GUT CLEARING

PROJECT: Cinnamon Bay Loop Trail and Campground Gut Clearing

In accordance with the terms and conditions of the solicitation, the Contractor shall perform the service described within the scope of work for the National Park Service (NPS) as described below.

All services performed shall be performed in accordance with applicable codes, accepted industry standards.

LOCATION

The project is located at the Virgin Islands National Park, Cinnamon Bay Loop Trail and Campground areas on the island of St. John, USVI.

Address: 1 Great Cinnamon Bay St. John, VI 00803

• Cinnamon Bay Campground gut adjacent to the Cinnamon Bay Sewage Plant towards the open box culverts by bath house 3 to the beach sand berm.

• Cinnamon Bay Loop Trial gut

• Cinnamon Bay Cottage box culverts drainage

DESCRIPTION

This project will remove and dispose of fallen trees, rockslides, and downed debris from the park campgrounds gut in several locations that remain from to Hurricane Irma and Maria. The work is to provide proper drainage to allow storm water to flow away from the campsites and trails.

The unsafe conditions of the blocked guts create a safety hazards to visitors especially when heavy rains flood the roads which channels the water into the gut.

Erosion from the excessive water being forced into the gut happens when the gut is not cleared below the campground elevation which in turn washes out the bare camp sites and trails. This sends sediment and other debris into the bay and damaging resources in and out of the water.

The rehabilitation of the gut will allow park visitors as well as employees to utilize the areas without being exposed to safety hazards. The improvements will allow several hundreds of visitors per day to use the area as well. Natural resources will be protected by eliminating silt and debris from entering the clear waters and settling which would damage protected resources that include but are not limited to the Cinnamon Bay Campgrounds.

THE WORK INCLUDES:

• Removing fallen trees, debris from water gut.

• Removing rockslide dirt and stones from water gut to proper elevation below the campground floor level.

• Removal of excessive rockslide dirt and stones to fill storage area across the street by water plant.

REQUIREMENT

1. Contractor is strongly encouraged to verify measurements and site conditions prior to bid submittals. (site visit will be held)

2. Contractor shall use all safety equipment and procedures; necessary protective equipment and tools to perform work in a safe manner including signage, cones, safety vest, hard hats etc.

3. Contractor shall perform work in a manner that will not cause damage anyone or any property.

4. Contractor shall always keep gate close to prevent any unauthorized pedestrians and vehicles from entering work areas.

5. Contractor shall remove all debris from site.

6. Contractor shall provide a schedule for project prior to beginning work after award and Notice to Proceed are issued.

7. No additional work is to be perform unless a written modification or change order is submitted for review to the staff at Virgin Islands National Park and approved to proceed is given in the form of a modification document by the Contracting Officer to the Contractor.

8. Contractor shall provide all necessary copies of invoice of work performed.

NPS POINTS OF CONTACT

Will be given at time of award.

FEES AND PAYMENT

A. All travel and any other direct or indirect costs for the work performed shall be included in your quote.

B. No legal liability on the part of the Government for any payment that may arise for performance under this contract beyond the amount that has been authorized.

C. Payment will be processed after inspection, acceptance, and approval by the Government that services were performed, and performance was satisfactory.

D. Contractor shall upload all approved invoices in the Invoices Processing Platform System, (IPP) for payment. Payment will only be made through IPP.gov.